Infinity Builders & Developers · Bokadvira
Delivery
Status10 mo late
Promised → actualDec 2025 → still open
Developer kept RERA dates100%2 of 2 due · Infinity Builders And Developers
Extension certificates1
Size & sales
Units booked37 / 45 · 82%
Buildings · land1 · 850 m²
Registration
RERA numbers
Status on MahaRERACertificate Signed
Registered on31 Dec 2020
Regulatory
MahaRERA cases0
Documents on file1
Last checked on MahaRERA13 Oct 2026

✓ marks the best value only where “best” is unambiguous. Prices are not ranked; medians need at least 3 registered deeds. 2 BHK is the flat size as declared to MahaRERA, for deeds matched to a flat.