Deedo IDDP-THN-WPGMCompletion was pushed back 1 year to Jun 2025, and that date has passed too; no MahaRERA orders on record; 35% of its units are booked.
Thane (M Corp.), Thane 400601 · Promoter: E. R. Constructions
Completion was pushed back 1 year to Jun 2025, and that date has passed too
- This projectRegistered 7 Sep 2020, completion promised 30 Jun 2024, revised to 30 Jun 2025, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700026303
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700026303 | 7 Sep 2020 | 30 Jun 2024 | 30 Jun 2025 | E. R. Constructions | Project page |
Documents129
2 documents held by Deedo, 127 filings listed on MahaRERA's project page
Finance
- PAN Carde r pancard.pdf · uploaded 28 Aug 2020Source
Legal
- Legal Title reportTITLE CERTIFICATE.pdf · uploaded 27 Aug 2020Source
- Declaration Form Bform b elite residency CMOPRESS.pdf · uploaded 27 Aug 2020Source
- Other – LegalExtention Latter Project Delay for Elite Residency.pdf · uploaded 14 Jan 2025Source
- Declaration Form BForm B (Rera Extention).pdf · uploaded 14 Jan 2025Source
- Other – LegalFormat B as on 30-09-2024.pdf · uploaded 19 Mar 2025Source
Show all 129 documentsShow fewer documents
Legal
Migrated
- 1 Copy of the legal title reportTITLE CERTIFICATE.pdf · uploaded 27 Aug 2020Source
- 1 Details of encumbrancesENCUMBRANCE.pdf · uploaded 27 Aug 2020Source
- 1 Copy of Layout Approval (in case of layout)scan 001.pdf · uploaded 27 Aug 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentPERMISSION COPY-min.pdf · uploaded 27 Aug 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 27 Aug 2020Source
- 1 Declaration in FORM Bform b elite residency CMOPRESS.pdf · uploaded 27 Aug 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE RERA.pdf · uploaded 27 Aug 2020Source
- 1 Proforma of Allotment letterSELF DECL.pdf · uploaded 27 Aug 2020Source
- 1 PAN Carde r pancard.pdf · uploaded 28 Aug 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate 18-02-2023_compressed.pdf · uploaded 25 Aug 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_E R Construction.pdf · uploaded 31 Aug 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 _14-08-2023_ E R Construction_Elite Residency.pdf · uploaded 31 Aug 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2020-21 Q2.pdf · uploaded 13 Jan 2025Source
- 17 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2024-25 Q2.pdf · uploaded 13 Jan 2025Source
- 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2024-25 Q1.pdf · uploaded 13 Jan 2025Source
- 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2023-24 Q4.pdf · uploaded 13 Jan 2025Source
- 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2023-24 Q3.pdf · uploaded 13 Jan 2025Source
- 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2023-24 Q2.pdf · uploaded 13 Jan 2025Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2023-24 Q1.pdf · uploaded 13 Jan 2025Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2022-23 Q4.pdf · uploaded 13 Jan 2025Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2022-23 Q3.pdf · uploaded 13 Jan 2025Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2022-23 Q2.pdf · uploaded 13 Jan 2025Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2022-23 Q1.pdf · uploaded 13 Jan 2025Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2021-22 Q4.pdf · uploaded 13 Jan 2025Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2021-22 Q3.pdf · uploaded 13 Jan 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2021-22 Q2.pdf · uploaded 13 Jan 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2021-22 Q1.pdf · uploaded 13 Jan 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2020-21 Q4.pdf · uploaded 13 Jan 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY- 2020-21 Q3.pdf · uploaded 13 Jan 2025Source
- 1 Declaration in FORM BForm B (Rera Extention).pdf · uploaded 14 Jan 2025Source
- 17 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2024-25 Q2.pdf · uploaded 14 Jan 2025Source
- 16 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2024-25 Q1.pdf · uploaded 14 Jan 2025Source
- 15 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2023-24 Q4.pdf · uploaded 14 Jan 2025Source
- 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2023-24 Q3.pdf · uploaded 14 Jan 2025Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2023-24 Q2.pdf · uploaded 14 Jan 2025Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2023-24 Q1.pdf · uploaded 14 Jan 2025Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2022-23 Q4.pdf · uploaded 14 Jan 2025Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2022-23 Q3.pdf · uploaded 14 Jan 2025Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2022-23 Q1.pdf · uploaded 14 Jan 2025Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2022-23 Q2.pdf · uploaded 14 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2020-21 Q2.pdf · uploaded 14 Jan 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2020-21 Q3.pdf · uploaded 14 Jan 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2020-21 Q4.pdf · uploaded 14 Jan 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2021-22 Q1.pdf · uploaded 14 Jan 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2021-22 Q2.pdf · uploaded 14 Jan 2025Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2021-22 Q3.pdf · uploaded 14 Jan 2025Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2021-22 Q4.pdf · uploaded 14 Jan 2025Source
- 17 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 24-25 Q2.pdf · uploaded 14 Jan 2025Source
- 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 24-25 Q1.pdf · uploaded 14 Jan 2025Source
- 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 23-24 Q4.pdf · uploaded 14 Jan 2025Source
- 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 23-24 Q3.pdf · uploaded 14 Jan 2025Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 23-24 Q2.pdf · uploaded 14 Jan 2025Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 23-24 Q1.pdf · uploaded 14 Jan 2025Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 22-23 Q4.pdf · uploaded 14 Jan 2025Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 22-23 Q3.pdf · uploaded 14 Jan 2025Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 22-23 Q1.pdf · uploaded 14 Jan 2025Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 21-22 Q4.pdf · uploaded 14 Jan 2025Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 21-22 Q3.pdf · uploaded 14 Jan 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 21-22 Q2.pdf · uploaded 14 Jan 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 21-22 Q1.pdf · uploaded 14 Jan 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 20-21 Q4.pdf · uploaded 14 Jan 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 20-21 Q3.pdf · uploaded 14 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 20-21 Q2.pdf · uploaded 14 Jan 2025Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 22-23 Q2.pdf · uploaded 14 Jan 2025Source
- 1 Other – LegalExtention Latter Project Delay for Elite Residency.pdf · uploaded 14 Jan 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 FY 2020-21.pdf · uploaded 14 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A FY 20-21.pdf · uploaded 14 Jan 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 FY 2021-22.pdf · uploaded 14 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A FY 21-22.pdf · uploaded 14 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A FY 22-23.pdf · uploaded 14 Jan 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 FY 2022-23.pdf · uploaded 14 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A FY 23-24.pdf · uploaded 14 Jan 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 FY 2023-24.pdf · uploaded 14 Jan 2025Source
- 1 Disclosure of sold/ booked inventorySold Unsold Inventory till 30-09-2025.pdf · uploaded 10 Feb 2025Source
- 1 Other – TechnicalCompletion Schedule Elite Residency till 30-06-2025.pdf · uploaded 10 Feb 2025Source
- 2 Other – TechnicalExtention Latter Project Delay for Elite Residency.pdf · uploaded 10 Feb 2025Source
- 1 Other – LegalFormat B as on 30-09-2024.pdf · uploaded 19 Mar 2025Source
- 1 Other – LegalFormat B (Consent Letters).pdf · uploaded 26 Mar 2025Source
- 1 Declaration in FORM BNew Form B 500 Stamp Paper.pdf · uploaded 3 Apr 2025Source
Technical
- Documentscan 001.pdf · uploaded 27 Aug 2020Source
- DocumentPERMISSION COPY-min.pdf · uploaded 27 Aug 2020Source
- Other – TechnicalCompletion Schedule Elite Residency till 30-06-2025.pdf · uploaded 10 Feb 2025Source
- Other – TechnicalExtention Latter Project Delay for Elite Residency.pdf · uploaded 10 Feb 2025Source
Technical (Architect)
- DocumentForm 1 Elite Residency.pdf · uploaded 24 Sep 2024Source
- DocumentForm 1 FY- 2020-21 Q2.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2020-21 Q3.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2020-21 Q4.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2021-22 Q1.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2021-22 Q2.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2021-22 Q3.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2021-22 Q4.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2022-23 Q1.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2022-23 Q2.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2022-23 Q3.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2022-23 Q4.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2023-24 Q1.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2023-24 Q2.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2023-24 Q3.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2023-24 Q4.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2024-25 Q1.pdf · uploaded 13 Jan 2025Source
- DocumentForm 1 FY- 2024-25 Q2.pdf · uploaded 13 Jan 2025Source
Technical (Engineer)
- DocumentForm 2 Elite Residency.pdf · uploaded 24 Sep 2024Source
- DocumentForm 2 FY 20-21 Q2.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 20-21 Q3.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 20-21 Q4.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 21-22 Q1.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 21-22 Q2.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 21-22 Q3.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 21-22 Q4.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 22-23 Q1.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 22-23 Q2.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 22-23 Q3.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 22-23 Q4.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 23-24 Q1.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 23-24 Q2.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 23-24 Q3.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 23-24 Q4.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 24-25 Q1.pdf · uploaded 14 Jan 2025Source
- DocumentForm 2 FY 24-25 Q2.pdf · uploaded 14 Jan 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals27/B/1
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, 2BHK, Office space, Shop57 units in all
- Address
- 27/B/1, Suleman Haji Road, Second RabodiPIN 400601
- Village
- Thane (M Corp.), Thane taluka
- Designated bank account
- 203
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Bangi Chawl
- South
- Ideal School
- East
- Noor Masjid
- West
- Suleman Haji Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking57 units
20 of 57 units booked (35%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 24.23 sq m · 261 sq ft | 6 | 1 |
| 1BHK | 25.59 sq m · 275 sq ft | 1 | 0 |
| 1BHK | 25.59 sq m · 275 sq ft | 2 | 1 |
| 1BHK | 31.37 sq m · 338 sq ft | 1 | 0 |
| 1BHK | 33.44 sq m · 360 sq ft | 8 | 8 |
| 1RK | 17.23 sq m · 185 sq ft | 1 | 0 |
| 1RK | 18.67 sq m · 201 sq ft | 6 | 1 |
| 1RK | 21.94 sq m · 236 sq ft | 1 | 0 |
Show all 28 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1RK | 22.14 sq m · 238 sq ft | 2 | 0 |
| 2BHK | 35.52 sq m · 382 sq ft | 1 | 0 |
| 2BHK | 38.89 sq m · 419 sq ft | 6 | 1 |
| 2BHK | 42.5 sq m · 457 sq ft | 1 | 1 |
| 2BHK | 43.77 sq m · 471 sq ft | 4 | 2 |
| 2BHK | 43.87 sq m · 472 sq ft | 3 | 2 |
| 2BHK | 54.36 sq m · 585 sq ft | 1 | 1 |
| 2BHK | 54.36 sq m · 585 sq ft | 1 | 1 |
| Office space | 15.18 sq m · 163 sq ft | 1 | 0 |
| Office space | 19.73 sq m · 212 sq ft | 1 | 0 |
| Office space | 21.02 sq m · 226 sq ft | 1 | 0 |
| Office space | 27.34 sq m · 294 sq ft | 1 | 0 |
| Office space | 28.78 sq m · 310 sq ft | 1 | 1 |
| Office space | 45.97 sq m · 495 sq ft | 1 | 0 |
| Office space | 51.58 sq m · 555 sq ft | 1 | 0 |
| Shop | 9.33 sq m · 100 sq ft | 1 | 0 |
| Shop | 9.42 sq m · 101 sq ft | 1 | 0 |
| Shop | 12.54 sq m · 135 sq ft | 1 | 0 |
| Shop | 18.36 sq m · 198 sq ft | 1 | 0 |
| Shop | 19.58 sq m · 211 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals8
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Makarand Laxman Toraskar | — |
| Architect | Makrand Toraskar And Associates | — |
| Chartered accountant | Bg Patil And Associates | — |
| Chartered accountant | Bhushan Patil | — |
| Chartered accountant | Mandar Kamalakar Patil | — |
| Chartered accountant | Vikash Kumar | — |
| Engineer | Anand Jayprakash Sawant | — |
| Engineer | Pentacon Structural Consultant Pvt Ltd | — |
Source: MahaRERA project page. Contact details are not shown.