Extended 4 mo12 floorsRERA P51700027277
Building 1, Central Empire
Deedo IDDP-THN-PHQZ-1MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked68%23 of 34 · MahaRERA
Completion30 Oct 202630 Jun 2026 · revised
Units & parking in Building 1
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1.5 BHK | 45.3 m² (487 sq.ft) | 15 | 11 |
| 2BHK | 50.7 m² (546 sq.ft) | 13 | 12 |
| SHOP NO. 1 | 29.2 m² (314 sq.ft) | 1 | 0 |
| SHOP NO. 2 | 14.2 m² (153 sq.ft) | 1 | 0 |
| SHOP NO.3 | 17.1 m² (184 sq.ft) | 1 | 0 |
| SHOP NO. 4 | 17.1 m² (184 sq.ft) | 1 | 0 |
| SHOP NO. 5 | 16.3 m² (175 sq.ft) | 1 | 0 |
| SHOP NO. 6 | 20.7 m² (222 sq.ft) | 1 | 0 |
As registered with MahaRERA
- RERA registration
- P51700027277 · registered 1 Dec 2020
- Promised completion
- 30 Jun 2026
- Revised completion
- 30 Oct 2026
- Sanctioned habitable floors
- 12
- Sanctioned floors (incl. basement, stilt, podium)
- 12
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-THN-PHQZ-1
Questions about Building 1
When is Building 1 due for completion?
The MahaRERA registration promises 30 Jun 2026, revised to 30 Oct 2026.
How many floors does Building 1 have?
12 sanctioned habitable floors, as registered with MahaRERA.