Skip to content
Residential / Group Housing · 1 building · 73 unitsRERA P51700052657

Shiv Anand

Deedo IDDP-THN-C4W6

MahaRERA shows it completed; no MahaRERA orders on record; 0% of its units are booked.

Thane (M Corp.), Thane 400602 · by Bhagwati Construction

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 73 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 15 Sep 2023, completion promised 31 Mar 2026.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700052657
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170005265715 Sep 202331 Mar 202631 Mar 2026Bhagwati ConstructionProject page
Documents89

1 document held by Deedo, 88 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardbhagwati pan card _PDF.pdf · uploaded 11 Jul 2023Source

Legal

  • Declaration Form BForm B -Bhagwati Construction.pdf · uploaded 11 Jul 2023Source
  • Legal Title reportTitle Report.pdf · uploaded 17 Jul 2023Source

Migrated

  • 1 PAN Cardbhagwati pan card _PDF.pdf · uploaded 11 Jul 2023Source
  • 1 Declaration in FORM BForm B -Bhagwati Construction.pdf · uploaded 11 Jul 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Oragnizations.pdf · uploaded 11 Jul 2023Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 11 Jul 2023Source
Show all 89 documentsShow fewer documents

Migrated

  • 1 Deviation Report with respect to model copy of AgreementDeviation report with respect to Model Copy of Agreement.pdf · uploaded 11 Jul 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 12 Jul 2023Source
  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 17 Jul 2023Source
  • 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 17 Jul 2023Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance - Finanace.pdf · uploaded 18 Jul 2023Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance - Finanace.pdf · uploaded 18 Jul 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate.pdf · uploaded 18 Jul 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate.pdf · uploaded 18 Jul 2023Source
  • 1 Proforma of Agreement for saleModel form of agreement_11zon.pdf · uploaded 18 Jul 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about Separate Bank Account.pdf · uploaded 18 Jul 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report with respect to Allotment Letter.pdf · uploaded 18 Jul 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Merged Form 3 - Bhagwati.pdf · uploaded 21 Jul 2023Source
  • 1 Copy of Layout Approval (in case of layout)1_11zon.pdf · uploaded 24 Jul 2023Source
  • 2 Copy of Layout Approval (in case of layout)2_11zon.pdf · uploaded 24 Jul 2023Source
  • 1 Building Plan Approval / NA Order for plotted development1_11zon.pdf · uploaded 24 Jul 2023Source
  • 2 Building Plan Approval / NA Order for plotted development2_11zon.pdf · uploaded 24 Jul 2023Source
  • 1 CERSAI detailsCERSAI_Search_Report_200275665738_For_Asset_Based_Search_27_07_2023_12_07_30_450.pdf · uploaded 27 Jul 2023Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Legal and Finance.pdf · uploaded 3 Aug 2023Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Legal and Finance.pdf · uploaded 3 Aug 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Final.pdf · uploaded 16 Aug 2023Source
  • 1 Other – TechnicalReply Final.pdf · uploaded 29 Aug 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1-Q2.PDF · uploaded 7 Jun 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1-Q3.PDF · uploaded 7 Jun 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1-Q4.PDF · uploaded 7 Jun 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2-Q2.PDF · uploaded 7 Jun 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2-Q3.PDF · uploaded 7 Jun 2024Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold 30-09-2023-Signed.pdf · uploaded 7 Jun 2024Source
  • 2 Disclosure of sold/ booked inventorySold-Unsold Q3.PDF · uploaded 7 Jun 2024Source
  • 3 Disclosure of sold/ booked inventorySold-unsold Q2.PDF · uploaded 7 Jun 2024Source
  • 4 Disclosure of sold/ booked inventorySold -Unsold Q4.PDF · uploaded 7 Jun 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2-Q4_Compressed.pdf · uploaded 8 Jun 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Q2 - Compressed.pdf · uploaded 8 Jun 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-Q3_comppressed.pdf · uploaded 8 Jun 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-Q4_compressed.pdf · uploaded 8 Jun 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - signed_compressed.pdf · uploaded 24 Jun 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)3_Form 3 - Q1 of FY 2024-25_Signed.pdf · uploaded 12 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)2_Form 2-Engineer Certificate - 30-June-2024.pdf · uploaded 12 Mar 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2_Form 2 - Engineer Certificate_30-Sept-2024.pdf · uploaded 12 Mar 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)2_Form 2 Engineer Certificate - 31-Dec-2024.pdf · uploaded 12 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1_Form 1-Architect Certificate - 30-June-2024.pdf · uploaded 17 Mar 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)1_Form 1 - Architect Certificate_30-Sept-2024.pdf · uploaded 17 Mar 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)1_Form 1 Architect Certificate - 31-Dec-2024.pdf · uploaded 17 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)3_Form 3 - Q2 of FY 2024-25_Signed.pdf · uploaded 17 Mar 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)3_Form 3 - Q3 of FY 2024-25_Signed.pdf · uploaded 17 Mar 2025Source
  • 1 Disclosure of sold/ booked inventory4_Disclosure of sold - 30-06-2024.pdf · uploaded 24 Mar 2025Source
  • 2 Disclosure of sold/ booked inventory4_Disclosure of sold - 30-09-2024.pdf · uploaded 24 Mar 2025Source
  • 3 Disclosure of sold/ booked inventory4_Disclosure of sold - 31-12-2024.pdf · uploaded 24 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)2_Form 2 - 30-June-2024.pdf · uploaded 2 Apr 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2_Form 2 - 30-Sep-2024.pdf · uploaded 2 Apr 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)2_Form 2 - 31-Dec-2024.pdf · uploaded 2 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A - FY 2023-24.pdf · uploaded 4 Apr 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 FY 2023-24.pdf · uploaded 17 Apr 2025Source
  • Form 11_Form 1 - 31-March-2025.pdf · uploaded 4 Jun 2025Source
  • Form 5 (FY 2024-2025)Form-5 -FY-2024-25.pdf · uploaded 1 Oct 2025Source
  • Form 2A (FY 2024-2025)Form-2A FY-2024-25.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 101 Form 1 - Architech Certificate 30-06-2024 .pdf · uploaded 6 Mar 2026Source
  • Withdrawal Update Form 202 Form 2 - Engineer Certificate 30-06-2025.pdf · uploaded 6 Mar 2026Source
  • Withdrawal Update Form 303 Form 3 - Q1 FY 2025-26 (Bhagwati Construction) SG .pdf · uploaded 6 Mar 2026Source
  • Withdrawal Update Form 101- Form 1 - as on 11-07-2025 (Bhagwati Construction) SG .pdf · uploaded 9 Mar 2026Source
  • Withdrawal Update Form 101- Form 1 - as on 11-07-2025 (Bhagwati Construction) SG .pdf · uploaded 9 Mar 2026Source
  • Withdrawal Update Form 202- Form 2 - Engineer Certificate 11-07-2025.pdf · uploaded 9 Mar 2026Source
  • Withdrawal Update Form 202- Form 2 - Engineer Certificate 11-07-2025.pdf · uploaded 9 Mar 2026Source
  • Withdrawal Update Form 303- Form 3 - as on 11-07-2025 (Bhagwati Construction) SG .pdf · uploaded 9 Mar 2026Source
  • Withdrawal Update Form 303- Form 3 - as on 11-07-2025 (Bhagwati Construction) SG .pdf · uploaded 9 Mar 2026Source
  • Occupational Certificate04- Occupancy Certificate 11-07-2025 (Bhagwati Construction) .pdf · uploaded 9 Mar 2026Source

Technical

  • Document1_11zon.pdf · uploaded 24 Jul 2023Source
  • Document2_11zon.pdf · uploaded 24 Jul 2023Source
  • Document1_11zon.pdf · uploaded 24 Jul 2023Source
  • Document2_11zon.pdf · uploaded 24 Jul 2023Source
  • Other – TechnicalReply Final.pdf · uploaded 29 Aug 2023Source

Technical (Architect)

  • Document1_Form 1-Architect Certificate - 30-June-2024.pdf · uploaded 17 Mar 2025Source
  • Document1_Form 1 - Architect Certificate_30-Sept-2024.pdf · uploaded 17 Mar 2025Source
  • Document1_Form 1 Architect Certificate - 31-Dec-2024.pdf · uploaded 17 Mar 2025Source
  • Document01- Form 1 - as on 11-07-2025 (Bhagwati Construction) SG .pdf · uploaded 9 Mar 2026Source

Technical (Engineer)

  • Document2_Form 2-Engineer Certificate - 30-June-2024.pdf · uploaded 12 Mar 2025Source
  • Document2_Form 2 - Engineer Certificate_30-Sept-2024.pdf · uploaded 12 Mar 2025Source
  • Document2_Form 2 Engineer Certificate - 31-Dec-2024.pdf · uploaded 12 Mar 2025Source
  • Document2_Form 2 - 30-June-2024.pdf · uploaded 2 Apr 2025Source
  • Document2_Form 2 - 30-Sep-2024.pdf · uploaded 2 Apr 2025Source
  • Document2_Form 2 - 31-Dec-2024.pdf · uploaded 2 Apr 2025Source
  • Document02- Form 2 - Engineer Certificate 11-07-2025.pdf · uploaded 9 Mar 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 80, C.T.S. No. 79

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, Shop, Studio Apartment73 units in all
Address
Plot T.N. No.13, C.T.S. No. 79 & 80, At Shivaji Path, Thane West, Shivaji Path, Tembi Naka, Thane WestPIN 400602
Village
Thane (M Corp.), Thane taluka
Land area for this project
636 sq m (6,840 sq ft)
Permissible built-up area
1,992 sq m (21,440 sq ft)
Sanctioned built-up area
1,992 sq m (21,440 sq ft)
Designated bank account
220
Developed in phases
No

Survey, CTS, gat or plot numbers

80C.T.S. No. 79Plot T.N. No.13

Land as published on MahaRERA's project page

Plot T.N. No.13, C.T.S. No. 79 & 80, At Shivaji Path, Thane West

Boundaries

North
Nowroji Nanabhai Road
South
Open Court yard of the property
East
Municipal Road
West
Agyari Lane Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking73 units

0 of 73 units booked (0%), as the promoter reported to MahaRERA

1BHK · 6 units1RK · 17 unitsShop · 9 unitsStudio Apartment · 41 units
TypeCarpet areaUnitsBooked
1BHK25.58 sq m · 275 sq ft10
1BHK25.58 sq m · 275 sq ft40
1BHK25.58 sq m · 275 sq ft10
1RK20.38 sq m · 219 sq ft10
1RK20.38 sq m · 219 sq ft30
1RK20.38 sq m · 219 sq ft10
1RK20.41 sq m · 220 sq ft40
1RK20.41 sq m · 220 sq ft10
Show all 35 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1RK20.41 sq m · 220 sq ft10
1RK28.71 sq m · 309 sq ft40
1RK28.71 sq m · 309 sq ft10
1RK28.71 sq m · 309 sq ft10
Shop9.58 sq m · 103 sq ft10
Shop12.33 sq m · 133 sq ft10
Shop20.01 sq m · 215 sq ft10
Shop22.5 sq m · 242 sq ft10
Shop26.25 sq m · 283 sq ft10
Shop26.74 sq m · 288 sq ft10
Shop37.39 sq m · 402 sq ft10
Shop37.55 sq m · 404 sq ft10
Shop37.72 sq m · 406 sq ft10
Studio Apartment11.97 sq m · 129 sq ft40
Studio Apartment11.97 sq m · 129 sq ft10
Studio Apartment13.5 sq m · 145 sq ft10
Studio Apartment13.5 sq m · 145 sq ft50
Studio Apartment15.63 sq m · 168 sq ft20
Studio Apartment15.63 sq m · 168 sq ft40
Studio Apartment16.25 sq m · 175 sq ft10
Studio Apartment16.25 sq m · 175 sq ft50
Studio Apartment16.78 sq m · 181 sq ft50
Studio Apartment16.78 sq m · 181 sq ft10
Studio Apartment21.07 sq m · 227 sq ft10
Studio Apartment21.07 sq m · 227 sq ft50
Studio Apartment25.11 sq m · 270 sq ft20
Studio Apartment25.11 sq m · 270 sq ft40

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMakarand Toraskar Associates—
Chartered accountantChintan D Saiya and Company—
Chartered accountantSwapnesh & Vinit Chartered Accountants—
EngineerNS Structural Consultants—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology