Aditya Associates
Deedo IDDD-8BBBOf 9 registrations whose promised date has arrived, 4 kept it (44%). The rest ran a median 5 mo late — longer than Maharashtra's 4 mo.
Delivery record
8 of 12 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 12 registrations
12 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Thana Co-Op Housing Society SopanP51700002433 | Thane (M Corp.) | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +24 mo |
| Atmaram SadanP51700011909 | Thane (M Corp.) | Certificate Signed | 31 Mar 2018 | 31 Mar 2018 | On date |
| Laxmi KeshavP51700013705 | Thane (M Corp.) | Certificate Signed | 31 Dec 2019 | 30 Mar 2021 | +15 mo |
| Satyajit Co-Op Housing Society Ltd.P51700024291 | Panchpakhadi | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| SanyogP51700033916 | Naupada | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
| Pankaj Co-Op Housing Society Ltd.P51700034605 | Thane (M Corp.) | Certificate Signed | 10 Sep 2023 | 31 Mar 2024 | +6 mo |
| Madhu Milind Co-Op Housing Society LtdP51700034830 | Naupada | Certificate Signed | 10 Mar 2025 | 10 Mar 2025 | On date |
| HundiwaleP51700046290 | Thane (M Corp.) | Certificate Signed | 16 Sep 2023 | 31 Mar 2024 | +6 mo |
| Phatak WadaP51700049073 | Thane (M Corp.) | Certificate Signed | 15 Oct 2026 | 15 Feb 2027 | +4 mo |
| Rameshwar Co-Op Housing Society Ltd.P51700053476 | Thane (M Corp.) | Certificate Signed | 10 Mar 2027 | 10 Jul 2027 | +4 mo |
| Arvind Co-Op Housing Society LtdP51700079079 | Naupada | Certificate Signed | 8 Jun 2027 | 8 Oct 2027 | +4 mo |
| Deepjyoti Co. Op. Housing SocietyPR1330002500870 | Naupada | Certificate Signed | 31 Jan 2028 | 31 May 2028 | +4 mo |
Show all 12 registrationsShow fewer
Aditya Associates, in questions
Does Aditya Associates finish projects on time?
Of 9 MahaRERA registrations whose promised completion date has arrived, 4 kept it (44%). The rest ran a median 5 mo late. Across Maharashtra, 73% kept their date.
How many projects has Aditya Associates registered with MahaRERA?
12 projects under 12 MahaRERA registrations; 8 completed on MahaRERA.
Does Aditya Associates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.