Others · 1 building · 177 unitsRERA P51700021181

Vasudev Paradise

Deedo IDDP-THN-TZ3H

Completion was pushed back 4 months, to May 2027; no MahaRERA orders on record; 84% of its units are booked.

Thane (M Corp.), Thane 401105 · by Aristone Developers

DeliveryExtended 4 moPromised Jan 2027 · now due May 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales84% booked148 of 177 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to May 2027

  • This projectRegistered 14 Jun 2019, completion promised 31 Jan 2027, revised to 31 May 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700021181
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002118114 Jun 201931 Jan 202731 May 2027Aristone DevelopersProject page
Documents116

1 document held by Deedo, 115 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardCOMPANY PAN CARD.pdf · uploaded 20 May 2019Source

Legal

  • Legal Title reportTitle Certificate.pdf · uploaded 20 May 2019Source
  • Declaration Form BFORM B.pdf · uploaded 20 May 2019Source
  • Legal Title reportAristone Title certificate latest_compressed.pdf · uploaded 7 Dec 2020Source
  • Declaration Form BAffidavit Cum Declaration.pdf · uploaded 26 Nov 2024Source
  • Declaration Form BAffidavit cum Declaration Latest.pdf · uploaded 20 Feb 2025Source

Migrated

  • 1 PAN CardCOMPANY PAN CARD.pdf · uploaded 20 May 2019Source
Show all 116 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportTitle Certificate.pdf · uploaded 20 May 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 20 May 2019Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 20 May 2019Source
  • 1 Certificates of CA (Form 3)Ca Certificate.pdf · uploaded 20 May 2019Source
  • 1 Building Plan Approval (IOD)iod.PDF · uploaded 21 May 2019Source
  • 1 Proforma of Allotment letterLETTER AGAINST AGREEMENT.pdf · uploaded 21 May 2019Source
  • 1 Copy of Layout Approval (in case of layout)layout compressed.pdf · uploaded 25 May 2019Source
  • 1 Details of encumbrancesNo Encumbrance.pdf · uploaded 28 May 2019Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch New ARISTONE.pdf · uploaded 28 May 2019Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENG NEW ARISTONE.pdf · uploaded 28 May 2019Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)no progress letter.pdf · uploaded 27 Jul 2019Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)no progress letter002.pdf · uploaded 17 Oct 2019Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)aristone.pdf · uploaded 20 Jan 2020Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)NO PROGRESS LETTER.pdf · uploaded 23 Jun 2020Source
  • 1 Details of Restarting of Construction work post lockdownCOVID 19.pdf · uploaded 23 Jun 2020Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)NO PROGRESS LETTER.pdf · uploaded 17 Oct 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5.pdf · uploaded 17 Oct 2020Source
  • 2 Copy of the legal title reportAristone Title certificate latest_compressed.pdf · uploaded 7 Dec 2020Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)no progress compressed.pdf · uploaded 27 Jan 2021Source
  • 2 Certificates of CA (Form 3)Form 3 compressed.pdf · uploaded 27 Jan 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A Site Engineer082.pdf · uploaded 21 May 2021Source
  • 3 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 21 May 2021Source
  • 1 Declaration about Commencement CertificateCC Declaration RERA Upload118.pdf · uploaded 19 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2 Site Engineer Quater ending June 21_compressed.pdf · uploaded 19 Aug 2021Source
  • 1 Disclosure of sold/ booked inventorySol Unsold List RERA Upload117_compressed.pdf · uploaded 19 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Aristone Developers (01-04-2020 to 31-03-2021).pdf · uploaded 19 Aug 2021Source
  • 2 Proforma of Allotment letterDraft Aristone rera flat agreement Final copy.pdf · uploaded 29 Sep 2021Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate .pdf · uploaded 3 Oct 2022Source
  • 4 Certificates of CA (Form 3)Form-3 (03-10-2022) (1).pdf · uploaded 10 Nov 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form-5 (03-10-2022) (2).pdf · uploaded 10 Nov 2022Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect cert205.pdf · uploaded 3 Apr 2023Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer cert209.pdf · uploaded 3 Apr 2023Source
  • 5 Certificates of CA (Form 3)Form 3_compressed.pdf · uploaded 3 Apr 2023Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 23 Sep 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 23 Sep 2023Source
  • 6 Certificates of CA (Form 3)Form-3.pdf · uploaded 23 Sep 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 23 Sep 2023Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect's Certificate.pdf · uploaded 12 Apr 2024Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate.pdf · uploaded 12 Apr 2024Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate.pdf · uploaded 12 Apr 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form - 5-ARISTONE.pdf · uploaded 2 May 2024Source
  • 2 Declaration in FORM BAffidavit Cum Declaration.pdf · uploaded 26 Nov 2024Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 26 Nov 2024Source
  • 5 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 26 Nov 2024Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 26 Nov 2024Source
  • 2 Disclosure of sold/ booked inventorySold Unsold List.pdf · uploaded 26 Nov 2024Source
  • 1 Declaration about Commencement CertificateDeclaration.pdf · uploaded 26 Nov 2024Source
  • 1 CERSAI detailsCersai Report and Undertaking.pdf · uploaded 26 Nov 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Real Estate.pdf · uploaded 26 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Engineer Quality Assurance.pdf · uploaded 26 Nov 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectCersai Report and Undertaking.pdf · uploaded 26 Nov 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Decaration about Bank Account.pdf · uploaded 11 Dec 2024Source
  • 1 a Details of encumbrances concerned to FinanceLegal Encumberance.pdf · uploaded 5 Feb 2025Source
  • 1 b Details of encumbrances concerned to LegalLegal Encumberance.pdf · uploaded 5 Feb 2025Source
  • 1 Proforma of Agreement for saleDRAFT AGREEMENT - Copy.pdf · uploaded 5 Feb 2025Source
  • 1 Certificates of CA (Form 3)CA Form Revised.pdf · uploaded 6 Feb 2025Source
  • 2 Certificates of CA (Form 3)CA Form Revised (2).pdf · uploaded 6 Feb 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold List (2).pdf · uploaded 6 Feb 2025Source
  • 1 Declaration in FORM BAffidavit cum Declaration Latest.pdf · uploaded 20 Feb 2025Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Aristone Developers Architect Certifiate.pdf · uploaded 20 Feb 2025Source
  • 3 Certificates of CA (Form 3)aristone developers_0001 (1)_compressed.pdf · uploaded 20 Feb 2025Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Aristone Developers Engineer Certificate.pdf · uploaded 20 Feb 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Aristone Developers Engineer Certificate.pdf · uploaded 20 Feb 2025Source
  • 1 Other – TechnicalRera Extension.pdf · uploaded 20 Feb 2025Source
  • 4 Certificates of CA (Form 3)aristone developers_0001_compressed (1)_compressed.pdf · uploaded 21 Feb 2025Source
  • Withdrawal Update Form 1VASUDEV HEIGHTS.pdf · uploaded 23 Jul 2025Source
  • Withdrawal Update Form 2VASUDE PARADISE_ENGINERRRR.pdf · uploaded 23 Jul 2025Source
  • Withdrawal Update Form 3ARISTONE DEVELOPERS.pdf · uploaded 23 Jul 2025Source
  • Withdrawal Update Form 1VASUDEV HEIGHTS.pdf · uploaded 13 Nov 2025Source
  • Withdrawal Update Form 2vasudev paradise Engineer certificate sept 25.pdf · uploaded 13 Nov 2025Source
  • Withdrawal Update Form 3ARISTONE DEV.pdf · uploaded 13 Nov 2025Source
  • Withdrawal Update Form 1VASUDEV HEIGHTS.pdf · uploaded 30 Dec 2025Source
  • Withdrawal Update Form 1VASUDEV HEIGHTS.pdf · uploaded 30 Dec 2025Source
  • Withdrawal Update Form 2vasudev paradise Engineer certificate sept 25.pdf · uploaded 30 Dec 2025Source
  • Withdrawal Update Form 2vasudev paradise Engineer certificate sept 25.pdf · uploaded 30 Dec 2025Source
  • Withdrawal Update Form 3ARISTONE DEV.pdf · uploaded 30 Dec 2025Source
  • Withdrawal Update Form 3ARISTONE DEV.pdf · uploaded 30 Dec 2025Source
  • Form 5 (FY 2024-2025)Form 5.pdf · uploaded 14 Jan 2026Source
  • Withdrawal Update Form 1VASUDEV HEIGHTS.pdf · uploaded 17 Jan 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 17 Jan 2026Source
  • Withdrawal Update Form 3FORM 3_compressed (1).pdf · uploaded 17 Jan 2026Source
  • Form 2A (FY 2019-2020)1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20).pdf · uploaded 17 Jan 2026Source
  • Form 2A (FY 2020-2021)1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21).pdf · uploaded 17 Jan 2026Source
  • Form 2A (FY 2023-2024)1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf · uploaded 17 Jan 2026Source
  • Form 2A (FY 2024-2025)Form 2A 13.01.2026.pdf · uploaded 17 Jan 2026Source
  • Form 5 (FY 2019-2020)1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20).pdf · uploaded 14 Mar 2026Source
  • Form 5 (FY 2020-2021)1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf · uploaded 14 Mar 2026Source
  • Form 5 (FY 2021-2022)1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf · uploaded 14 Mar 2026Source
  • Form 5 (FY 2022-2023)1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf · uploaded 14 Mar 2026Source
  • Form 5 (FY 2023-2024)1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24).pdf · uploaded 14 Mar 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 2Form- 2.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 3CA Certificate_compressed.pdf · uploaded 24 Apr 2026Source
  • Form 2A (FY 2025-2026)form 2a.pdf · uploaded 20 Jul 2026Source
  • Form 5 (FY 2025-2026)FORM 5 ARISTONE DEVELOPERS 2025-26.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 1Vasudev Paradise Arch June-26_0001.pdf · uploaded 22 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 VASUDEV PERADISE APRIL TO JUNE.pdf · uploaded 22 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 ARISTONE DEVELOPERS VASUDEV PARADIE.pdf · uploaded 22 Jul 2026Source

Technical

  • Documentiod.PDF · uploaded 21 May 2019Source
  • Documentlayout compressed.pdf · uploaded 25 May 2019Source
  • Other – TechnicalRera Extension.pdf · uploaded 20 Feb 2025Source

Technical (Architect)

  • DocumentArchitect Certificate.pdf · uploaded 26 Nov 2024Source
  • DocumentAristone Developers Architect Certifiate.pdf · uploaded 20 Feb 2025Source
  • DocumentVasudev Paradise Arch June-26_0001.pdf · uploaded 22 Jul 2026Source

Technical (Engineer)

  • DocumentEngineer Certificate.pdf · uploaded 26 Nov 2024Source
  • DocumentAristone Developers Engineer Certificate.pdf · uploaded 20 Feb 2025Source
  • DocumentAristone Developers Engineer Certificate.pdf · uploaded 20 Feb 2025Source
  • DocumentFORM 2 VASUDEV PERADISE APRIL TO JUNE.pdf · uploaded 22 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 430 PART OR HISSA NO 2

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, 3BHK, Shop177 units in all
Address
430 Part Or Hissa No 2, Thane, ThanePIN 401105
Village
Thane (M Corp.), Thane taluka
Land area for this project
2,000 sq m (21,528 sq ft)
Permissible built-up area
9,379 sq m (1,00,952 sq ft)
Sanctioned built-up area
9,100 sq m (97,954 sq ft)
Designated bank account
88
Developed in phases
No

Survey, CTS, gat or plot numbers

430 PART OR HISSA NO 2

Land as published on MahaRERA's project page

430 PART OR HISSA NO 2

Boundaries

North
Dp Road No 292
South
Survey No Old 423
East
Survey No Old 431
West
Survey No Old 424

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking177 units

148 of 177 units booked (84%), as the promoter reported to MahaRERA

1BHK · 42 units2BHK · 81 units3BHK · 42 unitsShop · 12 units
TypeCarpet areaUnitsBooked
1BHK36.58 sq m · 394 sq ft4230
2BHK49.71 sq m · 535 sq ft3933
2BHK54.09 sq m · 582 sq ft4238
3BHK69.86 sq m · 752 sq ft4239
Shop27.27 sq m · 294 sq ft22
Shop32.38 sq m · 349 sq ft43
Shop37.5 sq m · 404 sq ft21
Shop38.89 sq m · 419 sq ft21
Shop41.22 sq m · 444 sq ft21

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAnish & Associates—
Chartered accountantRamesh Dhondiram Lukad—
EngineerDilip Sharma—
EngineerNitesh B Jadhav—
EngineerSubhash Singh—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology