Deedo IDDP-THN-6RCMIts promised completion date, May 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 64% of its units are booked.
Thane (M Corp.), Thane 400615 · Promoter: ANIL thakurdas kursija
Its promised completion date, May 2023, has passed and MahaRERA does not show it completed
- This projectRegistered 19 Aug 2017, completion promised 30 May 2023, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700008758
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700008758 | 19 Aug 2017 | 30 May 2023 | 30 May 2023 | ANIL thakurdas kursija | Project page |
Documents41
1 document held by Deedo, 40 filings listed on MahaRERA's project page
Finance
- PAN CardATK New Pan card.pdf · uploaded 20 Jan 2022Source
Legal
Show all 41 documentsShow fewer documents
Migrated
- 3 Copy of the legal title reportTitle Report 3.pdf · uploaded 31 Jul 2017Source
- 1 Details of encumbrancesDeclaration Encumbrances.pdf · uploaded 31 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)Plan1-.pdf · uploaded 31 Jul 2017Source
- 2 Copy of Layout Approval (in case of layout)Plan2-.pdf · uploaded 31 Jul 2017Source
- 3 Copy of Layout Approval (in case of layout)Plan3-.pdf · uploaded 31 Jul 2017Source
- 4 Copy of Layout Approval (in case of layout)Plan4-.pdf · uploaded 31 Jul 2017Source
- 1 Building Plan Approval (IOD)Plan1-.pdf · uploaded 31 Jul 2017Source
- 2 Building Plan Approval (IOD)Plan2-.pdf · uploaded 31 Jul 2017Source
- 3 Building Plan Approval (IOD)Plan3-.pdf · uploaded 31 Jul 2017Source
- 4 Building Plan Approval (IOD)Plan4-.pdf · uploaded 31 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentC C Certificate-.pdf · uploaded 31 Jul 2017Source
- 1 Declaration in FORM BForm B-.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1-.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2-.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of CA (Form 3)Declaration of Form 3.pdf · uploaded 31 Jul 2017Source
- 1 Proforma of Allotment letterDeclaration Allottment letter.pdf · uploaded 31 Jul 2017Source
- 2 Proforma of Allotment letterDeclaration of Agreement for sale.pdf · uploaded 31 Jul 2017Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)03 - Society Registration Certificate.pdf · uploaded 23 Aug 2021Source
- 2 Status of Formation of Legal Entity (Society/Co Op etc.)STATUS - SOCIETY REGISTRATION.pdf · uploaded 23 Aug 2021Source
- 1 PAN CardATK New Pan card.pdf · uploaded 20 Jan 2022Source
- 1 Declaration about Commencement CertificateTrinity Heights - Commencement Certificate_11zon.pdf · uploaded 20 Jan 2022Source
- 1 Status of ConveyanceTrinity Heights - Status of Conveyance.pdf · uploaded 20 Jan 2022Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)20220219 - Form I.pdf · uploaded 19 Feb 2022Source
Technical
- DocumentPlan1-.pdf · uploaded 31 Jul 2017Source
- DocumentPlan1-.pdf · uploaded 31 Jul 2017Source
- DocumentPlan4-.pdf · uploaded 31 Jul 2017Source
- DocumentPlan3-.pdf · uploaded 31 Jul 2017Source
- DocumentPlan4-.pdf · uploaded 31 Jul 2017Source
- DocumentPlan2-.pdf · uploaded 31 Jul 2017Source
- DocumentPlan3-.pdf · uploaded 31 Jul 2017Source
- DocumentPlan2-.pdf · uploaded 31 Jul 2017Source
Technical (Architect)
- Document20220219 - Form I.pdf · uploaded 19 Feb 2022Source
Technical (Engineer)
- DocumentForm 2-.pdf · uploaded 31 Jul 2017Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals23/5, 23/7
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK114 units in all
- Address
- S NO 23/4, 23/5, 23/7, Ghodbunder RoadPIN 400615
- Village
- Thane (M Corp.), Thane taluka
- Location
- 19.27155, 72.96377
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- S No 144
- South
- S No 144
- East
- S No 142
- West
- S No 144
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking114 units
73 of 114 units booked (64%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 42.74 sq m · 460 sq ft | 60 | 37 |
| 2BHK | 59.92 sq m · 645 sq ft | 54 | 36 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Navrachana | — |
| Engineer | Epicon Consultants Pvt Ltd | — |
Source: MahaRERA project page. Contact details are not shown.