Anshul Bhosale Realty

Deedo IDDD-WXY4

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay18 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
DeregisteredKanvas B BuildingDeregistered: Kanvas B BuildingNot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Anshul Kanvas A And E BuildingP52100001023WagholiCertificate Signed30 Apr 201929 Oct 2020+18 mo
Kanvas B BuildingP52100023770WagholiCertificate Signed30 Dec 202730 Dec 2027On date

Anshul Bhosale Realty, in questions

Does Anshul Bhosale Realty finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.

How many projects has Anshul Bhosale Realty registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Anshul Bhosale Realty have MahaRERA regulatory cases?

1 regulatory case name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology