Anand Home
Deedo IDDP-THN-S383Completion was pushed back 1 year to Mar 2026, and that date has passed too; no MahaRERA orders on record; 87% of its units are booked.
Titwala, Thane 421605 · by Morya Group
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 year to Mar 2026, and that date has passed too
- This projectRegistered 28 Apr 2022, completion promised 31 Mar 2025, revised to 31 Mar 2026, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700034768
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700034768 | 28 Apr 2022 | 31 Mar 2025 | 31 Mar 2026 | M/s. MORYA GROUP | Project page |
Documents164
2 documents held by Deedo, 162 filings listed on MahaRERA's project page
Finance
- PAN Cardmorya group pan card.pdf · uploaded 5 Apr 2022Source
Legal
- Legal Title reportTITLE CERTIFICATE AS PER FORMAT_REV 2_compressed.pdf · uploaded 13 Apr 2022Source
- Declaration Form BFORM B REV 2_compressed.pdf · uploaded 19 Apr 2022Source
- Declaration Form BPOWER OF ATTORNEY_compressed.pdf · uploaded 19 Apr 2022Source
- Declaration Form BFORM B LANDOWNERS_compressed.pdf · uploaded 23 Apr 2022Source
- Declaration Form BForm B.pdf · uploaded 26 May 2025Source
Show all 164 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesdetails of encumbrance undertaking.pdf · uploaded 31 Mar 2022Source
- 2 Details of encumbrancestitwala search report.pdf · uploaded 31 Mar 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentNA ORDER_compressed.pdf · uploaded 31 Mar 2022Source
- 1 Commencement Certificates / NA Order for plotted developmenttitwala cc_compressed.pdf · uploaded 31 Mar 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA Architect Letter FORM 1_compressed.pdf · uploaded 31 Mar 2022Source
- 1 CERSAI detailscersai undertaking.pdf · uploaded 31 Mar 2022Source
- 1 Proforma of Allotment letterproforma of allotment letter_compressed.pdf · uploaded 31 Mar 2022Source
- 2 Proforma of Allotment letterAGREEMNT-DRAFT.pdf · uploaded 31 Mar 2022Source
- 1 PAN Cardmorya group pan card.pdf · uploaded 5 Apr 2022Source
- 1 Declaration about Commencement CertificateCC DECLATARION REV 02.pdf · uploaded 10 Apr 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 REV 2_compressed.pdf · uploaded 10 Apr 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 REV 2_compressed.pdf · uploaded 10 Apr 2022Source
- 1 Copy of the legal title reportTITLE CERTIFICATE AS PER FORMAT_REV 2_compressed.pdf · uploaded 13 Apr 2022Source
- 1 Copy of Layout Approval (in case of layout)01.pdf · uploaded 13 Apr 2022Source
- 2 Copy of Layout Approval (in case of layout)02.pdf · uploaded 13 Apr 2022Source
- 3 Copy of Layout Approval (in case of layout)03.pdf · uploaded 13 Apr 2022Source
- 4 Copy of Layout Approval (in case of layout)04.pdf · uploaded 13 Apr 2022Source
- 1 Declaration in FORM BFORM B REV 2_compressed.pdf · uploaded 19 Apr 2022Source
- 2 Declaration in FORM BPOWER OF ATTORNEY_compressed.pdf · uploaded 19 Apr 2022Source
- 3 Declaration in FORM BFORM B LANDOWNERS_compressed.pdf · uploaded 23 Apr 2022Source
- 3 Details of encumbrancesencumbrance letter RERA.pdf · uploaded 28 Mar 2023Source
- 4 a Details of encumbrances concerned to Financeencumbrance letter RERA.pdf · uploaded 28 Mar 2023Source
- 1 b Details of encumbrances concerned to Legalencumbrance letter RERA.pdf · uploaded 28 Mar 2023Source
- 1 Proforma of Agreement for saleDraft Agreement for sale FINAL.pdf · uploaded 28 Mar 2023Source
- 1 a Details of encumbrances concerned to FinanceABFL encumbrance phs 1.pdf · uploaded 8 Oct 2024Source
- 1 b Details of encumbrances concerned to LegalABFL encumbrance phs 1.pdf · uploaded 8 Oct 2024Source
- 1 a Details of encumbrances concerned to FinanceABFL encumbrance phs 1.pdf · uploaded 8 Oct 2024Source
- 1 b Details of encumbrances concerned to LegalABFL encumbrance phs 1.pdf · uploaded 8 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_March 23.pdf · uploaded 7 Feb 2025Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Dec 24.pdf · uploaded 7 Feb 2025Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Sep 24.pdf · uploaded 7 Feb 2025Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_June 24.pdf · uploaded 7 Feb 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_March 24.pdf · uploaded 7 Feb 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Dec 23.pdf · uploaded 7 Feb 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Sep 23.pdf · uploaded 7 Feb 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_June 23.pdf · uploaded 7 Feb 2025Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Dec 24.pdf · uploaded 7 Feb 2025Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Sep 24.pdf · uploaded 7 Feb 2025Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Jun 24.pdf · uploaded 7 Feb 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Dec 23.pdf · uploaded 7 Feb 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Sep 23.pdf · uploaded 7 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Jun 23.pdf · uploaded 7 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Mar 23.pdf · uploaded 7 Feb 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Mar 24.pdf · uploaded 7 Feb 2025Source
- 6 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - June 24.pdf · uploaded 7 Feb 2025Source
- 5 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - March 24.pdf · uploaded 7 Feb 2025Source
- 4 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - Dec 23.pdf · uploaded 7 Feb 2025Source
- 3 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - Sep 23.pdf · uploaded 7 Feb 2025Source
- 2 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - June 23.pdf · uploaded 7 Feb 2025Source
- 1 Disclosure of sold/ booked inventory1 Disclosure of Sold Booked Inventory - Mar 23.pdf · uploaded 7 Feb 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Mar 23.pdf · uploaded 7 Feb 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Mar 24.pdf · uploaded 7 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_March 2023.pdf · uploaded 10 Feb 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_June 2023.pdf · uploaded 10 Feb 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Sep 2023.pdf · uploaded 10 Feb 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Dec 2023.pdf · uploaded 10 Feb 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_March 2024.pdf · uploaded 10 Feb 2025Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_June 2024.pdf · uploaded 10 Feb 2025Source
- 7 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - Sep 24.pdf · uploaded 10 Feb 2025Source
- 8 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - Dec 24.pdf · uploaded 10 Feb 2025Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Sep 2024.pdf · uploaded 11 Feb 2025Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Dec 2024.pdf · uploaded 11 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA Audit Report_22-23.pdf · uploaded 11 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)RERA Audit Report_23-24.pdf · uploaded 11 Feb 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)format a anand homes phase 2.pdf · uploaded 13 Feb 2025Source
- 2 Declaration about all RERA Designated Bank Accounts (Format A)format a anand home.pdf · uploaded 13 Feb 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)format b anand home.pdf · uploaded 13 Feb 2025Source
- 1 Other – TechnicalPER-CRM.pdf · uploaded 23 Apr 2025Source
- 2 Other – TechnicalForm 2A.pdf · uploaded 23 Apr 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsOther Real Estates_compressed.pdf · uploaded 23 Apr 2025Source
- 1 Disclosure for secured/unsecured finance availed for the projectdisclosure of finance phs 1 anand home.pdf · uploaded 23 Apr 2025Source
- 1 Declaration in FORM BForm B.pdf · uploaded 26 May 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate - Mar 25.pdf · uploaded 5 Jun 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Mar-25-Phase-1.pdf · uploaded 5 Jun 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Mar 25.pdf · uploaded 5 Jun 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - Mar 25.pdf · uploaded 5 Jun 2025Source
- Form 1Form 1_Dec 24.pdf · uploaded 3 Sep 2025Source
- Form 2Engineer Certificate - Dec 24.pdf · uploaded 3 Sep 2025Source
- Form 3CA Certificate_Dec 24.pdf · uploaded 3 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory - Dec 24.pdf · uploaded 3 Sep 2025Source
- Form 1Form 1_Sep 24.pdf · uploaded 3 Sep 2025Source
- Form 2Engineer Certificate - Sep 24.pdf · uploaded 3 Sep 2025Source
- Form 3CA Certificate_Sep 2024.pdf · uploaded 3 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory - Sep 24.pdf · uploaded 3 Sep 2025Source
- Form 1Form 1_June 24.pdf · uploaded 3 Sep 2025Source
- Form 2Engineer Certificate - Jun 24.pdf · uploaded 3 Sep 2025Source
- Form 3CA Certificate_June 2024.pdf · uploaded 3 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory - June 24.pdf · uploaded 3 Sep 2025Source
- Form 1Form 1_March 24.pdf · uploaded 3 Sep 2025Source
- Form 2Engineer Certificate - Mar 24.pdf · uploaded 3 Sep 2025Source
- Form 3CA Certificate_March 2024.pdf · uploaded 3 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory - March 24.pdf · uploaded 3 Sep 2025Source
- Form 1Form 1_Dec 23.pdf · uploaded 3 Sep 2025Source
- Form 2Engineer Certificate - Dec 23.pdf · uploaded 3 Sep 2025Source
- Form 3CA Certificate_Dec 2023.pdf · uploaded 3 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory - Dec 23.pdf · uploaded 3 Sep 2025Source
- Form 1Form 1_Sep 23.pdf · uploaded 3 Sep 2025Source
- Form 2Engineer Certificate - Sep 23.pdf · uploaded 3 Sep 2025Source
- Form 3CA Certificate_Sep 2023.pdf · uploaded 3 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory - Sep 23.pdf · uploaded 3 Sep 2025Source
- Form 1Form 1_June 23.pdf · uploaded 3 Sep 2025Source
- Form 2Engineer Certificate - Jun 23.pdf · uploaded 3 Sep 2025Source
- Form 3CA Certificate_June 2023.pdf · uploaded 3 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory - June 23.pdf · uploaded 3 Sep 2025Source
- Form 1Form 1_March 23.pdf · uploaded 3 Sep 2025Source
- Form 2Engineer Certificate - Mar 23.pdf · uploaded 3 Sep 2025Source
- Form 3CA Certificate_March 2023.pdf · uploaded 3 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory - March 23.pdf · uploaded 3 Sep 2025Source
- Form 1Form 1_March 25.pdf · uploaded 3 Sep 2025Source
- Form 2Engineer Certificate - Mar 25.pdf · uploaded 3 Sep 2025Source
- Form 3CA Certificate_Mar-25-Phase-1.pdf · uploaded 3 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory - March 25.pdf · uploaded 3 Sep 2025Source
- Form 1Form 1.pdf · uploaded 3 Sep 2025Source
- Form 2Form 2.pdf · uploaded 3 Sep 2025Source
- Form 3Form 3.pdf · uploaded 3 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 3 Sep 2025Source
- Form 1Form 1.pdf · uploaded 3 Sep 2025Source
- Form 2Form 2.pdf · uploaded 3 Sep 2025Source
- Form 3Form 3.pdf · uploaded 3 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 3 Sep 2025Source
- Form 1Form 1.pdf · uploaded 3 Sep 2025Source
- Form 2Form 2.pdf · uploaded 3 Sep 2025Source
- Form 3Form 3.pdf · uploaded 3 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 3 Sep 2025Source
- Withdrawal Update Form 1Form 1_June 25.pdf · uploaded 3 Sep 2025Source
- Withdrawal Update Form 2Form 2_June 25.pdf · uploaded 3 Sep 2025Source
- Withdrawal Update Form 3Form 3_June 25.pdf · uploaded 3 Sep 2025Source
- Withdrawal Update Form 1Architect Certificate Phase 1 Sep 25.pdf · uploaded 1 Apr 2026Source
- Withdrawal Update Form 1Architect Certificate Phase 1 Dec 25.pdf · uploaded 1 Apr 2026Source
- Withdrawal Update Form 2Engineer Certificate Phase 1 Sep 25.pdf · uploaded 1 Apr 2026Source
- Withdrawal Update Form 2Engineer Certificate Phase 1 Dec 25.pdf · uploaded 1 Apr 2026Source
- Withdrawal Update Form 3CA Certificate_Sep-25-Phase-1.pdf · uploaded 1 Apr 2026Source
- Withdrawal Update Form 3CA Cerificate_Dec 25.pdf · uploaded 1 Apr 2026Source
- Withdrawal Update Form 1Form 1_Mar 26.pdf · uploaded 13 Jun 2026Source
- Withdrawal Update Form 2Form 2_Mar 26.pdf · uploaded 13 Jun 2026Source
- Withdrawal Update Form 3Form 3_Mar 26.pdf · uploaded 13 Jun 2026Source
- Withdrawal Update Form 1Form 1_Jun 26.pdf · uploaded 23 Sep 2026Source
- Withdrawal Update Form 2Form 2_Jun 26.pdf · uploaded 23 Sep 2026Source
- Withdrawal Update Form 3CA Certificate_Jun-26.pdf · uploaded 23 Sep 2026Source
Technical
- DocumentNA ORDER_compressed.pdf · uploaded 31 Mar 2022Source
- Document01.pdf · uploaded 13 Apr 2022Source
- Document02.pdf · uploaded 13 Apr 2022Source
- Document03.pdf · uploaded 13 Apr 2022Source
- Document04.pdf · uploaded 13 Apr 2022Source
- Other – TechnicalPER-CRM.pdf · uploaded 23 Apr 2025Source
- Other – TechnicalForm 2A.pdf · uploaded 23 Apr 2025Source
Technical (Engineer)
- DocumentEngineer Certificate - Mar 23.pdf · uploaded 7 Feb 2025Source
- DocumentEngineer Certificate - Jun 23.pdf · uploaded 7 Feb 2025Source
- DocumentEngineer Certificate - Sep 23.pdf · uploaded 7 Feb 2025Source
- DocumentEngineer Certificate - Dec 23.pdf · uploaded 7 Feb 2025Source
- DocumentEngineer Certificate - Mar 24.pdf · uploaded 7 Feb 2025Source
- DocumentEngineer Certificate - Jun 24.pdf · uploaded 7 Feb 2025Source
- DocumentEngineer Certificate - Sep 24.pdf · uploaded 7 Feb 2025Source
- DocumentEngineer Certificate - Dec 24.pdf · uploaded 7 Feb 2025Source
- DocumentEngineer Certificate - Mar 25.pdf · uploaded 5 Jun 2025Source
- DocumentForm 2_Jun 26.pdf · uploaded 23 Sep 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 78/1, 79
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK128 units in all
- Address
- 78/1 & 79, Mhaskal Road, Behind Ganesh Vidya MandirPIN 421605
- Village
- Titwala, Kalyan taluka
- Location
- 19.30088, 73.22196
- Land area for this project
- 4,917 sq m (52,925 sq ft)
- Permissible built-up area
- 4,917 sq m (52,925 sq ft)
- Sanctioned built-up area
- 4,917 sq m (52,925 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 85
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
78/1 & 79
Boundaries
- North
- 80
- South
- 78-2
- East
- 77
- West
- 79
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking128 units
111 of 128 units booked (87%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Wing F | 1BHK | 29.63 sq m · 319 sq ft | 54 | 45 |
| Wing F | 2BHK | 36.89 sq m · 397 sq ft | 8 | 7 |
| Wing G | 1BHK | 29.63 sq m · 319 sq ft | 58 | 52 |
| Wing G | 2BHK | 36.89 sq m · 397 sq ft | 8 | 7 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vijay R Pandey | — |
| Chartered accountant | Rajesh Raikar | — |
| Engineer | Omkar V Joshi | — |
Source: MahaRERA project page. Contact details are not shown.