Amit Builders

Deedo IDDD-6TK5

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 42 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay42 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases3no insolvency

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Eka Phase II - E BuildingP51600006366NashikCertificate Signed31 Dec 201931 Dec 2019On date
Eka Phase III - F BuildingP51600008507NashikCompleted31 Dec 201930 Jun 2023+42 mo

Amit Builders, in questions

Does Amit Builders finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 42 mo late. Across Maharashtra, 73% kept their date.

How many projects has Amit Builders registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.

Does Amit Builders have MahaRERA regulatory cases?

3 regulatory cases name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology