Amar Associates
Company or firm · 8 projects · 8 MahaRERA registrations
8Projects8 RERA registrations
0Completedas reported on MahaRERA project pages
80%Kept RERA date4 of 5 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| New Tashkent Terrace ChslP51800005598 | Borivali | 2017 | Not reported | 1 Oct 2018 | — | On date |
| Vinay HeritageP51700021080 | Mirabhayandar (M Corp.) | 2019 | Not reported | 30 Dec 2024 | 30 Dec 2025 | +12 months |
| Om Vasudev Chs Ltd.P51800045340 | Borivali | 2022 | Not reported | 31 Mar 2026 | — | On date |
| Shiv Shakti ChslP51800045346 | Borivali | 2022 | Not reported | 31 Mar 2026 | — | On date |
| Parul Kunj Chs Ltd.P51800045372 | Borivali | 2022 | Not reported | 31 Mar 2026 | — | On date |
| Shree Krupa ChslP51800048519 | Borivali | 2023 | Not reported | 31 Dec 2026 | — | On date |
| Vinay Avenue Building No. 16P99000053933 | Khairepada | 2023 | Not reported | 31 Dec 2026 | — | On date |
| Giriraj Mandir Premises Co operative Society LimitedPR1180002600187 | Eksar | 2026 | Not reported | 30 Sep 2029 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Vinay Heritage (P51700021080).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology