The Nilaya
Deedo IDDP-THN-JFG5It is due for completion in Dec 2027, with no extension on record; no MahaRERA orders on record; 22% of its units are booked.
Titwala, Thane 421605 · by Abhidarshan Corporation Llp
Buying a flat here?
See every deed registered on it.
It is due for completion in Dec 2027, with no extension on record
- This projectRegistered 5 Apr 2024, completion promised 31 Dec 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- Building (P51700055643)Size not on record8% booked
- MHADA15 floors18% booked
- Tower 358% built26 floors39% booked
Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700055643
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700055643 | 5 Apr 2024 | 31 Dec 2027 | — | Abhidarshan Corporation LLP | Project page |
Documents176
74 documents held by Deedo, 102 filings listed on MahaRERA's project page
Encumbrance details (2)
Commencement certificate (3)
Show all 176 documentsShow fewer documents
Other (29)
- Other17 Mar 2024ViewSource
- Other17 Mar 2024ViewSource
- Other17 Mar 2024ViewSource
- Other17 Mar 2024ViewSource
- Other17 Mar 2024ViewSource
- Other17 Mar 2024ViewSource
- Other17 Mar 2024ViewSource
- Other17 Mar 2024ViewSource
- Other17 Mar 2024ViewSource
- Other20 Mar 2024ViewSource
- Other31 Mar 2024ViewSource
- Other31 Mar 2024ViewSource
- Other1 Apr 2024ViewSource
- Other31 May 2024ViewSource
- Other29 Jul 2024ViewSource
- Other16 Oct 2024ViewSource
- Other29 Oct 2024ViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
Form 1 (11)
- Form 129 Jul 2024ViewSource
- Form 116 Oct 2024ViewSource
- Form 128 Oct 2024ViewSource
- Form 115 Jan 2025ViewSource
- Form 115 Jan 2025ViewSource
- Form 115 Jan 2025ViewSource
- Form 118 Feb 2025ViewSource
- Form 13 May 2025ViewSource
- Form 112 Mar 2026ViewSource
- Form 124 Jun 2026ViewSource
- Form 120 Aug 2026ViewSource
Form 2 (8)
Building plan (14)
- Building planDate not statedViewSource
- Building planDate not statedViewSource
- Building planDate not statedViewSource
- Building planDate not statedViewSource
- Building planDate not statedViewSource
- Building planDate not statedViewSource
- Building planDate not statedViewSource
- Building planDate not statedViewSource
- Building planDate not statedViewSource
- Building planDate not statedViewSource
- Building planDate not statedViewSource
- Building planDate not statedViewSource
- Building planDate not statedViewSource
- Building planDate not statedViewSource
Document library
- Copy of the legal title report20240307 Title Report for MAHARERA_0001.pdf · uploaded 17 Mar 2024View
- a Details of encumbrances concerned to Financeilovepdf_merged (6).pdf · uploaded 17 Mar 2024View
- b Details of encumbrances concerned to Legalilovepdf_merged (6).pdf · uploaded 17 Mar 2024View
- Commencement Certificates / NA Order for plotted developmentCommencement Letter updated.pdf · uploaded 17 Mar 2024View
- CERSAI detailsCERSAI.pdf · uploaded 17 Mar 2024View
- Disclosure of Interest in Other Real Estate OrganizationsAnnexure - A of all partners-1.pdf · uploaded 17 Mar 2024View
- Disclosure of Interest in Other Real Estate OrganizationsAnnexure - A of all partners-2.pdf · uploaded 17 Mar 2024View
- Disclosure of Interest in Other Real Estate OrganizationsAnnexure - A of all partners-3.pdf · uploaded 17 Mar 2024View
- Disclosure of Interest in Other Real Estate OrganizationsAnnexure - A of all partners-4.pdf · uploaded 17 Mar 2024View
- Disclosure of Interest in Other Real Estate OrganizationsAnnexure - A of all partners-5.pdf · uploaded 17 Mar 2024View
- Disclosure of Interest in Other Real Estate OrganizationsAnnexure - A of all partners-6.pdf · uploaded 17 Mar 2024View
- Disclosure of Interest in Other Real Estate OrganizationsAnnexure - A of all partners-7.pdf · uploaded 17 Mar 2024View
- Disclosure of Interest in Other Real Estate OrganizationsAnnexure - A of all partners-8.pdf · uploaded 17 Mar 2024View
- Disclosure of Interest in Other Real Estate OrganizationsAnnexure - A of all partners-9.pdf · uploaded 17 Mar 2024View
- Disclosure of Interest in Other Real Estate OrganizationsAnnexure - A of all partners-10.pdf · uploaded 17 Mar 2024View
- Declaration in FORM BFORM B (7).pdf · uploaded 18 Mar 2024View
- Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameseparate bank account updated abhi (1)-1.pdf · uploaded 19 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentPodium Plan Sheet No 2.PDF · uploaded 20 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentPodium Plan Sheet No 3.PDF · uploaded 20 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentPodium Plan Sheet No 4.PDF · uploaded 20 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentPodium Plan Sheet No 5.PDF · uploaded 20 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentPodium Plan Sheet No 5.PDF · uploaded 20 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentPodium Plan Sheet No 6.PDF · uploaded 20 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentBasement Plan Sheet No 7.PDF · uploaded 20 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentTower-1 (A,B,C) Sheet No 8.PDF · uploaded 20 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentTower-1 (A,B,C) Sheet No 9.PDF · uploaded 20 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentTower 10 plans.pdf · uploaded 20 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentTower-1 (A,B,C) Sheet No 11.PDF · uploaded 20 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentTower-3 Sheet No 16.PDF · uploaded 20 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentTower-3 Sheet No 17.PDF · uploaded 20 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentTower-3 Sheet No 18.PDF · uploaded 20 Mar 2024View
- Deviation Report with respect to Allotment letterDeviation Report respect to Allotment Let (1).pdf · uploaded 20 Mar 2024View
- Deviation Report with respect to model copy of AgreementDeviation Report_0001 (1)_compressed (1).pdf · uploaded 20 Mar 2024View
- Proforma of Allotment letter1 Proforma of Allotment letter (4) (1).pdf · uploaded 20 Mar 2024View
- Declaration about Commencement CertificateSCAN COPY OF RERA DOCS (1)-6 (1).pdf · uploaded 20 Mar 2024View
- Copy of Layout Approval (in case of layout)Layout (6) (1).pdf · uploaded 20 Mar 2024View
- Commencement Certificates / NA Order for plotted development20240305 CC Revalidation Letter.pdf · uploaded 20 Mar 2024View
- Other – TechnicalAnnexure - A.pdf · uploaded 31 Mar 2024View
- Other – TechnicalLayout_compressed (1).pdf · uploaded 31 Mar 2024View
- Proforma of Agreement for saleAgreement for SALE -RERA (2).pdf · uploaded 1 Apr 2024View
- Other – LegalIndex II of S No 194.pdf · uploaded 1 Apr 2024View
- Other – LegalIndex II of S No 197 2 1.pdf · uploaded 1 Apr 2024View
- Other – LegalIndex II of S No 197 2 2.pdf · uploaded 1 Apr 2024View
- Other – LegalIndex II of S No 197 2 3.pdf · uploaded 1 Apr 2024View
- Other – LegalIndex II of S No 228 1B.pdf · uploaded 1 Apr 2024View
- Other – LegalIndex II of S No 164 195.pdf · uploaded 1 Apr 2024View
- Deviation Report with respect to model copy of AgreementDeviation Report (22-5-24) (1).pdf · uploaded 31 May 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)the nilaya Architects Form-1.pdf · uploaded 29 Jul 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Rera Form 2 -the nilaya.pdf · uploaded 29 Jul 2024View
- Disclosure of sold/ booked inventoryDsclosure of sold the nilaya.pdf · uploaded 29 Jul 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)The Nilaya - RERA Progress Report.pdf · uploaded 16 Oct 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Rera Form 2 - Abhidarshan June 2024.pdf · uploaded 16 Oct 2024View
- Disclosure of sold/ booked inventorySold Unsold inventry_0001 (3).pdf · uploaded 16 Oct 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Form 1.pdf · uploaded 28 Oct 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)From 2.pdf · uploaded 28 Oct 2024View
- Disclosure of sold/ booked inventoryDisclosure of Sold unsold inventry_0001.pdf · uploaded 29 Oct 2024View
- Copy of Layout Approval (in case of layout)Layout_1-compressed.pdf · uploaded 29 Oct 2024View
- Building Plan Approval / NA Order for plotted developmentMhada Tower (2).pdf · uploaded 5 Nov 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Form 1 certificate Mar-24 THE NILAYA.pdf · uploaded 15 Jan 2025View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Form 1 certificate Jun-24 THE NILAYA.pdf · uploaded 15 Jan 2025View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Form 1 certificate Sept-24 THE NILAYA.pdf · uploaded 15 Jan 2025View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Engineer’s Certificate on Cost Incurred on Project (Form 2) THE NILYA.pdf · uploaded 15 Jan 2025Source
- Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Engineer’s Certificate on Cost Incurred on Project (Form 2) THE NILAYA.pdf · uploaded 15 Jan 2025Source
- Engineer’s Certificate on Cost Incurred on Project (Form 2)3 Engineer’s Certificate on Cost Incurred on Project (Form 2) THE NILAYA.pdf · uploaded 15 Jan 2025Source
- Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 18 Feb 2025View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 18 Feb 2025View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_compressed.pdf · uploaded 3 May 2025View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 3 May 2025View
- Withdrawal Update Form 1Form 1.pdf · uploaded 12 Mar 2026View
- Withdrawal Update Form 2Rera Form 2 - Abhidarsha - June 2025.pdf · uploaded 12 Mar 2026View
- Withdrawal Update Form 1Form-1 Q2.pdf · uploaded 12 Mar 2026View
- Withdrawal Update Form 2Rera Form 2 - Abhidarsha - Sep 2025.pdf · uploaded 12 Mar 2026View
- Withdrawal Update Form 1FORM 1.pdf · uploaded 24 Jun 2026View
- Withdrawal Update Form 2Rera Form 2 - Abhidarsha - Dec 2025.pdf · uploaded 24 Jun 2026View
- Withdrawal Update Form 1FORM 1 - Mar-26.pdf · uploaded 20 Aug 2026View
- Withdrawal Update Form 2Rera Form 2 - March 2026.pdf · uploaded 20 Aug 2026View
Promoter documents
Technical documents
- Building Plan ApprovalTower-1 (A,B,C) Sheet No 11.PDFView
- Layout ApprovalLayout (6) (1).pdfView
- Building Plan ApprovalTower-3 Sheet No 16.PDFView
- Building Plan ApprovalTower-3 Sheet No 17.PDFView
- Building Plan ApprovalTower-3 Sheet No 18.PDFView
- Building Plan ApprovalPodium Plan Sheet No 2.PDFView
- Building Plan ApprovalPodium Plan Sheet No 3.PDFView
- Building Plan ApprovalPodium Plan Sheet No 4.PDFView
- Building Plan ApprovalPodium Plan Sheet No 5.PDFView
- Building Plan ApprovalPodium Plan Sheet No 5.PDFView
- Building Plan ApprovalPodium Plan Sheet No 6.PDFView
- Building Plan ApprovalBasement Plan Sheet No 7.PDFView
- Building Plan ApprovalTower-1 (A,B,C) Sheet No 8.PDFView
- Building Plan ApprovalTower-1 (A,B,C) Sheet No 9.PDFView
- Building Plan ApprovalTower 10 plans.pdfView
- Layout ApprovalLayout_1-compressed.pdfView
- Building Plan ApprovalMhada Tower (2).pdfView
Other legal documents
Proforma allotment letter
- Proforma allotment letter1 Proforma of Allotment letter (4) (1).pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 194, 197 · Kalyan-Dombivli Municipal Corporation
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Active
- Address
- Survey No. 164, 194, 197, Hissa No. 2A, 2B, 2C, Survey No. 228, Hissa No. 1/B, Opposite Abhidarshan Garden Near Ganesh Nagar Society Mayuresh Nagar, TitwalaPIN 421605
- Village
- Titwala, Kalyan taluka
- Location
- 19.29400, 73.21509
- Land area for this project
- 642 sq m (6,913 sq ft)
- Permissible built-up area
- 9,054 sq m (97,457 sq ft)
- Sanctioned built-up area
- 9,054 sq m (97,457 sq ft)
- Recreational open space
- 1,475 sq m (15,873 sq ft)
- Planning authority
- Kalyan-Dombivli Municipal Corporation
- Designated bank account
- State Bank Of India
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Survey No. 164, 194,197, Hissa No. 2A, 2B, 2C, Survey No. 228, Hissa No. 1/B
Boundaries
- North
- Survey no 228 1 2
- South
- Survey no 197 2 3
- East
- Survey no 197 2 1
- West
- Survey no 164
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking242 parking spaces
0 units registered
Parking
| Building | Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|---|
| MHADA | Closed/Covered | 0 | 0 | 0 | 0 | 1 |
| MHADA | Open Space | 94 | 0 | 0 | 0 | 94 |
| Tower 3 | Closed/Covered | 0 | 0 | 0 | 0 | 37 |
| Tower 3 | Open Space | 73 | 37 | 0 | 0 | 110 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress3 buildings and areas
Work completed, as the promoter reported it to MahaRERA (Form 1)
MHADA
Show all 11 activitiesShow fewer activities
Tower 3
Show all 11 activitiesShow fewer activities
Common areas and amenities
Show all 15 activitiesShow fewer activities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sobhana Despande | — |
| Chartered accountant | Mamta N Kholiya | — |
| Chartered accountant | Urvi Devansh Rangani | — |
| Engineer | Vishal Raghwani | — |
Source: MahaRERA project page. Contact details are not shown.