Skip to content
Residential / Group Housing · 1 building · 24 unitsRERA P51700051506

Bharat Residency C Wing

Deedo IDDP-THN-92DC

Completion was pushed back 1 year and 4 months to Mar 2026, and that date has passed too; no MahaRERA orders on record; 38% of its units are booked.

Rambaug, Thane 421301 · by Shiv Sai Developers

Delivery2 yrs latePromised Nov 2024 · revised Mar 2026 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales38% booked9 of 24 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 1 year and 4 months to Mar 2026, and that date has passed too

  • This projectRegistered 23 Jun 2023, completion promised 30 Nov 2024, revised to 31 Mar 2026, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700051506
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170005150623 Jun 202330 Nov 202431 Mar 2026Shiv Sai DevelopersProject page
Documents59

2 documents held by Deedo, 57 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN Card Shiv sai developers.pdf · uploaded 12 Nov 2022Source

Legal

  • Declaration Form BB Form_11zon.pdf · uploaded 12 Nov 2022Source
  • Legal Title reporttital certificate.pdf · uploaded 8 Dec 2022Source

Migrated

  • 1 PAN CardPAN Card Shiv sai developers.pdf · uploaded 12 Nov 2022Source
  • 1 Copy of Layout Approval (in case of layout)blue print lay out_11zon.pdf · uploaded 12 Nov 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentblue print floor plAN_11zon_11zon.pdf · uploaded 12 Nov 2022Source
Show all 59 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentc c copy.pdf · uploaded 12 Nov 2022Source
  • 1 Declaration in FORM BB Form_11zon.pdf · uploaded 12 Nov 2022Source
  • 1 Declaration about Commencement Certificatedeclaration CC.pdf · uploaded 17 Nov 2022Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 17 Nov 2022Source
  • 1 Copy of the legal title reporttital certificate.pdf · uploaded 8 Dec 2022Source
  • 1 a Details of encumbrances concerned to FinanceFinance certificate.pdf · uploaded 8 Dec 2022Source
  • 2 a Details of encumbrances concerned to FinanceENCUMBRANCE LETTER.pdf · uploaded 8 Dec 2022Source
  • 1 b Details of encumbrances concerned to LegalFinance certificate.pdf · uploaded 8 Dec 2022Source
  • 2 b Details of encumbrances concerned to LegalENCUMBRANCE LETTER.pdf · uploaded 8 Dec 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samebank details.pdf · uploaded 8 Dec 2022Source
  • 1 Deviation Report with respect to Allotment letterAL deviation.pdf · uploaded 8 Dec 2022Source
  • 1 Deviation Report with respect to model copy of AgreementAfs deviation.pdf · uploaded 8 Dec 2022Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsPRADEEP BHOIR.pdf · uploaded 14 Feb 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsH BHOIR.pdf · uploaded 22 Feb 2023Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsRUPESH BHOIR.pdf · uploaded 22 Feb 2023Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsSANJYA BHOIR.pdf · uploaded 22 Feb 2023Source
  • 5 Disclosure of Interest in Other Real Estate OrganizationsSANTOSH BHOIR.pdf · uploaded 22 Feb 2023Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 22 Feb 2023Source
  • 1 Proforma of Agreement for saleshiv sai developer Bhoir.pdf · uploaded 16 Mar 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form_3_BW.pdf · uploaded 13 May 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 29 May 2023Source
  • 1 Other – TechnicalPlinth Completion Certificate.pdf · uploaded 29 May 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Progress Letter 22-09-2022.pdf · uploaded 21 Mar 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Progress Letter 22-12-2022.pdf · uploaded 21 Mar 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Progress Letter 22-03-2023.pdf · uploaded 21 Mar 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Progress Letter 22-06-2023.pdf · uploaded 21 Mar 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Progress Letter 22-09-2023.pdf · uploaded 21 Mar 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Progress Letter 22-12-2023.pdf · uploaded 21 Mar 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ref_77_81_875_ R-6_2024_RUPESH BHOIR PRADIP BHOIR NF_(22-12-2023).pdf · uploaded 8 Apr 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ref_77_81_875_ R-1_2022_RUPESH BHOIR PRADIP BHOIR NF_(22-09-2022).pdf · uploaded 8 Apr 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ref_77_81_875_ R-2_2022_RUPESH BHOIR PRADIP BHOIR NF_(22-12-2022).pdf · uploaded 8 Apr 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ref_77_81_875_ R-3_2023_RUPESH BHOIR PRADIP BHOIR NF_(22-03-2023).pdf · uploaded 8 Apr 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ref_77_81_875_ R-4_2024_RUPESH BHOIR PRADIP BHOIR NF_(22-06-2023).pdf · uploaded 8 Apr 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ref_77_81_875_ R-5_2024_RUPESH BHOIR PRADIP BHOIR NF_(22-09-2023).pdf · uploaded 8 Apr 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect letter C wing 20 12 24 NEW.pdf · uploaded 18 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)SHIV SAI DEVELOPERS FORM 3 FY 23-24 SIGNED.pdf · uploaded 18 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Dec 2022.pdf · uploaded 18 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Mar 2023.pdf · uploaded 18 Feb 2025Source
  • 1 Disclosure of sold/ booked inventorydiscolsure of sold C wing.pdf · uploaded 18 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)SHIV SAI DEVELOPERS FORM 5 FY 23-24 SIGNED.pdf · uploaded 18 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)DEC 24 Form 3.pdf · uploaded 25 Feb 2025Source
  • Form 5 (FY 2023-2024)SHIV SAI DEVELOPERS FORM 5 FY 23-24 SIGNED.pdf · uploaded 3 Apr 2026Source
  • Form 5 (FY 2024-2025)Form 5 FY 24-25 Signed.pdf · uploaded 3 Apr 2026Source

Technical

  • Documentblue print lay out_11zon.pdf · uploaded 12 Nov 2022Source
  • Documentblue print floor plAN_11zon_11zon.pdf · uploaded 12 Nov 2022Source
  • Other – TechnicalPlinth Completion Certificate.pdf · uploaded 29 May 2023Source

Technical (Architect)

  • Documentarchitect letter C wing 20 12 24 NEW.pdf · uploaded 18 Feb 2025Source
  • DocumentProgress Letter 22-12-2023.pdf · uploaded 3 Apr 2026Source

Technical (Engineer)

  • DocumentRef_77_81_875_ R-5_2024_RUPESH BHOIR PRADIP BHOIR NF_(22-09-2023).pdf · uploaded 8 Apr 2024Source
  • DocumentForm 2 Engineer Dec 2022.pdf · uploaded 18 Feb 2025Source
  • DocumentForm 2 Engineer Mar 2023.pdf · uploaded 18 Feb 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S NO 84 HISS NO 7+11B

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK24 units in all
Address
S No 84 Hiss No 7+11b, Rambaug Lane No 4 End, KalyanPIN 421301
Village
Rambaug, Kalyan taluka
Land area for this project
1,719 sq m (18,500 sq ft)
Permissible built-up area
1,719 sq m (18,500 sq ft)
Sanctioned built-up area
1,719 sq m (18,500 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

S NO 84 HISS NO 7+11B

Land as published on MahaRERA's project page

S NO 84 HISS NO 7+11B

Boundaries

North
19 14 48 7
South
Road
East
73 08 16 6
West
Jeevan Sandhya Apartment

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking24 units

9 of 24 units booked (38%), as the promoter reported to MahaRERA

1BHK · 8 units2BHK · 16 units
TypeCarpet areaUnitsBooked
1BHK37.93 sq m · 408 sq ft87
2BHK53.44 sq m · 575 sq ft80
2BHK54.4 sq m · 586 sq ft82

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShirish Nachane—
Chartered accountantRachna Thakkar—
Chartered accountantYash Kotecha—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology