Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
The Mpire Phase IIIP52100032906FursungiCertificate Signed31 Dec 202431 Dec 2024On date
The Mpire Building EP52100050878FursungiCertificate Signed31 Dec 202631 Dec 2026On date
The Mpire Building - FP52100077527FursungiCertificate Signed31 Dec 202730 Apr 2028+4 mo

Agn Venture, in questions

Does Agn Venture finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Agn Venture registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does Agn Venture have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.