Certificate Signed

Mulund, Mumbai Suburban 400081 |Promoter: Akshay Housing

Residential / Group HousingRERAP51800050853
9 May 2023Registered with MahaRERA
31 Dec 2027Promised completion
30 Apr 2028Revised completionPushed back 4 months
1Building
274Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
—274 units in all
Address
1111/A, 1111/B, 1102/D/2 & 1112, Mithagar Road, Mulund EastPIN 400081
Designated bank account
76
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.16581, 72.95582
Avneesh Imperium is at latitude 19.16581, longitude 72.95582.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
9 May 2023
Promised
31 Dec 2027
Revised
30 Apr 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P518000508539 May 202331 Dec 202730 Apr 2028Akshay HousingProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Avneesh Imperium A Wing33274

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

274 units registered

— · 274 units
TypeCarpet areaUnits
——274

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 96 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardAkshay Housing Pan Card.pdf · uploaded 5 Apr 2023Source
  • OthersFrom - 3_ MARCH 2025.pdf · uploaded 12 Jun 2025Source
  • DocumentMIRPL_Pan Card.pdf · uploaded 25 Aug 2025Source
  • OthersMIRPL_Incorporation Certificate.pdf · uploaded 25 Aug 2025Source

Legal

  • Declaration Form BAffidavit cum Declartion AH RERA.pdf · uploaded 8 Apr 2023Source
  • Legal Title reportLegal Title Report_Adv_11zon.pdf · uploaded 29 Apr 2023Source

Migrated

  • 1 PAN CardAkshay Housing Pan Card.pdf · uploaded 5 Apr 2023Source
Show all 97 documentsShow fewer documents

Migrated

  • 1 a Details of encumbrances concerned to FinanceEmcumbrance Certificate Legal and Fianace.pdf · uploaded 6 Apr 2023Source
  • 1 b Details of encumbrances concerned to LegalEmcumbrance Certificate Legal and Fianace.pdf · uploaded 6 Apr 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommecement Certificate.pdf · uploaded 6 Apr 2023Source
  • 1 Declaration about Commencement Certificatedeclaration- Commencement Certificate.pdf · uploaded 6 Apr 2023Source
  • 1 CERSAI detailsCersai_Undertaking_2.pdf · uploaded 6 Apr 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentPLAN.pdf · uploaded 8 Apr 2023Source
  • 1 Declaration in FORM BAffidavit cum Declartion AH RERA.pdf · uploaded 8 Apr 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form-1 architech certificate.pdf · uploaded 8 Apr 2023Source
  • 1 Proforma of Allotment letterProforma of Allotment Letter.pdf · uploaded 8 Apr 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsOther Real Estate Orgnisation -Final.pdf · uploaded 10 Apr 2023Source
  • 1 Proforma of Agreement for salemodel Sale Agreement AVNEESH EMPERIUM.pdf · uploaded 10 Apr 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFrom A For Bank Details.pdf · uploaded 10 Apr 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report- Allotment Letter.pdf · uploaded 10 Apr 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report-Agrrement for sale.pdf · uploaded 10 Apr 2023Source
  • 1 Copy of Layout Approval (in case of layout)scan new 1-8 (1)_11zon.pdf · uploaded 20 Apr 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentscan 4-8_11zon.pdf · uploaded 20 Apr 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentscan 6-8_11zon.pdf · uploaded 20 Apr 2023Source
  • 4 Building Plan Approval / NA Order for plotted developmentscan 7-8_11zon.pdf · uploaded 20 Apr 2023Source
  • 5 Building Plan Approval / NA Order for plotted developmentscan 2-8_11zon.pdf · uploaded 20 Apr 2023Source
  • 6 Building Plan Approval / NA Order for plotted developmentscan 8-8_11zon.pdf · uploaded 20 Apr 2023Source
  • 2 a Details of encumbrances concerned to FinanceNo Encumbrances.pdf · uploaded 22 Apr 2023Source
  • 2 b Details of encumbrances concerned to LegalNo Encumbrances.pdf · uploaded 22 Apr 2023Source
  • 1 Other – TechnicalCemencement Certificate Decleration.pdf · uploaded 27 Apr 2023Source
  • 1 Copy of the legal title reportLegal Title Report_Adv_11zon.pdf · uploaded 29 Apr 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 3 May 2023Source
  • 2 Other – Technicaldeclaration.pdf · uploaded 4 May 2023Source
  • 3 Other – Technicalscan 3-8.pdf · uploaded 4 May 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate - AKSHAY HOUSING-Sale_260423.pdf · uploaded 30 May 2023Source
  • 2 Proforma of Agreement for saleAVNEESH REVISED RERA.pdf · uploaded 31 May 2023Source
  • 3 Proforma of Agreement for saleRevised Rera Agreement.pdf · uploaded 29 Jun 2023Source
  • 7 Building Plan Approval / NA Order for plotted developmentAmended Sale Building IOA 1.pdf · uploaded 21 Aug 2023Source
  • 8 Building Plan Approval / NA Order for plotted developmentAmended Sale Building IOA 2.pdf · uploaded 21 Aug 2023Source
  • 9 Building Plan Approval / NA Order for plotted developmentAmended Sale Building IOA 3.pdf · uploaded 21 Aug 2023Source
  • 10 Building Plan Approval / NA Order for plotted developmentAmended Sale Building IOA 4.pdf · uploaded 21 Aug 2023Source
  • 11 Building Plan Approval / NA Order for plotted developmentAmended Sale Building IOA 5.pdf · uploaded 21 Aug 2023Source
  • 12 Building Plan Approval / NA Order for plotted developmentAmended Sale Building IOA 6.pdf · uploaded 21 Aug 2023Source
  • 13 Building Plan Approval / NA Order for plotted developmentAmended Sale Building IOA 7.pdf · uploaded 21 Aug 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Sep 23.pdf · uploaded 8 Feb 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Q4.pdf · uploaded 8 Feb 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Sep 23.pdf · uploaded 8 Feb 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Q4.pdf · uploaded 8 Feb 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Sep 23.pdf · uploaded 8 Feb 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Q4.pdf · uploaded 8 Feb 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentSale Bldg Further CC.pdf · uploaded 17 Apr 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_APRIL-24.pdf · uploaded 23 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_JULY-24.pdf · uploaded 23 Nov 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_NOV-24.pdf · uploaded 23 Nov 2024Source
  • Withdrawal Update Form 1Architect Certificate - June-25_Phase I.pdf · uploaded 30 Jun 2026Source
  • Withdrawal Update Form 1Architect Certificate - Sept-25_Phase I.pdf · uploaded 30 Jun 2026Source
  • Withdrawal Update Form 2Form_2_Ph-I__Jun-25.pdf · uploaded 30 Jun 2026Source
  • Withdrawal Update Form 2Form_2_Ph-I_Sep-25.pdf · uploaded 30 Jun 2026Source
  • Withdrawal Update Form 3From 3 Ph I.pdf · uploaded 30 Jun 2026Source
  • Withdrawal Update Form 3From-3_Ph I_Sep-25.pdf · uploaded 30 Jun 2026Source

Technical

  • DocumentPLAN.pdf · uploaded 8 Apr 2023Source
  • Documentscan 2-8_11zon.pdf · uploaded 20 Apr 2023Source
  • Documentscan 8-8_11zon.pdf · uploaded 20 Apr 2023Source
  • Documentscan 4-8_11zon.pdf · uploaded 20 Apr 2023Source
  • Documentscan 6-8_11zon.pdf · uploaded 20 Apr 2023Source
  • Documentscan 7-8_11zon.pdf · uploaded 20 Apr 2023Source
  • Documentscan new 1-8 (1)_11zon.pdf · uploaded 20 Apr 2023Source
  • Other – TechnicalCemencement Certificate Decleration.pdf · uploaded 27 Apr 2023Source
  • Other – Technicaldeclaration.pdf · uploaded 4 May 2023Source
  • Other – Technicalscan 3-8.pdf · uploaded 4 May 2023Source
  • DocumentAmended Sale Building IOA 1.pdf · uploaded 21 Aug 2023Source
  • DocumentAmended Sale Building IOA 2.pdf · uploaded 21 Aug 2023Source
  • DocumentAmended Sale Building IOA 3.pdf · uploaded 21 Aug 2023Source
  • DocumentAmended Sale Building IOA 4.pdf · uploaded 21 Aug 2023Source
  • DocumentAmended Sale Building IOA 5.pdf · uploaded 21 Aug 2023Source
  • DocumentAmended Sale Building IOA 6.pdf · uploaded 21 Aug 2023Source
  • DocumentAmended Sale Building IOA 7.pdf · uploaded 21 Aug 2023Source
  • Document1.pdf · uploaded 12 Jun 2025Source
  • Document2.pdf · uploaded 12 Jun 2025Source
  • Document3.pdf · uploaded 12 Jun 2025Source
  • Document4.pdf · uploaded 12 Jun 2025Source
  • Document5.pdf · uploaded 12 Jun 2025Source
  • Document6.pdf · uploaded 12 Jun 2025Source
  • Document7.pdf · uploaded 12 Jun 2025Source
  • Document8.pdf · uploaded 12 Jun 2025Source
  • Document9.pdf · uploaded 12 Jun 2025Source
  • Document10.pdf · uploaded 12 Jun 2025Source
  • Document11.pdf · uploaded 12 Jun 2025Source
  • Document12.pdf · uploaded 12 Jun 2025Source
  • Document13.pdf · uploaded 12 Jun 2025Source
  • Document14.pdf · uploaded 12 Jun 2025Source
  • Document15.pdf · uploaded 12 Jun 2025Source
  • OthersFORM - 1_ MARCH 2025.pdf · uploaded 12 Jun 2025Source
  • OthersFrom - 2_ MARCH 2025.pdf · uploaded 12 Jun 2025Source

Technical (Architect)

  • DocumentArchitect Certificate - Sept-25_Phase I.pdf · uploaded 30 Jun 2026Source

Technical (Engineer)

  • DocumentForm_2_Ph-I_Sep-25.pdf · uploaded 30 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Mulund, Kurla taluka

Survey, CTS, gat or plot numbers

1102/D/21111/A1111/B1112

Boundaries

North
1111a
South
1090
East
1113a
West
1102

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDesign Crest—
Chartered accountantJayantkumar V Mehta—
Chartered accountantJ V Mehta & Co—
Chartered accountantNiyati Deepak Mehta—
EngineerBhausaheb Desai—
EngineerDesTech Structural Consultants—
Registered real estate agentPhantom Advisory LLP—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology