Skip to content
Deedo home
Menu

Sunder Town

Completed

Chitoda, Wardha 442001 |Promoter: Asif Hussain, Sushil Dhote, Surendra Chamat, Sudhakar Chamlate, Ravindra Ekapure, & Gopichand Mate

22 Mar 2024Registered with MahaRERA
31 Dec 2025Promised completion
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Completed
Land area for this project
11,977 sq m (1,28,924 sq ft)
Permissible built-up area
0 sq m (0 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Recreational open space
2,106 sq m (22,672 sq ft)
Address
Survey No 37, Chitoda, ChitodaPIN 442001
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Sunder Town is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2025

The latest completion date on record passed 10 months ago.

Registered
22 Mar 2024
Promised
31 Dec 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5040005541522 Mar 202431 Dec 2025—Asif Hussain, Sushil Dhote, Surendra Chamat, Sudhakar Chamlate, Ravindra Ekapure, & Gopichand MateProject page

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Building

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Common areas and amenities

  • Internal Roads & FootpathsKHADIKARAN ROAD100%
  • Water SupplyNot applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Storm Water DrainsNALI100%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingELECTRIC POLE100%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

17 documents held by Deedo, 84 filings listed on MahaRERA's project page

Others

Encumbrances

Registration certificate

Completions

Form 2

Form 1

Allotment letter

Document library

  • Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 18 Dec 2023Source
  • Building Plan Approval / NA Order for plotted developmentNA.pdf · uploaded 18 Dec 2023Source
  • Commencement Certificates / NA Order for plotted developmentNA.pdf · uploaded 18 Dec 2023Source
  • Copy of the legal title reportLegal Title.pdf · uploaded 5 Jan 2024Source
  • a Details of encumbrances concerned to FinanceEncumbrance Cert.pdf · uploaded 5 Jan 2024Source
  • b Details of encumbrances concerned to LegalEncumbrance Cert.pdf · uploaded 5 Jan 2024Source
  • a Details of encumbrances concerned to FinanceLegal Encumbrance Certificate.pdf · uploaded 5 Jan 2024Source
  • b Details of encumbrances concerned to LegalLegal Encumbrance Certificate.pdf · uploaded 5 Jan 2024Source
  • Disclosure of sold/ booked inventoryDisclosure of Inventory_compressed.pdf · uploaded 5 Jan 2024Source
  • Disclosure of Interest in Other Real Estate OrganizationsDiscl of interest Mr Gopichand Mate.pdf · uploaded 5 Jan 2024Source
  • Disclosure of Interest in Other Real Estate OrganizationsDiscl of interest Mr Ravindra Ekapure.pdf · uploaded 5 Jan 2024Source
  • Disclosure of Interest in Other Real Estate OrganizationsDiscl of interest Mr Sdhakar Chamlate.pdf · uploaded 5 Jan 2024Source
  • Disclosure of Interest in Other Real Estate OrganizationsDiscl of interest Mr Surendra Chamat.pdf · uploaded 5 Jan 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsDiscl of interest Mr Sushil Dhote.pdf · uploaded 5 Jan 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsDiscl Of Int Mr Asif Hussain.pdf · uploaded 5 Jan 2024View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 5 Jan 2024View
  • Other – TechnicalClarification.pdf · uploaded 5 Jan 2024Source
  • Deviation Report with respect to Allotment letterDeviation - Allotment20240103_12293653.pdf · uploaded 5 Jan 2024Source
  • Deviation Report with respect to model copy of AgreementDeviation - Agreement20240103_12242406.pdf · uploaded 5 Jan 2024Source
  • Declaration in FORM BForm B.pdf · uploaded 11 Jan 2024Source
  • Proforma of Agreement for saleAgreement to sale.pdf · uploaded 12 Jan 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 13 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 13 Jan 2024View
  • Other – LegalSaledeed-others.pdf · uploaded 6 Feb 2024Source
  • Other – Legalsaledeed-Asif hussain.pdf · uploaded 6 Feb 2024Source
  • Other – TechnicalAnnexure A-other technical.pdf · uploaded 7 Feb 2024Source
  • Declaration about Commencement CertificateFORMAT D (1).pdf · uploaded 7 Feb 2024Source
  • Other – FinanceSelfdeclarationfornonformation-otherFinance.pdf · uploaded 7 Feb 2024Source
  • a Details of encumbrances concerned to FinanceFinancialencumbrances.pdf · uploaded 7 Feb 2024Source
  • b Details of encumbrances concerned to LegalFinancialencumbrances.pdf · uploaded 7 Feb 2024Source
  • CERSAI detailsCersai Declaration.pdf · uploaded 7 Feb 2024Source
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 7 Feb 2024View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration Bank.pdf · uploaded 7 Feb 2024View
  • Other – TechnicalOrder No- 50.pdf · uploaded 8 Mar 2024Source
  • Commencement Certificates / NA Order for plotted developmentRevised CC Verification- Sunder Town.pdf · uploaded 8 Mar 2024Source
  • Other – TechnicalRevised CC Verification- Sunder Town.pdf · uploaded 8 Mar 2024Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFORM 4.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFORM 4.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFORM 4.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFORM 4.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFORM 4.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFORM 4.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFORM 4.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFORM 4.pdf · uploaded 6 Oct 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 6 Oct 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 6 Oct 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 6 Oct 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 6 Oct 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 6 Oct 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 6 Oct 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 6 Oct 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentProof of mailcompletion.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentProof of mailcompletion.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentProof of mailcompletion.pdf · uploaded 6 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentProof of mailcompletion.pdf · uploaded 6 Oct 2024View
  • Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 4 Dec 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 4 Dec 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 4 Dec 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 4 Dec 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 4 Dec 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 4 Dec 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 4 Dec 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 6 Dec 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 6 Dec 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 6 Dec 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 6 Dec 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION.pdf · uploaded 6 Dec 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 6 Dec 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION.pdf · uploaded 6 Dec 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 6 Dec 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION.pdf · uploaded 6 Dec 2024View

Promoter documents

  • Legal Title reportLegal Title.pdf · uploaded 5 Jan 2024Source
  • Declaration Form BForm B.pdf · uploaded 11 Jan 2024Source

Technical documents

  • Layout ApprovalLayout.pdfSource
  • NA Order for Plotted DevelopmentNA.pdfSource

Other legal documents

  • Other – LegalSaledeed-others.pdfSource
  • Other – Legalsaledeed-Asif hussain.pdfSource

Financial documents

  • Other – FinanceSelfdeclarationfornonformation-otherFinance.pdf · uploaded 7 Feb 2024Source

Proforma allotment letter

  • Proforma allotment letterAllotment Letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Chitoda, Wardha taluka

Survey, CTS, gat or plot numbers

37SURVEY NO 37

As published on MahaRERA's project page

SURVEY NO 37

Boundaries

North
Survey No 41
South
Nalla
East
Survey No 38
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAnand Tangirala—
Chartered accountantJ. Chandak & Co.—
Chartered accountantPrateek Kishor Harkutiya—
EngineerAnand Tangirala—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology