Alliance Infrastructure
Deedo IDDD-8Y06Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 13 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Metro City 3P50500021557 | Gotal Panjari | Lapsed | 28 Feb 2025 | — | +21 mo* |
| Metro City 4P50500032537 | Wela Harichandra | Certificate Signed | 1 Dec 2026 | 1 Apr 2027 | +4 mo |
Alliance Infrastructure, in questions
Does Alliance Infrastructure finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 13 mo late. Across Maharashtra, 73% kept their date.
How many projects has Alliance Infrastructure registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Alliance Infrastructure have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.