Promised date passed30 floorsRERA P51700001031
Tower -27, Lodha Amara
Deedo IDDP-THN-YD7K-T27MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked97%157 of 162 · MahaRERA
Completion30 Dec 2021as registered
Units & parking in Tower -27
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK D | 46.5 m² (501 sq.ft) | 1 | 0 |
| 2BHK Optima | 48.8 m² (525 sq.ft) | 16 | 16 |
| 2BHK Optima | 50.7 m² (546 sq.ft) | 16 | 16 |
| 2BHKSMALL | 42.8 m² (461 sq.ft) | 5 | 4 |
| 2 BHK Ultima | 57.8 m² (622 sq.ft) | 58 | 57 |
| 2 BHK Ultima | 62.4 m² (672 sq.ft) | 1 | 1 |
| 2BHK Ultima | 57.6 m² (620 sq.ft) | 56 | 54 |
| 3BHKULTIMAJODI | 100.9 m² (1,086 sq.ft) | 3 | 3 |
| 4BHK Jodi | 100.9 m² (1,086 sq.ft) | 5 | 5 |
| 5BHKJODI | 116.7 m² (1,256 sq.ft) | 1 | 1 |
As registered with MahaRERA
- RERA registration
- P51700001031 · registered 25 Jul 2017
- Promised completion
- 30 Dec 2021
- Revised completion
- 30 Dec 2021
- Sanctioned habitable floors
- 30
- Sanctioned floors (incl. basement, stilt, podium)
- 30
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-THN-YD7K-T27
Questions about Tower -27
When is Tower -27 due for completion?
The MahaRERA registration promises 30 Dec 2021.
How many floors does Tower -27 have?
30 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology