Abhilasha Developers
Deedo IDDD-07Q5Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 29 mo late.
Delivery record
4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sai VatikaP52100022735 | Chandkhed | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +35 mo* |
| Sai Vatika - ParijatP52100030300 | Chandkhed | Certificate Signed | 31 Dec 2022 | 31 Dec 2023 | +47 mo* |
| Sai Vatika - JuiP52100047197 | Chandkhed | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +23 mo* |
| Sai VatikaP52100052605 | Chandkhed | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Abhilasha Developers, in questions
Does Abhilasha Developers finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 29 mo late. Across Maharashtra, 73% kept their date.
How many projects has Abhilasha Developers registered with MahaRERA?
3 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.
Does Abhilasha Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.