Deedo IDDD-6VZ1Of 7 registrations whose promised date has arrived, 6 kept it (86%). The rest ran a median 7 mo late.
Delivery record
1 of 7 registrations with dates moved or missed their RERA date · months late against the original promise
7 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Joy SquareP51700003827 | Thane (M Corp.) | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Ace SquareP51700009184 | Thane (M Corp.) | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Ace SquareP51700009878 | Thane (M Corp.) | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Metropolis - RIVERAP51700022700 | Thane (M Corp.) | Certificate Signed | 30 Mar 2025 | 30 Mar 2025 | On date |
| Metropolis AquarisP51700022959 | Thane (M Corp.) | Certificate Signed | 30 Sep 2025 | 30 Sep 2025 | On date |
| Metropolis AquarisP51700022961 | Thane (M Corp.) | Certificate Signed | 30 Sep 2024 | 30 Sep 2024 | On date |
| Metropolis - Insignia TowersP51700026750 | Thane (M Corp.) | Certificate Signed | 14 Apr 2026 | 14 Aug 2026 | +7 mo* |
Anant Square, in questions
Does Anant Square finish projects on time?
Of 7 MahaRERA registrations whose promised completion date has arrived, 6 kept it (86%). The rest ran a median 7 mo late. Across Maharashtra, 73% kept their date.
How many projects has Anant Square registered with MahaRERA?
5 projects under 7 MahaRERA registrations; 6 completed on MahaRERA.
Does Anant Square have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.