Adi Developers
Deedo IDDD-DKNMOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late.
Delivery record
3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| GandhakutiP52100016077 | Jalochi | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Adi Imperial AvenueP52100033386 | Jalochi | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
| KasturiP52100076947 | Jalochi | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Adi AnviPM1260002501506 | Jalochi | Certificate Signed | 31 Dec 2031 | 30 Apr 2032 | +4 mo |
Adi Developers, in questions
Does Adi Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Adi Developers registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.
Does Adi Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.