Central Park
Deedo IDDP-THN-FP7ACompletion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 39% of its units are booked.
Thane (M Corp.), Thane 400612 · by Harmain Enterprises
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2028
- This projectRegistered 25 Mar 2022, completion promised 31 Dec 2027, revised to 30 Apr 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- Building No 116 floors · 239 units48% booked
- Building No 216 floors · 196 units29% booked
- Building No 316 floors · 194 units38% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700034243
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700034243 | 25 Mar 2022 | 31 Dec 2027 | 30 Apr 2028 | Harmain Enterprises | Project page |
Documents90
1 document held by Deedo, 89 filings listed on MahaRERA's project page
Show all 90 documentsShow fewer documents
Migrated
- 3 Copy of Layout Approval (in case of layout)3.pdf · uploaded 8 Mar 2022Source
- 4 Copy of Layout Approval (in case of layout)4.pdf · uploaded 8 Mar 2022Source
- 5 Copy of Layout Approval (in case of layout)5.pdf · uploaded 8 Mar 2022Source
- 6 Copy of Layout Approval (in case of layout)6.pdf · uploaded 8 Mar 2022Source
- 7 Copy of Layout Approval (in case of layout)7.pdf · uploaded 8 Mar 2022Source
- 8 Copy of Layout Approval (in case of layout)8.pdf · uploaded 8 Mar 2022Source
- 9 Copy of Layout Approval (in case of layout)9.pdf · uploaded 8 Mar 2022Source
- 10 Copy of Layout Approval (in case of layout)10.pdf · uploaded 8 Mar 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 8 Mar 2022Source
- 1 Proforma of Allotment letterFinal AGR.pdf · uploaded 8 Mar 2022Source
- 1 Details of encumbrancesEncumbrances.pdf · uploaded 11 Mar 2022Source
- 1 Declaration about Commencement CertificateDeclaration of CC.pdf · uploaded 11 Mar 2022Source
- 1 CERSAI detailsCERSAI Report.pdf · uploaded 11 Mar 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Harmain Enterprises.pdf · uploaded 11 Mar 2022Source
- 1 Building Plan Approval / NA Order for plotted development1.pdf · uploaded 18 Mar 2022Source
- 1 Declaration in FORM BForm B Notarised.pdf · uploaded 18 Mar 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 2 May 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 2 May 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)HARMAIN-FORM 1 - ARCHITECT CERTIFICATE - 30092023 - COMP.pdf · uploaded 10 Nov 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)HARMAIN- FORM 5 - ANNULA REPORT - 2022-23.pdf · uploaded 10 Nov 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 -CENTRAL PARK- ARCHITECT CERT - 31032024.pdf · uploaded 19 Jun 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - CENTRAL PARK-ENGINEERS CERT - 31032024.pdf · uploaded 19 Jun 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - HARMAIN - CA CERTIFICATE - 31032024.pdf · uploaded 19 Jun 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 - HARMAIN - ANNUAL REPORT - 2023-24.pdf · uploaded 19 Jun 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - ARCHITECT CERTIFICATE.pdf · uploaded 19 Feb 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - ARCHITECT CERT - DEC 24.pdf · uploaded 19 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - CA CERT -HARMAINENTP - 30-09-2024.pdf · uploaded 19 Feb 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - CA CERT - HARMAINENTP - 31-12-2024.pdf · uploaded 19 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - ENGINEERS CERTFICATE -Harmain Entp 30 09 2024.pdf · uploaded 19 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - ENGINEERS CERTFICATE -Harmain Entp 31 12 2024.pdf · uploaded 19 Feb 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentHARMAIN CC.pdf · uploaded 7 Mar 2025Source
- 1 Copy of Layout Approval (in case of layout)HARMAIN DRWAING - 1 TO 6.pdf · uploaded 18 Mar 2025Source
- 2 Copy of Layout Approval (in case of layout)HARMAIN DRWAING - 7 TO 12.pdf · uploaded 18 Mar 2025Source
- 3 Copy of Layout Approval (in case of layout)HARMAIN DRWAING - 13 TO 18.pdf · uploaded 18 Mar 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentHARMAIN DRWAING - 1.pdf · uploaded 18 Mar 2025Source
- Form 5 (FY 2022-2023)HARMAIN- FORM 5 - ANNULA REPORT - 2022-23.pdf · uploaded 20 May 2026Source
- Form 5 (FY 2023-2024)FORM 5 - HARMAIN - ANNUAL REPORT - 2023-24.pdf · uploaded 20 May 2026Source
- Form 5 (FY 2024-2025)Foem 5 - Harmain - 24-25.pdf · uploaded 20 May 2026Source
- Form 1FORM 1 - central park harmain rera 31-03-2025.pdf · uploaded 21 May 2026Source
- Form 2FORM - 2_HARMAIN ENTERPRISES - MARCH-25 - 31032025 DS.pdf · uploaded 21 May 2026Source
- Form 3FORM 3 - HARMAIN- MARCH-2025- 20042025.pdf · uploaded 21 May 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD AND BOOKED INVENTORY_ HARMAIN ENTP - March-25.pdf · uploaded 21 May 2026Source
- Withdrawal Update Form 1FORM 1 - central park harmain rera 31-03-2025.pdf · uploaded 21 May 2026Source
- Withdrawal Update Form 1FORM 1 - central park harmain rera 31-03-2025.pdf · uploaded 21 May 2026Source
- Withdrawal Update Form 1FORM 1 - HARMAIN ENTP- 30062025.pdf · uploaded 21 May 2026Source
- Withdrawal Update Form 2FORM - 2_HARMAIN ENTERPRISES - MARCH-25 - 31032025 DS.pdf · uploaded 21 May 2026Source
- Withdrawal Update Form 2FORM - 2_HARMAIN ENTERPRISES - JUNE-25 - 30062025 DS.pdf · uploaded 21 May 2026Source
- Withdrawal Update Form 2FORM - 2_HARMAIN ENTERPRISES - JUNE-25 - 30062025 DS.pdf · uploaded 21 May 2026Source
- Withdrawal Update Form 3FORM 3 - HARMAIN- MARCH-2025- 20042025.pdf · uploaded 21 May 2026Source
- Withdrawal Update Form 3FORM 3 - HARMAIN- JUNE -2025- 20042025.pdf · uploaded 21 May 2026Source
- Withdrawal Update Form 3FORM 3 - HARMAIN- JUNE -2025- 20042025.pdf · uploaded 21 May 2026Source
- Withdrawal Update Form 1FORM 1 - central park harmain rera 31-12-2025.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 1FORM 1 -central park harmain rera 30-09-2025.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 2FORM - 2_HARMAIN ENTERPRISES - DEC-25 - 31122025 DS.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 2FORM - 2_HARMAIN ENTERPRISES - SEPT-25 - 30092025 DS.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 3FORM 3 - HARMAIN- DEC-2025- 20042025.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 3FORM 3 - HARMAIN- SEPT-2025- 20042025.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 1FORM 1 - central park harmain rera 30-03-2026 sign.pdf · uploaded 6 Jun 2026Source
- Withdrawal Update Form 2fORM-2 - Harmain Entp- MARCH-26 -signed.pdf · uploaded 6 Jun 2026Source
- Withdrawal Update Form 3FORM-3MARCH-26.pdf · uploaded 6 Jun 2026Source
- Form 5 (FY 2025-2026)form 5.pdf · uploaded 9 Jun 2026Source
Technical
- Document1.pdf · uploaded 8 Mar 2022Source
- Document2.pdf · uploaded 8 Mar 2022Source
- Document3.pdf · uploaded 8 Mar 2022Source
- Document4.pdf · uploaded 8 Mar 2022Source
- Document5.pdf · uploaded 8 Mar 2022Source
- Document6.pdf · uploaded 8 Mar 2022Source
- Document7.pdf · uploaded 8 Mar 2022Source
- Document8.pdf · uploaded 8 Mar 2022Source
- Document9.pdf · uploaded 8 Mar 2022Source
- Document10.pdf · uploaded 8 Mar 2022Source
- Document1.pdf · uploaded 18 Mar 2022Source
- DocumentHARMAIN DRWAING - 1 TO 6.pdf · uploaded 18 Mar 2025Source
- DocumentHARMAIN DRWAING - 7 TO 12.pdf · uploaded 18 Mar 2025Source
- DocumentHARMAIN DRWAING - 13 TO 18.pdf · uploaded 18 Mar 2025Source
- DocumentHARMAIN DRWAING - 1.pdf · uploaded 18 Mar 2025Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 53/3, 54/3
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK, Office space, Shop, 1BHK629 units in all
- Address
- 53/3, 54/3, 55/4, M A Road, Near Tmc Stadium, Kausa, MumbraPIN 400612
- Village
- Thane (M Corp.), Thane taluka
- Location
- 19.17348, 73.03088
- Land area for this project
- 9,591 sq m (1,03,237 sq ft)
- Permissible built-up area
- 6,578 sq m (70,805 sq ft)
- Sanctioned built-up area
- 6,578 sq m (70,805 sq ft)
- Recreational open space
- 2,166 sq m (23,317 sq ft)
- Designated bank account
- 21
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
53/3, 54/3, 55/4
Boundaries
- North
- S No 52
- South
- Central Empire
- East
- S No 70
- West
- 30 Mtr Dp Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking629 units
245 of 629 units booked (39%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building No 1 | 2BHK | 48.47 sq m · 522 sq ft | 40 | 21 |
| Building No 1 | 2BHK | 55.53 sq m · 598 sq ft | 80 | 44 |
| Building No 1 | 2BHK | 57.31 sq m · 617 sq ft | 40 | 30 |
| Building No 1 | 3BHK | 78.38 sq m · 844 sq ft | 40 | 16 |
| Building No 1 | Office space | 55.71 sq m · 600 sq ft | 4 | 0 |
| Building No 1 | Office space | 57.21 sq m · 616 sq ft | 5 | 1 |
| Building No 1 | Office space | 58.86 sq m · 634 sq ft | 4 | 0 |
| Building No 1 | Office space | 67.15 sq m · 723 sq ft | 4 | 0 |
Show all 25 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building No 1 | Office space | 97.83 sq m · 1,053 sq ft | 4 | 0 |
| Building No 1 | Shop | 17.61 sq m · 190 sq ft | 2 | 1 |
| Building No 1 | Shop | 20.95 sq m · 226 sq ft | 2 | 0 |
| Building No 1 | Shop | 21.95 sq m · 236 sq ft | 2 | 1 |
| Building No 1 | Shop | 22.07 sq m · 238 sq ft | 2 | 0 |
| Building No 1 | Shop | 28.33 sq m · 305 sq ft | 2 | 0 |
| Building No 1 | Shop | 28.34 sq m · 305 sq ft | 4 | 0 |
| Building No 1 | Shop | 28.52 sq m · 307 sq ft | 2 | 1 |
| Building No 1 | Shop | 37.27 sq m · 401 sq ft | 2 | 0 |
| Building No 2 | 1BHK | 38.3 sq m · 412 sq ft | 118 | 26 |
| Building No 2 | 1BHK | 38.48 sq m · 414 sq ft | 22 | 8 |
| Building No 2 | 2BHK | 45.38 sq m · 488 sq ft | 33 | 16 |
| Building No 2 | 2BHK | 50.23 sq m · 541 sq ft | 23 | 6 |
| Building No 3 | 1BHK | 38.3 sq m · 412 sq ft | 109 | 28 |
| Building No 3 | 1BHK | 38.48 sq m · 414 sq ft | 23 | 12 |
| Building No 3 | 2BHK | 45.38 sq m · 488 sq ft | 41 | 23 |
| Building No 3 | 2BHK | 50.23 sq m · 541 sq ft | 21 | 11 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sachin Charpe | — |
| Chartered accountant | Abdul Kaleem A Choudhari | — |
| Chartered accountant | Jamil Ahmed Shaikh | — |
| Chartered accountant | S. R. Siddiqui & Co. | — |
| Engineer | Sscons Consulting Structural Engineers | — |
Source: MahaRERA project page. Contact details are not shown.