Acme Housing India Private Limited

Company or firm · 8 projects · 8 MahaRERA registrations

8Projects8 RERA registrations
0Completedas reported on MahaRERA project pages
38%Kept RERA date3 of 8 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 5 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
AlpiniaP51700000778Thane (M Corp.)2017Not reported31 Dec 201930 Dec 2021+24 months
DandeliaP51700001032Thane (M Corp.)2017Not reported31 Dec 2018—On date
Gingelia ResidentialP51700001033Thane (M Corp.)2017Not reported30 Dec 202230 Dec 2023+12 months
HerbeliaP51700001038Thane (M Corp.)2017Not reported30 Dec 202230 Dec 2023+12 months
Oasis - Tower 2P51800001238Borivali2017Not reported31 Dec 201930 Dec 2021+24 months
CentiliaP51700010837Thane (M Corp.)2017Not reported31 Dec 2017—On date
BasiliaP51700010925Thane (M Corp.)2017Not reported31 Dec 2017—On date
Fennelia CommercialP51700025082Thane (M Corp.)2020Not reported30 Dec 202531 Jul 2027+19 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Alpinia+24 mo
  • DandeliaOn date
  • Gingelia Residential+12 mo
  • Herbelia+12 mo
  • Oasis - Tower 2+24 mo
  • CentiliaOn date
  • BasiliaOn date
  • Fennelia Commercial+19 mo

Track record notes

  • 3 of 8 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Alpinia (P51700000778).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology