Promised date passed35 floorsRERA P51700008758
Main building, Trinity Heights
Deedo IDDP-THN-6RCM-THMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked64%73 of 114 · MahaRERA
Completion30 May 2023as registered
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 42.7 m² (460 sq.ft) | 60 | 37 |
| 2BHK | 59.9 m² (645 sq.ft) | 54 | 36 |
As registered with MahaRERA
- RERA registration
- P51700008758 · registered 19 Aug 2017
- Promised completion
- 30 May 2023
- Revised completion
- 30 May 2023
- Sanctioned habitable floors
- 35
- Building
- TRINITY HEIGHTS
- Sanctioned floors (incl. basement, stilt, podium)
- 35
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- Sanctioned FSI area (sq m)
- 22
- MahaRERA status
- Certificate Signed
- Deedo ID
- Deedo IDDP-THN-6RCM-TH
Questions about Main building
When is Main building due for completion?
The MahaRERA registration promises 30 May 2023.
How many floors does Main building have?
35 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology