Rui, Ahmednagar

Deedo IDDL-AHM-RUI

10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects3
Registrations6some projects hold several
Completion still due06 past their date
Median extensionNot on record0% of registrations extended
Regulatory cases5on 2 projects

10 in 10 registrations run late here

6 MahaRERA registrations in Rui

6 past even the latest date

Projects in Rui

3 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Sai Hermitage Shirdi - By Ananta Block - 7Harihar Infraventure (India) Private Limited2 yrs 11 mo late——
Sai Hermitage Shirdi By AnantaHarihar Infraventure (India) Private Limited2 yrs 10 mo late——
Sai PrasadSoham PropertiesCompleted—17%
Rui market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Harihar Infraventure (India) Private Limited2 projects
  2. Soham Properties1 project

Rui, in questions

How many projects in Rui run late?

10 in 10 MahaRERA registrations (6 of 6): their completion date was extended or has passed, data through 7 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Rui by Deedo. Medians on fewer than 3 deeds are not shown.

Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology