M M Valley C1
Deedo IDDP-THN-N86AMahaRERA shows it completed; no MahaRERA orders on record; 95% of its units are booked.
Thane, Maharashtra 400612 · by Alfa Enterprises · 100% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 22 Aug 2017, completion promised 31 Dec 2018.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
6 buildings
Open a building to see every flat, floor by floor.
- 160eSize not on record100% booked
- 1sSize not on record0% booked
- A-1 (MM _Vatlley - Premium)Size not on record52% booked
- Cony.Size not on record0% booked
- Main building17 floors · 116 units95% booked
- N06Size not on record0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700009447
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700009447 | 22 Aug 2017 | 31 Dec 2018 | 31 Dec 2018 | Alfa Enterprises | Project page |
Documents61
2 documents held by Deedo, 59 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN CardPAN.pdf · uploaded 30 Jul 2017Source
Legal
- Legal Title reportTITLE CERTIFICATE_Compressed.pdf · uploaded 30 Jul 2017Source
- OtherBANK ACC A2-C1.pdf · uploaded 31 Jul 2017Source
- Declaration Form BFORM B MM Valley C1_Compressed.pdf · uploaded 31 Jul 2017Source
- Otherdeclaration C1.pdf · uploaded 1 Nov 2017Source
- Declaration Form BFORM - B C1.pdf · uploaded 4 Dec 2017Source
Show all 61 documentsShow fewer documents
Legal
- OtherDEED OF ADMISSION Alfa.pdf · uploaded 6 Dec 2017Source
Migrated
- 1 PAN CardPAN.pdf · uploaded 30 Jul 2017Source
- 1 Copy of the legal title reportTITLE CERTIFICATE_Compressed.pdf · uploaded 30 Jul 2017Source
- 1 Details of encumbrancesENCUMBRANCS-C1.pdf · uploaded 30 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)_6 C1.pdf · uploaded 30 Jul 2017Source
- 2 Copy of Layout Approval (in case of layout)_10 C1.pdf · uploaded 30 Jul 2017Source
- 3 Copy of Layout Approval (in case of layout)_11 C1.pdf · uploaded 30 Jul 2017Source
- 1 Building Plan Approval (IOD)IOA.pdf · uploaded 30 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 30 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1-C1.pdf · uploaded 30 Jul 2017Source
- 1 Proforma of Allotment letterDECLARATION - AGREEMENT C1.pdf · uploaded 30 Jul 2017Source
- 1 Declaration in FORM BFORM B MM Valley C1_Compressed.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER'S CERTIFICATE_Compressed.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of CA (Form 3)FORM 3 -C1.pdf · uploaded 31 Jul 2017Source
- 1 OtherBANK ACC A2-C1.pdf · uploaded 31 Jul 2017Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM-1.pdf · uploaded 1 Nov 2017Source
- 2 Otherdeclaration C1.pdf · uploaded 1 Nov 2017Source
- 2 Details of encumbrancesENCUMBRANCES LETTER.pdf · uploaded 4 Dec 2017Source
- 2 Declaration in FORM BFORM - B C1.pdf · uploaded 4 Dec 2017Source
- 3 OtherDEED OF ADMISSION Alfa.pdf · uploaded 6 Dec 2017Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM - 1.pdf · uploaded 31 Jan 2018Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2.pdf · uploaded 31 Jan 2018Source
- 2 Certificates of CA (Form 3)FORM-3.pdf · uploaded 31 Jan 2018Source
- 2 Proforma of Allotment letterAgeement C 1.pdf · uploaded 31 Jan 2018Source
- 3 Proforma of Allotment letterAllotment Letter Mumbra C1.pdf · uploaded 31 Jan 2018Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Valley LetteR Formation.pdf · uploaded 6 Apr 2018Source
- 2 Status of Formation of Legal Entity (Society/Co Op etc.)Valley Society Letter sent by Courier.pdf · uploaded 6 Apr 2018Source
- 3 Status of Formation of Legal Entity (Society/Co Op etc.)Valley List of attend meeting UPLOAD.pdf · uploaded 6 Apr 2018Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM-1.pdf · uploaded 21 Apr 2018Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2.pdf · uploaded 21 Apr 2018Source
- 3 Certificates of CA (Form 3)FORM-3.pdf · uploaded 21 Apr 2018Source
- 4 Certificates of CA (Form 3)FORM-3(1).pdf · uploaded 22 Apr 2018Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM-1.pdf · uploaded 6 Aug 2018Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2.pdf · uploaded 6 Aug 2018Source
- 5 Certificates of CA (Form 3)FORM-3.pdf · uploaded 6 Aug 2018Source
- 1 Certificates of CA (Form 5)C1 RERA Certificate.pdf · uploaded 30 Sep 2018Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM-1.pdf · uploaded 30 Oct 2018Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FOMR-3.pdf · uploaded 30 Oct 2018Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2.pdf · uploaded 30 Oct 2018Source
- 6 Certificates of CA (Form 3)FOMR-3.pdf · uploaded 30 Oct 2018Source
- 1 Certificates of Architect (Form 4)FORM-4.pdf · uploaded 3 Nov 2018Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM-1.pdf · uploaded 25 Jan 2019Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2.pdf · uploaded 25 Jan 2019Source
- 7 Certificates of CA (Form 3)FORM 3.pdf · uploaded 25 Jan 2019Source
- 2 Certificates of CA (Form 5)A2 RERA Certificate-2019_Compressed.pdf · uploaded 29 Oct 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Scan.pdf · uploaded 30 Oct 2019Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD 31082021.pdf · uploaded 15 Sep 2022View
Technical
Technical (Architect)
- DocumentFORM-1.pdf · uploaded 25 Jan 2019Source
Technical (Engineer)
- DocumentFORM-2.pdf · uploaded 25 Jan 2019Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 55
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1 BHK116 units in all
- Address
- 55, 56, 57 P, Thane, ThanePIN 400612
- Location
- 19.16563, 73.03221
- Land area for this project
- 2,323 sq m (25,000 sq ft)
- Permissible built-up area
- 4,598 sq m (49,495 sq ft)
- Sanctioned built-up area
- 4,598 sq m (49,495 sq ft)
- Recreational open space
- 239 sq m (2,575 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
55,56,57 P
Boundaries
- North
- S No 54
- South
- S No 58
- East
- Sonkhar Boundary
- West
- S No 59
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking116 units
110 of 116 units booked (95%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 34.98 sq m · 377 sq ft | 56 | 54 |
| 1 BHK | 37.26 sq m · 401 sq ft | 60 | 56 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Joshi Deshaware & Associates | — |
| Engineer | Associated Consultants | — |
Source: MahaRERA project page. Contact details are not shown.