Deedo IDDP-THN-KNNMCompletion was pushed back 4 months, to Apr 2033; no MahaRERA orders on record; 0% of its units are booked.
Thane (M Corp.), Thane 400705 · by Raheja Universal (Pvt.) Ltd
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2033
- This projectRegistered 16 Jun 2025, completion promised 31 Dec 2032, revised to 30 Apr 2033.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700080542
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700080542 | 16 Jun 2025 | 31 Dec 2032 | 30 Apr 2033 | Raheja Universal (Pvt.) Ltd. | Project page |
Documents119
2 documents held by Deedo, 117 filings listed on MahaRERA's project page
Finance
Show all 119 documentsShow fewer documents
Migrated
- 1 PAN CardPAN card.PDF · uploaded 7 Apr 2025Source
- 1 a Details of encumbrances concerned to FinancePrime-2 Encumbrance Letter Finance and Legal.pdf · uploaded 7 Apr 2025Source
- 1 Copy of Layout Approval (in case of layout)Prime 2 layout Plan.pdf · uploaded 7 Apr 2025Source
- 1 Declaration in FORM BPrime-2 Form B.pdf · uploaded 7 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Prime 2 .pdf · uploaded 7 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Prime-2 Form-2.pdf · uploaded 7 Apr 2025Source
- 2 Building Plan Approval / NA Order for plotted development4-5.pdf · uploaded 7 Apr 2025Source
- 10 Building Plan Approval / NA Order for plotted development20-21.pdf · uploaded 7 Apr 2025Source
- 9 Building Plan Approval / NA Order for plotted development18-19.pdf · uploaded 7 Apr 2025Source
- 8 Building Plan Approval / NA Order for plotted development16-17.pdf · uploaded 7 Apr 2025Source
- 7 Building Plan Approval / NA Order for plotted development14-15.pdf · uploaded 7 Apr 2025Source
- 6 Building Plan Approval / NA Order for plotted development12-13.pdf · uploaded 7 Apr 2025Source
- 5 Building Plan Approval / NA Order for plotted development10-11.pdf · uploaded 7 Apr 2025Source
- 4 Building Plan Approval / NA Order for plotted development8-9.pdf · uploaded 7 Apr 2025Source
- 3 Building Plan Approval / NA Order for plotted development6-7.pdf · uploaded 7 Apr 2025Source
- 1 Building Plan Approval / NA Order for plotted development2-3.pdf · uploaded 7 Apr 2025Source
- 1 Declaration about Commencement CertificatePrime-2 CC Declaration.pdf · uploaded 7 Apr 2025Source
- 1 CERSAI detailsPrime-2 - CERSAI UNDERTAKING.pdf · uploaded 7 Apr 2025Source
- 2 CERSAI detailsCERSAI report ABFL 150cr .pdf · uploaded 7 Apr 2025Source
- 3 CERSAI detailsCERSAI report HDFC 150cr.pdf · uploaded 7 Apr 2025Source
- 4 CERSAI detailsCERSAI report HDFC 225cr.pdf · uploaded 7 Apr 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Prime-2 Declaration about all RERA Designated Bank Accounts (Format A) .pdf · uploaded 7 Apr 2025Source
- 1 Deviation Report with respect to Allotment letterPrime-2 Allotment Letter Deviation Report.pdf · uploaded 7 Apr 2025Source
- 1 b Details of encumbrances concerned to LegalPrime-2 Encumbrance Letter Finance and Legal.pdf · uploaded 7 Apr 2025Source
- 1 Other – TechnicalPlot area declaration.pdf · uploaded 7 Apr 2025Source
- 2 Other – TechnicalEmail from SPA.pdf · uploaded 7 Apr 2025Source
- 1 Deviation Report with respect to model copy of AgreementPrime-2 ATSL deviation report.pdf · uploaded 7 Apr 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest (SLR).pdf · uploaded 7 Apr 2025Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest (RSR).pdf · uploaded 7 Apr 2025Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest (ASR).pdf · uploaded 7 Apr 2025Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure for securedunsecured finance availed for the project.pdf · uploaded 7 Apr 2025Source
- 1 Copy of the legal title reportPrime 2 Title Report .pdf · uploaded 6 May 2025Source
- 1 Proforma of Allotment letterPrime-2 Allotment letter.pdf · uploaded 6 May 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentPrime 2 Commencement Certificate.pdf · uploaded 6 May 2025Source
- 2 Other – LegalDOA 05102006.pdf · uploaded 6 May 2025Source
- 1 Other – LegalClarification .pdf · uploaded 6 May 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Prime-2 Format 'B'.pdf · uploaded 6 May 2025Source
- 1 Other – FinanceClarification .pdf · uploaded 8 May 2025Source
- 3 Other – TechnicalFinal Plot area declaration.pdf · uploaded 8 May 2025Source
- 1 Proforma of Agreement for salePrime-2 Agreement .pdf · uploaded 23 May 2025Source
- 4 Other – Technicalreciept.pdf · uploaded 26 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Prime-2.pdf · uploaded 29 May 2025Source
- Withdrawal Update Form 1Prime-2 Form-1.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 1Prime-2 Form-1.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 1Prime-2 Form-1.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 1Prime-2 Form-1.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 1Prime-2 Form-1.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 2Prime-2 Form-2.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 2Prime-2 Form-2.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 2Prime-2 Form-2.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 2Prime-2 Form-2.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 2Prime-2 Form-2.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 3Prime-2 Form-3.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 3Prime-2 Form-3.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 3Prime-2 Form-3.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 3Prime-2 Form-3.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 3Prime-2 Form-3.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 1Prime-2 Form-1.pdf · uploaded 8 Sep 2025Source
- Withdrawal Update Form 1Prime-2 Form-1.pdf · uploaded 8 Sep 2025Source
- Withdrawal Update Form 2Prime-2 Form-2.pdf · uploaded 8 Sep 2025Source
- Withdrawal Update Form 2Prime-2 Form-2.pdf · uploaded 8 Sep 2025Source
- Withdrawal Update Form 3Prime-2 Form-3.pdf · uploaded 8 Sep 2025Source
- Withdrawal Update Form 3Prime-2 Form-3.pdf · uploaded 8 Sep 2025Source
- Withdrawal Update Form 1Prime-2 Form-1.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 1Prime-2 Form-1.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 2Prime-2 Form-2.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 2Prime-2 Form-2.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 3Prime-2 Form-3.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 3Prime-2 Form-3.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 1Form 1 (Sep 2025).pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 1Form 1 (Sep 2025).pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 2Prime-2 Form-2.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 2Form 2- Raheja Prime 2 as on Sep 2025.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 3Form 3_Prime-2_30092025.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 3Form 3_Prime-2_30092025.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 1Form 1 Prime2 30122025.pdf · uploaded 28 Jan 2026Source
- Withdrawal Update Form 2Prime 2 311225.pdf · uploaded 28 Jan 2026Source
- Withdrawal Update Form 3Form 3 as on Dec 2025.pdf · uploaded 28 Jan 2026Source
- Withdrawal Update Form 1Form 1 - Prime 2.pdf · uploaded 15 May 2026Source
- Withdrawal Update Form 2Prime - II.pdf · uploaded 15 May 2026Source
- Withdrawal Update Form 3Form 3 Prime-2 31 03 2026.pdf · uploaded 15 May 2026Source
- Form 2A (FY 2025-2026)Prime 2.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 1Form 1 Prime 2 dt 30 06 2026.pdf · uploaded 15 Jul 2026Source
- Withdrawal Update Form 2Prime 2 30 06 2026.pdf · uploaded 15 Jul 2026Source
- Withdrawal Update Form 3Form 3 Prime 2 30 06 2026.pdf · uploaded 15 Jul 2026Source
Technical
- DocumentPrime 2 layout Plan.pdf · uploaded 7 Apr 2025Source
- Document2-3.pdf · uploaded 7 Apr 2025Source
- Document4-5.pdf · uploaded 7 Apr 2025Source
- Document6-7.pdf · uploaded 7 Apr 2025Source
- Document8-9.pdf · uploaded 7 Apr 2025Source
- Document10-11.pdf · uploaded 7 Apr 2025Source
- Document12-13.pdf · uploaded 7 Apr 2025Source
- Document14-15.pdf · uploaded 7 Apr 2025Source
- Document16-17.pdf · uploaded 7 Apr 2025Source
- Document18-19.pdf · uploaded 7 Apr 2025Source
- Document20-21.pdf · uploaded 7 Apr 2025Source
- Other – TechnicalPlot area declaration.pdf · uploaded 7 Apr 2025Source
- Other – TechnicalEmail from SPA.pdf · uploaded 7 Apr 2025Source
- Other – TechnicalFinal Plot area declaration.pdf · uploaded 8 May 2025Source
- Other – Technicalreciept.pdf · uploaded 26 May 2025Source
- OthersLayout.pdf · uploaded 28 Jul 2025Source
- OthersProposed Layout.pdf · uploaded 28 Jul 2025Source
- DocumentPrime-2 Building Plan 1-8.pdf · uploaded 8 Sep 2025Source
- DocumentPrime-2 building Plan 9-14.pdf · uploaded 8 Sep 2025Source
- DocumentPrime -2 Building Plan 15-21.pdf · uploaded 8 Sep 2025Source
- DocumentLayout Prime 2.pdf · uploaded 26 Feb 2026Source
- DocumentPrime 2 Approval Plan Pg 2-10.pdf · uploaded 26 Feb 2026Source
- DocumentPrime 2 Approval Plan Pg 11-18.pdf · uploaded 26 Feb 2026Source
- DocumentPrime 2 Approval Plan Pg 19-21.pdf · uploaded 26 Feb 2026Source
Technical (Architect)
- DocumentForm 1 - Prime 2.pdf · uploaded 7 Oct 2026Source
Technical (Engineer)
- DocumentForm 2 - Prime 2.pdf · uploaded 9 Oct 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Gen-2/1/B
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- IT Office, Restaurant, Shop Restaurant, ShopRestaurant836 units in all
- Address
- Gen-2/1/B, Off Sion Panvel Highway, TTC Industrial AreaPIN 400705
- Village
- Thane (M Corp.), Thane taluka
- Land area for this project
- 10,486 sq m (1,12,869 sq ft)
- Approved layout area
- 2,23,309 sq m (24,03,671 sq ft)
- Permissible built-up area
- 1,03,810 sq m (11,17,405 sq ft)
- Sanctioned built-up area
- 1,03,810 sq m (11,17,405 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Gen-2/1/B
Boundaries
- North
- Internal Road
- South
- Internal Road
- East
- Future Phase
- West
- Internal Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking836 units
0 of 836 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| IT Office | 48.87 sq m · 526 sq ft | 116 | 0 |
| IT Office | 49.61 sq m · 534 sq ft | 29 | 0 |
| IT Office | 58.44 sq m · 629 sq ft | 90 | 0 |
| IT Office | 68.75 sq m · 740 sq ft | 29 | 0 |
| IT Office | 70.7 sq m · 761 sq ft | 232 | 0 |
| IT Office | 70.98 sq m · 764 sq ft | 29 | 0 |
| IT Office | 73.76 sq m · 794 sq ft | 29 | 0 |
| IT Office | 74.23 sq m · 799 sq ft | 22 | 0 |
Show all 34 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| IT Office | 74.88 sq m · 806 sq ft | 29 | 0 |
| IT Office | 76.18 sq m · 820 sq ft | 29 | 0 |
| IT Office | 78.13 sq m · 841 sq ft | 29 | 0 |
| IT Office | 79.8 sq m · 859 sq ft | 29 | 0 |
| IT Office | 80.92 sq m · 871 sq ft | 30 | 0 |
| IT Office | 107.77 sq m · 1,160 sq ft | 30 | 0 |
| IT Office | 128.11 sq m · 1,379 sq ft | 12 | 0 |
| IT Office | 146.23 sq m · 1,574 sq ft | 8 | 0 |
| IT Office | 171.31 sq m · 1,844 sq ft | 19 | 0 |
| IT Office | 311.69 sq m · 3,355 sq ft | 20 | 0 |
| IT Office | 315.59 sq m · 3,397 sq ft | 10 | 0 |
| IT Office | 2,594.57 sq m · 27,928 sq ft | 1 | 0 |
| IT Office | 2,721.94 sq m · 29,299 sq ft | 1 | 0 |
| Restaurant | 247.31 sq m · 2,662 sq ft | 1 | 0 |
| Restaurant | 366.78 sq m · 3,948 sq ft | 1 | 0 |
| Restaurant | 543.2 sq m · 5,847 sq ft | 1 | 0 |
| Restaurant | 603.68 sq m · 6,498 sq ft | 1 | 0 |
| Shop Restaurant | 94.76 sq m · 1,020 sq ft | 1 | 0 |
| Shop Restaurant | 130.53 sq m · 1,405 sq ft | 1 | 0 |
| Shop Restaurant | 138.61 sq m · 1,492 sq ft | 1 | 0 |
| Shop Restaurant | 145.48 sq m · 1,566 sq ft | 1 | 0 |
| Shop Restaurant | 157.56 sq m · 1,696 sq ft | 1 | 0 |
| Shop Restaurant | 193.24 sq m · 2,080 sq ft | 1 | 0 |
| Shop Restaurant | 199.37 sq m · 2,146 sq ft | 1 | 0 |
| Shop Restaurant | 443.24 sq m · 4,771 sq ft | 1 | 0 |
| ShopRestaurant | 200.3 sq m · 2,156 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals6
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Kamal Khemani | — |
| Chartered accountant | Vinit & Associates | — |
| Chartered accountant | Vinit Shah | — |
| Engineer | Avinash Shinde | — |
| Engineer | Mahesh Lalla | — |
| Other | Kamal | — |
Source: MahaRERA project page. Contact details are not shown.