Company or firm · first RERA registration 2017

Acme Sawant Ventures

Deedo IDDD-K03N

Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 5 mo late.

Projects33 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay5 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
AzaleaP52100004621BhilarewadiCertificate Signed30 Sep 201830 Sep 2018On date
ArcadiaP52100013508BhilarewadiCertificate Signed30 Jun 202630 Oct 2026+5 mo*
Azalea BP52100014721BhilarewadiCertificate Signed1 Jan 20191 Jan 2019On date

Acme Sawant Ventures, in questions

Does Acme Sawant Ventures finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 5 mo late. Across Maharashtra, 73% kept their date.

How many projects has Acme Sawant Ventures registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does Acme Sawant Ventures have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology