Skip to content
Residential / Group Housing · 2 buildings · 53 unitsRERA P50300011855

Raj Township

Deedo IDDP-AMR-24E0

MahaRERA shows it completed, after its date was pushed back 1 year and 6 months; no MahaRERA orders on record; 100% of its units are booked.

Badnera, Amravati 444601 · by Raj Associates

DeliveryCompletedAs MahaRERA shows · after a 1 yr 6 mo extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked53 of 53 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 1 year and 6 months

  • This projectRegistered 31 Aug 2017, completion promised 31 Aug 2019, revised to 28 Feb 2021.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP50300011855
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030001185531 Aug 201731 Aug 201928 Feb 2021Raj AssociatesProject page
Documents79

40 documents held by Deedo, 39 filings listed on MahaRERA's project page

Encumbrance details

Form 1 (7)

Show all 79 documentsShow fewer documents

Allotment letter (2)

Other (7)

Title report

Form B

Registration certificate

Form 5 (6)

Extension certificate

Form 2 (5)

Form 2A (4)

Occupancy / completion certificate

  • Occupancy / completion certificate11 Jun 2024ViewSource

Form 4

Layout plan

Building plan

Document library

  • Proforma of Allotment letterLETTER OF ALLOTMENT.pdf · uploaded 31 Jul 2017View
  • Details of encumbrancesNEC.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)PLAN_opt.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ar n engg certificate.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ar n engg certificate.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)SANCTION PLAN_opt.pdf · uploaded 31 Jul 2017View
  • OtherOTHER.pdf · uploaded 31 Jul 2017View
  • Copy of the legal title reporttitle reportopt.pdf · uploaded 27 Aug 2017View
  • Declaration in FORM Bpromoterform b.pdf · uploaded 27 Aug 2017View
  • Proforma of Allotment letterSale Deed_Format_Raj Township_Feb_2018.pdf · uploaded 22 May 2018View
  • Certificates of CA (Form 5)FORM 5 RAJ ASSOCIATES.pdf · uploaded 30 Sep 2018View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5 ANNUAL REPORT DIAMOND.pdf · uploaded 31 Dec 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Raj Form 5 1920.pdf · uploaded 11 Jun 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Raj Form 5 2021.pdf · uploaded 11 Jun 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Raj Form 5 2122.pdf · uploaded 11 Jun 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Raj Form 5 2223.pdf · uploaded 11 Jun 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A - Engineer Raj Township 1920.pdf · uploaded 11 Jun 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A - Engineer Raj Township 2021.pdf · uploaded 11 Jun 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A - Engineer Raj Township 2122.pdf · uploaded 11 Jun 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A - Engineer Raj Township 2223.pdf · uploaded 11 Jun 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Architect Raj Associates OC Date.pdf · uploaded 11 Jun 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Architect Raj Associates Q1.pdf · uploaded 11 Jun 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Architect Raj Associates Q2.pdf · uploaded 11 Jun 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Architect Raj Associates Q3.pdf · uploaded 11 Jun 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Architect Raj Associates Q4.pdf · uploaded 11 Jun 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Architect Raj Associates Q1 24.pdf · uploaded 11 Jun 2024View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Engineer Raj Township OC Date.pdf · uploaded 11 Jun 2024View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Engineer Raj Township Q1.pdf · uploaded 11 Jun 2024View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Engineer Raj Township Q3.pdf · uploaded 11 Jun 2024View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Engineer Raj Township Q4.pdf · uploaded 11 Jun 2024View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Engineer Raj Township Q1 24.pdf · uploaded 11 Jun 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentDiamond Full OC.pdf · uploaded 11 Jun 2024View
  • Architect’s Certificate on Completion of Project (Form 4)Form 4 Raj Township.pdf · uploaded 11 Jun 2024View
  • Disclosure of sold/ booked inventoryInventory Disclosure - Promoter Letterhead RAJ Township OC DATE.pdf · uploaded 13 Jun 2024View

Promoter documents

  • Legal Title reporttitle reportopt.pdf · uploaded 27 Aug 2017View
  • Declaration Form Bpromoterform b.pdf · uploaded 27 Aug 2017View

Technical documents

  • Layout ApprovalPLAN_opt.pdfView
  • Building Plan ApprovalSANCTION PLAN_opt.pdfView

Proforma allotment letter

  • Proforma allotment letterSale Deed_Format_Raj Township_Feb_2018.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 159/1, 159/2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Address
159/1, 159/2, 160, 162, 164/2 PartPIN 444601
Village
Badnera, Amravati taluka
Land area for this project
7,040 sq m (75,778 sq ft)
Permissible built-up area
46,690 sq m (5,02,566 sq ft)
Sanctioned built-up area
7,040 sq m (75,778 sq ft)
Recreational open space
1,869 sq m (20,118 sq ft)
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

159/1159/2160162164/2 PART

Land as published on MahaRERA's project page

159/1, 159/2, 160, 162, 164/2 PART

Boundaries

North
Khasra No 157 And 158
South
Khasra No163
East
Badnera Amravati Bypass Road
West
Part Of 161 And 163

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking1 parking space

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00001

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress2 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Diamond

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Common areas and amenities

  • Internal Roads & FootpathsWork Completed100%
  • Water SupplyWork Completed100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Work Completed100%
  • Storm Water DrainsWork Completed100%
  • Landscaping & Tree PlantingWork Completed100%
  • Street LightingWork Completed100%
Show all 15 activitiesShow fewer activities
  • Community BuildingsWork Completed100%
  • Treatment And Disposal Of Sewage And Sullage WaterWork Completed100%
  • Solid Waste Management And DisposalWork Completed100%
  • Water conservation /Rain water harvestingWork Completed100%
  • Energy managemcntWork Completed100%
  • Fire protection and fire safety requirementsWork Completed100%
  • Electrical meter room, sub-station, receiving stationWork Completed100%
  • Aggregate area of recreational Open SpaceCOMPLETED100%
  • Open ParkingWork Completed100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals20

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPradnya Sanjay Nagpure—
ArchitectPradnya Sanjay Nagpure—
ArchitectPradnya Sanjay Nagpure—
ArchitectPradnya Sanjay Nagpure—
ArchitectSanjay K Nagpure—
ArchitectSanjay K Nagpure—
ArchitectSanjay K Nagpure—
ArchitectSanjay K Nagpure—
Show all 20 professionalsShow fewer professionals
RoleNameRegistration no.
EngineerHg Iche—
EngineerHg Iche—
EngineerHg Iche—
EngineerHg Iche—
OtherHuzaifa S Sanawadwala—
OtherHuzaifa S Sanawadwala—
OtherHuzaifa S Sanawadwala—
OtherHuzaifa S Sanawadwala—
OtherYunus Ibrahim Ali—
OtherYunus Ibrahim Ali—
OtherYunus Ibrahim Ali—
OtherYunus Ibrahim Ali—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology