Skip to content
Residential / Group Housing · 1 building · 14 unitsRERA P51700047948

Millano Heights

Deedo IDDP-THN-3FAA

MahaRERA shows it completed, after its date was pushed back 1 year; no MahaRERA orders on record; 14% of its units are booked.

Ulhasnagar (M Corp.), Thane 421004 · by Chimnani Constructions

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 1 yr extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales14% booked2 of 14 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 1 year

  • This projectRegistered 1 Dec 2022, completion promised 31 Dec 2024, revised to 30 Dec 2025.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700047948
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000479481 Dec 202231 Dec 202430 Dec 2025Chimnani ConstructionsProject page
Documents69

2 documents held by Deedo, 67 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN 2.pdf · uploaded 7 Oct 2022Source

Legal

  • Legal Title reporttitle report.pdf · uploaded 7 Oct 2022Source
  • Legal Title reportsearch report.pdf · uploaded 7 Oct 2022Source
  • Declaration Form BForm B.pdf · uploaded 7 Oct 2022Source
  • Other – LegalJustification signed.pdf · uploaded 30 Jan 2025Source
  • Declaration Form BForm B Signed.pdf · uploaded 30 Jan 2025Source
Show all 69 documentsShow fewer documents

Legal

  • Declaration Form BForm B New.pdf · uploaded 20 Mar 2025Source

Migrated

  • 1 PAN CardPAN 2.pdf · uploaded 7 Oct 2022Source
  • 1 Copy of the legal title reporttitle report.pdf · uploaded 7 Oct 2022Source
  • 2 Copy of the legal title reportsearch report.pdf · uploaded 7 Oct 2022Source
  • 1 a Details of encumbrances concerned to FinanceEncumbernace Certificate.pdf · uploaded 7 Oct 2022Source
  • 1 b Details of encumbrances concerned to Legallegal.pdf · uploaded 7 Oct 2022Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT AND BUILDING.pdf · uploaded 7 Oct 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentLAYOUT AND BUILDING.pdf · uploaded 7 Oct 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC (1).pdf · uploaded 7 Oct 2022Source
  • 1 Declaration about Commencement CertificateComencement Declaration.pdf · uploaded 7 Oct 2022Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 7 Oct 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 7 Oct 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 7 Oct 2022Source
  • 1 Deviation Report with respect to Allotment letterDeclaration of no changes.pdf · uploaded 7 Oct 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeclaration of no changes.pdf · uploaded 7 Oct 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200249140372_For_Asset_Based_Search_08_10_2022_15_17_37_448.pdf · uploaded 8 Oct 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Letter (2).pdf · uploaded 15 Oct 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 22 Oct 2022Source
  • 1 Proforma of Allotment letterAlottment Letter Chimnani.pdf · uploaded 16 Nov 2022Source
  • 1 Proforma of Agreement for saleAgreement For Sale.pdf · uploaded 21 Nov 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Chinmai const CA Cert.pdf · uploaded 7 Aug 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 12 Aug 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 12 Aug 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Chimnani Const.pdf · uploaded 26 Nov 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Milano Heights Form 1 Ar cert (Bunty Chimnani).pdf · uploaded 2 Feb 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Milano Heights Form 2 Engg cert (Bunty Chimnani).pdf · uploaded 2 Feb 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Ca Cerificate.pdf · uploaded 2 Feb 2024Source
  • 1 Disclosure of sold/ booked inventorySold unsold.pdf · uploaded 12 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Chimnani construction (1).pdf · uploaded 31 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 17 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 17 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 17 Nov 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 17 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 17 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 17 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1.pdf · uploaded 29 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3.pdf · uploaded 29 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2.pdf · uploaded 29 Jan 2025Source
  • 1 Declaration in FORM BForm B Signed.pdf · uploaded 30 Jan 2025Source
  • 1 Other – LegalJustification signed.pdf · uploaded 30 Jan 2025Source
  • 1 Disclosure of sold/ booked inventorysold unsold signed.pdf · uploaded 30 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 30 Jan 2025Source
  • 1 Declaration in FORM BForm B New.pdf · uploaded 20 Mar 2025Source
  • 1 Other – TechnicalPert Chart.pdf · uploaded 20 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1 ARCHITECT CERT.pdf · uploaded 20 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)chimnani Form 3.pdf · uploaded 20 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2 ENGINEER CERT.pdf · uploaded 20 Apr 2025Source
  • Occupational CertificateOc Chimnani.pdf · uploaded 16 Jun 2025Source

Technical

  • DocumentLAYOUT AND BUILDING.pdf · uploaded 7 Oct 2022Source
  • DocumentLAYOUT AND BUILDING.pdf · uploaded 7 Oct 2022Source
  • Other – TechnicalPert Chart.pdf · uploaded 20 Mar 2025Source

Technical (Architect)

  • DocumentMilano Heights Form 1 Ar cert (Bunty Chimnani).pdf · uploaded 2 Feb 2024Source
  • DocumentForm 1.pdf · uploaded 17 Nov 2024Source
  • DocumentForm 1.pdf · uploaded 17 Nov 2024Source
  • DocumentFORM -1.pdf · uploaded 29 Jan 2025Source
  • DocumentFORM -1 ARCHITECT CERT.pdf · uploaded 20 Apr 2025Source

Technical (Engineer)

  • DocumentMilano Heights Form 2 Engg cert (Bunty Chimnani).pdf · uploaded 2 Feb 2024Source
  • DocumentForm 2.pdf · uploaded 17 Nov 2024Source
  • DocumentForm 2.pdf · uploaded 17 Nov 2024Source
  • DocumentFORM -2.pdf · uploaded 29 Jan 2025Source
  • DocumentFORM -2 ENGINEER CERT.pdf · uploaded 20 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel CD HOLD LAND OF ROOM NO 1095, CTS NO 21142

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—14 units in all
Address
Cd Hold Land Of Room No 1095, Cts No 21142, Ulhasnagar, UlhasnagarPIN 421004
Village
Ulhasnagar (M Corp.), Ulhasnagar taluka
Land area for this project
209 sq m (2,250 sq ft)
Permissible built-up area
752 sq m (8,096 sq ft)
Sanctioned built-up area
752 sq m (8,096 sq ft)
Designated bank account
220
Developed in phases
No

Survey, CTS, gat or plot numbers

CD HOLD LAND OF ROOM NO 1095CTS NO 21142

Land as published on MahaRERA's project page

CD HOLD LAND OF ROOM NO 1095, CTS NO 21142

Boundaries

North
Building
South
Building
East
Building
West
Building

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking14 units

14 units registered

— · 14 units
TypeCarpet areaUnits
——14

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals7

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectBhushan G Rupani—
ArchitectRavindra Pawar—
Chartered accountantGirish S Tarwani—
Chartered accountantVinesh Ahuja—
EngineerBhushan G Rupan—
EngineerRavindra Pawar—
OtherSunil N Patil—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology