Akshay Housing
Deedo IDDD-SD0XNone of 2 registrations has reached its promised completion date yet.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Avneesh ImperiumP51800050853 | Mulund | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| AVNEESH IMPERIUM Phase IIP51800077660 | Mumbai Suburban | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
Akshay Housing, in questions
Does Akshay Housing finish projects on time?
None of its 2 MahaRERA registrations has reached its promised completion date yet.
How many projects has Akshay Housing registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Akshay Housing have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.