Amit Builders
Deedo IDDD-6TK5Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 42 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| complaint | Eka Phase III - F BuildingComplaint CC001000000000021 | Not on record |
| complaint | Eka Phase III - F BuildingComplaint CC001000000000075 | Not on record |
| complaint | Eka Phase III - F BuildingComplaint CC001000000040284 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Eka Phase II - E BuildingP51600006366 | Nashik | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Eka Phase III - F BuildingP51600008507 | Nashik | Completed | 31 Dec 2019 | 30 Jun 2023 | +42 mo |
Amit Builders, in questions
Does Amit Builders finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 42 mo late. Across Maharashtra, 73% kept their date.
How many projects has Amit Builders registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Amit Builders have MahaRERA regulatory cases?
3 regulatory cases name its registrations.