Central Park

Deedo IDDP-THN-FP7A

Completion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 39% of its units are booked.

Thane (M Corp.), Thane 400612 · by Harmain Enterprises

DeliveryExtended 4 moPromised Dec 2027 · now due Apr 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales39% booked245 of 629 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2028

  • This projectRegistered 25 Mar 2022, completion promised 31 Dec 2027, revised to 30 Apr 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700034243
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170003424325 Mar 202231 Dec 202730 Apr 2028Harmain EnterprisesProject page
Documents90

1 document held by Deedo, 89 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card of Harmain.pdf · uploaded 8 Mar 2022Source

Legal

  • Legal Title reportTitle Report.pdf · uploaded 8 Mar 2022Source
  • Declaration Form BForm B Notarised.pdf · uploaded 18 Mar 2022Source

Migrated

  • 1 PAN CardPAN Card of Harmain.pdf · uploaded 8 Mar 2022Source
  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 8 Mar 2022Source
  • 1 Copy of Layout Approval (in case of layout)1.pdf · uploaded 8 Mar 2022Source
  • 2 Copy of Layout Approval (in case of layout)2.pdf · uploaded 8 Mar 2022Source
Show all 90 documentsShow fewer documents

Migrated

  • 3 Copy of Layout Approval (in case of layout)3.pdf · uploaded 8 Mar 2022Source
  • 4 Copy of Layout Approval (in case of layout)4.pdf · uploaded 8 Mar 2022Source
  • 5 Copy of Layout Approval (in case of layout)5.pdf · uploaded 8 Mar 2022Source
  • 6 Copy of Layout Approval (in case of layout)6.pdf · uploaded 8 Mar 2022Source
  • 7 Copy of Layout Approval (in case of layout)7.pdf · uploaded 8 Mar 2022Source
  • 8 Copy of Layout Approval (in case of layout)8.pdf · uploaded 8 Mar 2022Source
  • 9 Copy of Layout Approval (in case of layout)9.pdf · uploaded 8 Mar 2022Source
  • 10 Copy of Layout Approval (in case of layout)10.pdf · uploaded 8 Mar 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 8 Mar 2022Source
  • 1 Proforma of Allotment letterFinal AGR.pdf · uploaded 8 Mar 2022Source
  • 1 Details of encumbrancesEncumbrances.pdf · uploaded 11 Mar 2022Source
  • 1 Declaration about Commencement CertificateDeclaration of CC.pdf · uploaded 11 Mar 2022Source
  • 1 CERSAI detailsCERSAI Report.pdf · uploaded 11 Mar 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Harmain Enterprises.pdf · uploaded 11 Mar 2022Source
  • 1 Building Plan Approval / NA Order for plotted development1.pdf · uploaded 18 Mar 2022Source
  • 1 Declaration in FORM BForm B Notarised.pdf · uploaded 18 Mar 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 2 May 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 2 May 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)HARMAIN-FORM 1 - ARCHITECT CERTIFICATE - 30092023 - COMP.pdf · uploaded 10 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)HARMAIN- FORM 5 - ANNULA REPORT - 2022-23.pdf · uploaded 10 Nov 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 -CENTRAL PARK- ARCHITECT CERT - 31032024.pdf · uploaded 19 Jun 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - CENTRAL PARK-ENGINEERS CERT - 31032024.pdf · uploaded 19 Jun 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - HARMAIN - CA CERTIFICATE - 31032024.pdf · uploaded 19 Jun 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 - HARMAIN - ANNUAL REPORT - 2023-24.pdf · uploaded 19 Jun 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - ARCHITECT CERTIFICATE.pdf · uploaded 19 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - ARCHITECT CERT - DEC 24.pdf · uploaded 19 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - CA CERT -HARMAINENTP - 30-09-2024.pdf · uploaded 19 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - CA CERT - HARMAINENTP - 31-12-2024.pdf · uploaded 19 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - ENGINEERS CERTFICATE -Harmain Entp 30 09 2024.pdf · uploaded 19 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - ENGINEERS CERTFICATE -Harmain Entp 31 12 2024.pdf · uploaded 19 Feb 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentHARMAIN CC.pdf · uploaded 7 Mar 2025Source
  • 1 Copy of Layout Approval (in case of layout)HARMAIN DRWAING - 1 TO 6.pdf · uploaded 18 Mar 2025Source
  • 2 Copy of Layout Approval (in case of layout)HARMAIN DRWAING - 7 TO 12.pdf · uploaded 18 Mar 2025Source
  • 3 Copy of Layout Approval (in case of layout)HARMAIN DRWAING - 13 TO 18.pdf · uploaded 18 Mar 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentHARMAIN DRWAING - 1.pdf · uploaded 18 Mar 2025Source
  • Form 5 (FY 2022-2023)HARMAIN- FORM 5 - ANNULA REPORT - 2022-23.pdf · uploaded 20 May 2026Source
  • Form 5 (FY 2023-2024)FORM 5 - HARMAIN - ANNUAL REPORT - 2023-24.pdf · uploaded 20 May 2026Source
  • Form 5 (FY 2024-2025)Foem 5 - Harmain - 24-25.pdf · uploaded 20 May 2026Source
  • Form 1FORM 1 - central park harmain rera 31-03-2025.pdf · uploaded 21 May 2026Source
  • Form 2FORM - 2_HARMAIN ENTERPRISES - MARCH-25 - 31032025 DS.pdf · uploaded 21 May 2026Source
  • Form 3FORM 3 - HARMAIN- MARCH-2025- 20042025.pdf · uploaded 21 May 2026Source
  • Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD AND BOOKED INVENTORY_ HARMAIN ENTP - March-25.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 1FORM 1 - central park harmain rera 31-03-2025.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 1FORM 1 - central park harmain rera 31-03-2025.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 1FORM 1 - HARMAIN ENTP- 30062025.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 2FORM - 2_HARMAIN ENTERPRISES - MARCH-25 - 31032025 DS.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 2FORM - 2_HARMAIN ENTERPRISES - JUNE-25 - 30062025 DS.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 2FORM - 2_HARMAIN ENTERPRISES - JUNE-25 - 30062025 DS.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 3FORM 3 - HARMAIN- MARCH-2025- 20042025.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 3FORM 3 - HARMAIN- JUNE -2025- 20042025.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 3FORM 3 - HARMAIN- JUNE -2025- 20042025.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 1FORM 1 - central park harmain rera 31-12-2025.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 1FORM 1 -central park harmain rera 30-09-2025.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 2FORM - 2_HARMAIN ENTERPRISES - DEC-25 - 31122025 DS.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 2FORM - 2_HARMAIN ENTERPRISES - SEPT-25 - 30092025 DS.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 3FORM 3 - HARMAIN- DEC-2025- 20042025.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 3FORM 3 - HARMAIN- SEPT-2025- 20042025.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 1FORM 1 - central park harmain rera 30-03-2026 sign.pdf · uploaded 6 Jun 2026Source
  • Withdrawal Update Form 2fORM-2 - Harmain Entp- MARCH-26 -signed.pdf · uploaded 6 Jun 2026Source
  • Withdrawal Update Form 3FORM-3MARCH-26.pdf · uploaded 6 Jun 2026Source
  • Form 5 (FY 2025-2026)form 5.pdf · uploaded 9 Jun 2026Source

Technical

  • Document1.pdf · uploaded 8 Mar 2022Source
  • Document2.pdf · uploaded 8 Mar 2022Source
  • Document3.pdf · uploaded 8 Mar 2022Source
  • Document4.pdf · uploaded 8 Mar 2022Source
  • Document5.pdf · uploaded 8 Mar 2022Source
  • Document6.pdf · uploaded 8 Mar 2022Source
  • Document7.pdf · uploaded 8 Mar 2022Source
  • Document8.pdf · uploaded 8 Mar 2022Source
  • Document9.pdf · uploaded 8 Mar 2022Source
  • Document10.pdf · uploaded 8 Mar 2022Source
  • Document1.pdf · uploaded 18 Mar 2022Source
  • DocumentHARMAIN DRWAING - 1 TO 6.pdf · uploaded 18 Mar 2025Source
  • DocumentHARMAIN DRWAING - 7 TO 12.pdf · uploaded 18 Mar 2025Source
  • DocumentHARMAIN DRWAING - 13 TO 18.pdf · uploaded 18 Mar 2025Source
  • DocumentHARMAIN DRWAING - 1.pdf · uploaded 18 Mar 2025Source

Technical (Architect)

  • DocumentFORM 1 - ARCHITECT CERTIFICATE.pdf · uploaded 19 Feb 2025Source
  • DocumentFORM 1 - ARCHITECT CERT - DEC 24.pdf · uploaded 19 Feb 2025Source
  • DocumentFORM 1 - central park harmain rera 30-03-2026 sign.pdf · uploaded 6 Jun 2026Source

Technical (Engineer)

  • DocumentFORM 2 - ENGINEERS CERTFICATE -Harmain Entp 30 09 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentFORM 2 - ENGINEERS CERTFICATE -Harmain Entp 31 12 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentfORM-2 - Harmain Entp- MARCH-26 -signed.pdf · uploaded 6 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 53/3, 54/3

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK, Office space, Shop, 1BHK629 units in all
Address
53/3, 54/3, 55/4, M A Road, Near Tmc Stadium, Kausa, MumbraPIN 400612
Village
Thane (M Corp.), Thane taluka
Land area for this project
9,591 sq m (1,03,237 sq ft)
Permissible built-up area
6,578 sq m (70,805 sq ft)
Sanctioned built-up area
6,578 sq m (70,805 sq ft)
Recreational open space
2,166 sq m (23,317 sq ft)
Designated bank account
21
Developed in phases
Yes

Survey, CTS, gat or plot numbers

53/354/355/4

Land as published on MahaRERA's project page

53/3, 54/3, 55/4

Boundaries

North
S No 52
South
Central Empire
East
S No 70
West
30 Mtr Dp Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking629 units

245 of 629 units booked (39%), as the promoter reported to MahaRERA

2BHK · 278 units3BHK · 40 unitsOffice space · 21 unitsShop · 18 units1BHK · 272 units
BuildingTypeCarpet areaUnitsBooked
Building No 12BHK48.47 sq m · 522 sq ft4021
Building No 12BHK55.53 sq m · 598 sq ft8044
Building No 12BHK57.31 sq m · 617 sq ft4030
Building No 13BHK78.38 sq m · 844 sq ft4016
Building No 1Office space55.71 sq m · 600 sq ft40
Building No 1Office space57.21 sq m · 616 sq ft51
Building No 1Office space58.86 sq m · 634 sq ft40
Building No 1Office space67.15 sq m · 723 sq ft40
Show all 25 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Building No 1Office space97.83 sq m · 1,053 sq ft40
Building No 1Shop17.61 sq m · 190 sq ft21
Building No 1Shop20.95 sq m · 226 sq ft20
Building No 1Shop21.95 sq m · 236 sq ft21
Building No 1Shop22.07 sq m · 238 sq ft20
Building No 1Shop28.33 sq m · 305 sq ft20
Building No 1Shop28.34 sq m · 305 sq ft40
Building No 1Shop28.52 sq m · 307 sq ft21
Building No 1Shop37.27 sq m · 401 sq ft20
Building No 21BHK38.3 sq m · 412 sq ft11826
Building No 21BHK38.48 sq m · 414 sq ft228
Building No 22BHK45.38 sq m · 488 sq ft3316
Building No 22BHK50.23 sq m · 541 sq ft236
Building No 31BHK38.3 sq m · 412 sq ft10928
Building No 31BHK38.48 sq m · 414 sq ft2312
Building No 32BHK45.38 sq m · 488 sq ft4123
Building No 32BHK50.23 sq m · 541 sq ft2111

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSachin Charpe—
Chartered accountantAbdul Kaleem A Choudhari—
Chartered accountantJamil Ahmed Shaikh—
Chartered accountantS. R. Siddiqui & Co.—
EngineerSscons Consulting Structural Engineers—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology