Promised date passed20 floorsRERA P51700026679

Main building, Veda

Deedo IDDP-THN-NSNZ-VEDA

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

All of Veda
Median saleNot on recordneeds 3 or more sales
Booked68%98 of 145 · MahaRERA
Completion30 Sep 2024as registered
Units & parking in Main building
TypeCarpet areaUnitsBooked
1.5BHK42.3 m² (456 sq.ft)98
1.5BHK42.5 m² (457 sq.ft)98
1.5BHK43.2 m² (465 sq.ft)11
1.5BHK46.3 m² (498 sq.ft)76
1BHK27.1 m² (291 sq.ft)117
1BHK29.3 m² (315 sq.ft)117
1BHK30.1 m² (324 sq.ft)22
1BHK30.9 m² (333 sq.ft)33
1BHK31 m² (334 sq.ft)42
1BHK31.4 m² (338 sq.ft)115
1BHK32.8 m² (353 sq.ft)2014
1BHK37.8 m² (407 sq.ft)10
2BHK42.1 m² (454 sq.ft)11
2BHK43.9 m² (473 sq.ft)115
2BHK44.3 m² (477 sq.ft)107
2BHK46.2 m² (497 sq.ft)44
2BHK46.4 m² (499 sq.ft)11
2BHK47.3 m² (509 sq.ft)44
Office space37.5 m² (403 sq.ft)10
Office space40.1 m² (432 sq.ft)10
Office space47.8 m² (515 sq.ft)20
Office space50.1 m² (540 sq.ft)10
Office space50.6 m² (545 sq.ft)10
Office space53.1 m² (571 sq.ft)10
Office space55.8 m² (601 sq.ft)21
Office space56.6 m² (609 sq.ft)11
Office space62.8 m² (676 sq.ft)10
Shop12.4 m² (133 sq.ft)11
Shop20.2 m² (217 sq.ft)21
Shop34 m² (366 sq.ft)11
Shop37.2 m² (401 sq.ft)21
Shop44.3 m² (477 sq.ft)11
Shop45.6 m² (491 sq.ft)11
Shop50.2 m² (540 sq.ft)22
Shop50.8 m² (546 sq.ft)11
Shop54.8 m² (590 sq.ft)11
Shop57.2 m² (615 sq.ft)11
Shop379 m² (4,080 sq.ft)10
As registered with MahaRERA
RERA registration
P51700026679 · registered 21 Oct 2020
Promised completion
30 Sep 2024
Revised completion
30 Sep 2024
Sanctioned habitable floors
20
Building
VEDA
Sanctioned floors (incl. basement, stilt, podium)
20
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
DP-THN-NSNZ-VEDA
Questions about Main building

When is Main building due for completion?

The MahaRERA registration promises 30 Sep 2024.

How many floors does Main building have?

20 sanctioned habitable floors, as registered with MahaRERA.

Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology