Company or firm · first RERA registration 2019

Abhilasha Developers

Deedo IDDD-07Q5

Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 29 mo late.

Projects34 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay29 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sai VatikaP52100022735ChandkhedCertificate Signed30 Dec 202330 Dec 2023+35 mo*
Sai Vatika - ParijatP52100030300ChandkhedCertificate Signed31 Dec 202231 Dec 2023+47 mo*
Sai Vatika - JuiP52100047197ChandkhedCertificate Signed31 Dec 202431 Dec 2024+23 mo*
Sai VatikaP52100052605ChandkhedCertificate Signed31 Dec 202630 Apr 2027+4 mo

Abhilasha Developers, in questions

Does Abhilasha Developers finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 29 mo late. Across Maharashtra, 73% kept their date.

How many projects has Abhilasha Developers registered with MahaRERA?

3 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.

Does Abhilasha Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology