Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 18 mo late.

Projects44 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay18 mowhen late
First sales on record30registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
FavolosaP52100002469Pune (M Corp.)Certificate Signed31 Mar 201931 Mar 2019On date
Hermes Paras 3P52100025287YerawadaCertificate Signed30 Mar 202430 Mar 2024+32 mo*
ManasiP52100049332KothrudCertificate Signed31 Dec 202531 Dec 2025On date
Niti ApartmentP52100080956Pune (M Corp.)Certificate Signed31 Mar 202831 Jul 2028+4 mo

Abhilasha Developers, in questions

Does Abhilasha Developers finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.

How many projects has Abhilasha Developers registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.

Does Abhilasha Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology