Sun View Heights
Deedo IDDP-THN-5B8VCompletion was pushed back 4 months, to Jan 2029; no MahaRERA orders on record; 0% of its units are booked.
Vashi, Thane 400703 · by Sun View Homes LLP
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Jan 2029
- This projectRegistered 20 Aug 2024, completion promised 30 Sep 2028, revised to 30 Jan 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700077509
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700077509 | 20 Aug 2024 | 30 Sep 2028 | 30 Jan 2029 | Sun View Homes LLP | Project page |
Documents88
1 document held by Deedo, 87 filings listed on MahaRERA's project page
Finance
- PAN CardLLP PAN.pdf · uploaded 29 May 2024Source
Legal
Migrated
- 1 PAN CardLLP PAN.pdf · uploaded 29 May 2024Source
- 1 a Details of encumbrances concerned to FinanceSelf Declaration About Encumbrances Concerned to Finance.pdf · uploaded 29 May 2024Source
- 1 b Details of encumbrances concerned to LegalSelf Declaration About Encumbrances Concerned to Finance.pdf · uploaded 29 May 2024Source
- 1 Copy of Layout Approval (in case of layout)plan highlight_compressed.pdf · uploaded 29 May 2024Source
Show all 88 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentPAGE NO 3CC DRAWING_compressed.pdf · uploaded 29 May 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentPAGE NO 4 CC DRAWING_compressed.pdf · uploaded 29 May 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentPAGE NO5 CC DRAWING_compressed.pdf · uploaded 29 May 2024Source
- 4 Building Plan Approval / NA Order for plotted developmentPAGE NO6 CC DRAWING_compressed.pdf · uploaded 29 May 2024Source
- 5 Building Plan Approval / NA Order for plotted developmentPAGE NO7 CC DRAWING_compressed.pdf · uploaded 29 May 2024Source
- 6 Building Plan Approval / NA Order for plotted developmentPAGE NO8 CC DRAWING_compressed.pdf · uploaded 29 May 2024Source
- 7 Building Plan Approval / NA Order for plotted developmentPAGE NO9 CC DRAWING_compressed.pdf · uploaded 29 May 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCC final highlighted.pdf · uploaded 29 May 2024Source
- 1 Declaration about Commencement CertificateDeclaration About Commencement Certificate Format-D SIGNED COPY (1).pdf · uploaded 29 May 2024Source
- 1 Declaration in FORM BForm B Affidavit cum Declaration (Company) (1).pdf · uploaded 29 May 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architects Certificate.pdf · uploaded 29 May 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sunview engineer cert finalcompressed (1).pdf · uploaded 29 May 2024Source
- 1 CERSAI detailsUndertaking About cersai Certificate Order 26-2021- MahaRERA.pdf · uploaded 29 May 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Desclosure of Interest in other Real Estate Organizations-1.pdf · uploaded 29 May 2024Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Desclosure of Interest in other Real Estate Organizations-2.pdf · uploaded 29 May 2024Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Desclosure of Interest in other Real Estate Organizations-3.pdf · uploaded 29 May 2024Source
- 1 Proforma of Allotment letterFinal Allotment Letter Draft.pdf · uploaded 29 May 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Bank Account for Real Estate Project.pdf · uploaded 29 May 2024Source
- 1 Deviation Report with respect to Allotment letterNo Deviation from Allotment Letter.pdf · uploaded 29 May 2024Source
- 1 Other – TechnicalAnnexure A Declaration Cum Undertaking.pdf · uploaded 29 May 2024Source
- 1 Copy of the legal title reportFINAL TITLE REPORT.pdf · uploaded 22 Jun 2024Source
- 2 a Details of encumbrances concerned to FinanceTo Whomsoever It May Concern.pdf · uploaded 10 Jul 2024Source
- 2 b Details of encumbrances concerned to LegalTo Whomsoever It May Concern.pdf · uploaded 10 Jul 2024Source
- 1 Proforma of Agreement for saleAFS Sun View reviewed.pdf · uploaded 10 Jul 2024Source
- 1 Deviation Report with respect to model copy of AgreementRevised Deviation report AFS 22_06 signed.pdf · uploaded 10 Jul 2024Source
- 1 Other – LegalIndex 2 copy.pdf · uploaded 10 Jul 2024Source
- 2 Other – LegalMAHARERA Clarification.pdf · uploaded 10 Jul 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Signed.pdf · uploaded 12 Aug 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 15 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.PDF · uploaded 16 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Sunview.pdf · uploaded 5 Nov 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Signed(Final).pdf · uploaded 5 Nov 2024Source
- 1 a Details of encumbrances concerned to FinanceEncumbrance Certificate.pdf · uploaded 19 Dec 2024Source
- 1 CERSAI detailsCERSAI Signed.pdf · uploaded 19 Dec 2024Source
- 1 b Details of encumbrances concerned to LegalEncumbrance Certificate.pdf · uploaded 19 Dec 2024Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure for Secured Finance.pdf · uploaded 19 Dec 2024Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD DISCLOSURE - Sep 24 Signed (1).pdf · uploaded 4 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Dec 24.PDF · uploaded 15 Jan 2025Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 22 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Dec 24.pdf · uploaded 22 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Signed_compressed.pdf · uploaded 22 Jan 2025Source
- 1 Proforma of Agreement for saleAFS Sun View reviewed[1].pdf · uploaded 22 Jan 2025Source
- 2 Disclosure of sold/ booked inventorySold Booked - Dec 24.pdf · uploaded 23 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)mar 25.pdf · uploaded 8 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 19 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 19 Apr 2025Source
- 1 Disclosure of sold/ booked inventorySold Booked Mar-25.pdf · uploaded 22 Apr 2025Source
- Withdrawal Update Form 1Form 1 Architectu0027s Certificate.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 2Form 2 Engineeru0027s Certificate.PDF · uploaded 19 Jul 2025Source
- Withdrawal Update Form 3Form 3 (Sunview Heights - 30-06-2025).pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 1Form 1 Architectu0027s Certificate.pdf · uploaded 18 Sep 2025Source
- Withdrawal Update Form 2Form 2 Engineeru0027s Certificate.PDF · uploaded 18 Sep 2025Source
- Withdrawal Update Form 3Form 3 Sunview Heights_30-06-2025.pdf · uploaded 18 Sep 2025Source
- Form 5 (FY 2024-2025)Form 5_Sun View Heights_Signed_FY 2024-25.pdf · uploaded 7 Oct 2025Source
- Withdrawal Update Form 1Form 1 Architectu0027s Certificate.pdf · uploaded 18 Oct 2025Source
- Withdrawal Update Form 2From 2 Engineeru0027s Certificate.pdf · uploaded 18 Oct 2025Source
- Withdrawal Update Form 3Withdrawal Application Form3.pdf · uploaded 18 Oct 2025Source
- Withdrawal Update Form 1Form 1 Architectu0027s Certificate.pdf · uploaded 25 Dec 2025Source
- Withdrawal Update Form 2From 2 Engineeru0027s Certificate.pdf · uploaded 25 Dec 2025Source
- Withdrawal Update Form 3Form 3 sunview updated.pdf · uploaded 25 Dec 2025Source
- Form 2A (FY 2024-2025)FORM 2A 24-25.PDF · uploaded 30 Dec 2025Source
- Withdrawal Update Form 1FORM 1 - Q3 signed stamped.PDF · uploaded 14 Feb 2026Source
- Withdrawal Update Form 2FORM 2 - Q3 signed stamped.pdf · uploaded 14 Feb 2026Source
- Withdrawal Update Form 3FORM 3 - Q3 signed stamped.pdf · uploaded 14 Feb 2026Source
- Withdrawal Update Form 1FORM 1 - MARCH 2026.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2FORM 2 - MARCH 2026.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3FORM 3 - MARCH 2026 final.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 1FORM 1 - JUNE 2026.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 2FORM 2 - JUNE 2026.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 3FORM 3 - JUNE 2026.pdf · uploaded 17 Jul 2026Source
- Form 2A (FY 2025-2026)FORM 2A - FY 25-26.PDF · uploaded 12 Sep 2026Source
- Form 5 (FY 2025-2026)FORM 5 - FY 25-26.pdf · uploaded 29 Sep 2026Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel PLOT NO 14 CONDOMINIUM NO 14 SECTOR 09
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK Sale, 3BHK Sale, F5 3BHK Rehab Unit, F5 Shop Rehab, F5 Shop Rehab unit, F5 Shop Rehab Unit, Office space sale, Office Space Sale, Shop sale, Shop Sale, SSU Shop Rehab Unit86 units in all
- Address
- Plot No 14 Condominium No 14 Sector 09, Sector 9 Vashi, VashiPIN 400703
- Village
- Navi Mumbai (M Corp.), Thane taluka
- Location
- 19.07845, 72.99781
- Land area for this project
- 2,033 sq m (21,886 sq ft)
- Permissible built-up area
- 8,555 sq m (92,083 sq ft)
- Sanctioned built-up area
- 8,555 sq m (92,083 sq ft)
- Recreational open space
- 781 sq m (8,406 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PLOT NO 14 CONDOMINIUM NO 14 SECTOR 09
Boundaries
- North
- F 3 Building
- South
- Plot No 16 And 6 Meters Road
- East
- F 4 Building
- West
- Open Ground And Plot No 4
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking86 units
0 of 86 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK Sale | 67.72 sq m · 729 sq ft | 40 | 0 |
| 3BHK Sale | 95.41 sq m · 1,027 sq ft | 8 | 0 |
| F5 3BHK Rehab Unit | 88.48 sq m · 952 sq ft | 12 | 0 |
| F5 Shop Rehab | 47.07 sq m · 507 sq ft | 1 | 0 |
| F5 Shop Rehab unit | 26.63 sq m · 287 sq ft | 1 | 0 |
| F5 Shop Rehab unit | 53.68 sq m · 578 sq ft | 2 | 0 |
| F5 Shop Rehab Unit | 46.91 sq m · 505 sq ft | 1 | 0 |
| F5 Shop Rehab Unit | 46.92 sq m · 505 sq ft | 2 | 0 |
Show all 22 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| F5 Shop Rehab Unit | 53.7 sq m · 578 sq ft | 1 | 0 |
| Office space sale | 35.22 sq m · 379 sq ft | 1 | 0 |
| Office space sale | 47.41 sq m · 510 sq ft | 2 | 0 |
| Office space sale | 57.52 sq m · 619 sq ft | 1 | 0 |
| Office space sale | 58.98 sq m · 635 sq ft | 1 | 0 |
| Office Space Sale | 100.09 sq m · 1,077 sq ft | 1 | 0 |
| Shop sale | 20.4 sq m · 220 sq ft | 1 | 0 |
| Shop sale | 38.97 sq m · 419 sq ft | 1 | 0 |
| Shop sale | 59.98 sq m · 646 sq ft | 1 | 0 |
| Shop Sale | 41.44 sq m · 446 sq ft | 1 | 0 |
| Shop Sale | 58.87 sq m · 634 sq ft | 1 | 0 |
| SSU Shop Rehab Unit | 18.28 sq m · 197 sq ft | 2 | 0 |
| SSU Shop Rehab Unit | 36.7 sq m · 395 sq ft | 2 | 0 |
| SSU Shop Rehab Unit | 36.79 sq m · 396 sq ft | 3 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals6
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Dimensions Architects Pvt Ltd | — |
| Chartered accountant | CA Rishabh Lodaya | — |
| Chartered accountant | J B Patel And Associates | — |
| Engineer | Anand Kumar Gupta | — |
| Engineer | Structural Concept Designs Private Limited | — |
| Other | Reraone | — |
Source: MahaRERA project page. Contact details are not shown.