Residential / Group Housing · 1 building · 173 unitsRERA P51700051520

Gami Ved

Deedo IDDP-THN-48JE

Completion was pushed back 4 months, to Oct 2027; no MahaRERA orders on record; 31% of its units are booked.

Nerul, Thane 400706 · by Ambalal Bhanji Gami

DeliveryExtended 4 moPromised Jun 2027 · now due Oct 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales31% booked54 of 173 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Oct 2027

  • This projectRegistered 23 Jun 2023, completion promised 30 Jun 2027, revised to 30 Oct 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700051520
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170005152023 Jun 202330 Jun 202730 Oct 2027Ambalal Bhanji GamiProject page
Documents126

1 document held by Deedo, 125 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardpan card Ambalal Gami.pdf · uploaded 10 May 2023Source

Legal

  • Declaration Form BFORM -B (Promoter).pdf · uploaded 11 May 2023Source
  • Legal Title reportShort Title - Gami Ved_11zon.pdf · uploaded 19 May 2023Source

Migrated

  • 1 PAN Cardpan card Ambalal Gami.pdf · uploaded 10 May 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC_11zon.pdf · uploaded 10 May 2023Source
  • 1 a Details of encumbrances concerned to FinanceNo ENCUMBRANCE LETTER -Dues.pdf · uploaded 11 May 2023Source
  • 2 a Details of encumbrances concerned to FinanceNo ENCUMBRANCE LETTER Litigations.pdf · uploaded 11 May 2023Source
Show all 126 documentsShow fewer documents

Migrated

  • 1 b Details of encumbrances concerned to LegalNo ENCUMBRANCE LETTER -Dues.pdf · uploaded 11 May 2023Source
  • 2 b Details of encumbrances concerned to LegalNo ENCUMBRANCE LETTER Litigations.pdf · uploaded 11 May 2023Source
  • 1 Copy of Layout Approval (in case of layout)1 Copy of Layout Approval (in case of layout).pdf · uploaded 11 May 2023Source
  • 1 Building Plan Approval / NA Order for plotted development1 Copy of Layout Approval (in case of layout).pdf · uploaded 11 May 2023Source
  • 2 Building Plan Approval / NA Order for plotted development2 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 11 May 2023Source
  • 3 Building Plan Approval / NA Order for plotted development3 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 11 May 2023Source
  • 1 Declaration about Commencement CertificateFORMAT D - For Single Building.pdf · uploaded 11 May 2023Source
  • 1 Declaration in FORM BFORM -B (Promoter).pdf · uploaded 11 May 2023Source
  • 1 CERSAI detailsDECLARATION of Cersai.pdf · uploaded 11 May 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A -AMBALAL BHANJI GAMI.pdf · uploaded 11 May 2023Source
  • 1 Copy of the legal title reportShort Title - Gami Ved_11zon.pdf · uploaded 19 May 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report of Alloment_New Parth Developers_Gami Ved_17052023.pdf · uploaded 23 May 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3 Gami Ved_compressed.pdf · uploaded 25 May 2023Source
  • 1 Proforma of Allotment letterAllotment letter as per RERA_New Parth Developers_Gami Ved_17052023 (1).pdf · uploaded 25 May 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A - Seperate Bank Account Details.pdf · uploaded 25 May 2023Source
  • 1 Proforma of Agreement for saleAFS_New Parth Developers_Gami Ved_02062023.pdf · uploaded 5 Jun 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation-Gami Ved_compressed.pdf · uploaded 9 Jun 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Gami Ved as on June 2023.pdf · uploaded 1 Aug 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Gami Ved as on 30-06-2023.pdf · uploaded 1 Aug 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Gami Ved as on 17-08-2023.pdf · uploaded 18 Aug 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Gami Ved as on 30-09-2023.pdf · uploaded 4 Nov 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Gami Ved as on Sep 2023.pdf · uploaded 7 Nov 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Gami Ved as on 30-10-2023.pdf · uploaded 9 Nov 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Gami Ved as on June 2023.pdf · uploaded 10 Jan 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Gami Ved as on Sept 2023.pdf · uploaded 10 Jan 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Gami Ved as on Dec 2023.pdf · uploaded 10 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Gami Ved as on June 2023.pdf · uploaded 10 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Gami Ved as on Sept 2023.pdf · uploaded 10 Jan 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Gami Ved as on June 2023.pdf · uploaded 10 Jan 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Gami Ved as on Sept 2023.pdf · uploaded 10 Jan 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Gami Ved as on Dec 2023.pdf · uploaded 17 Jan 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Gami Ved as 31-12-2023.pdf · uploaded 17 Jan 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Gami Ved as on March 2024.pdf · uploaded 6 Apr 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Gami Ved as on March 2024.pdf · uploaded 12 Apr 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Gami Ved as 31-03-2024.pdf · uploaded 12 Apr 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)6 Architect’s Certificate of Percentage of Completion of Work (Form 1) (2).pdf · uploaded 20 Apr 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)6 Engineer’s Certificate on Cost Incurred on Project (Form 2) (4).pdf · uploaded 20 Apr 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)cz.pdf · uploaded 20 Apr 2024Source
  • 1 Disclosure of sold/ booked inventoryCIRCULAR 29 Gami Ved as on March 2024.pdf · uploaded 15 May 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Gami Ved as 31-05-2024.pdf · uploaded 22 Jun 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Gami Ved as on May 2024.pdf · uploaded 24 Jun 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Gami Ved as on June 2024.pdf · uploaded 8 Jul 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Gami Ved as on June 2024.pdf · uploaded 13 Jul 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Gami Ved as on June 2024.pdf · uploaded 13 Jul 2024Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Letter.pdf · uploaded 7 Oct 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Gami Ved as 30-09-2024 final.pdf · uploaded 7 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Gami Ved as on Sept 2024.pdf · uploaded 7 Oct 2024Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Letter.pdf · uploaded 7 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - Gami Ved for FY 2023-24.pdf · uploaded 16 Oct 2024Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - Gami Ved for FY 2023-24 (SIGNED).pdf · uploaded 17 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 of Gami Ved as 30-09-2024 final.pdf · uploaded 26 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Gami Ved as on 31-10-2024.pdf · uploaded 16 Nov 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Gami Ved as on 31-10-2024.pdf · uploaded 16 Nov 2024Source
  • 2 Disclosure of sold/ booked inventoryCIRCULAR 29 Gami Ved as on Sep 2024.pdf · uploaded 2 Dec 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Gami Ved as on 31st Oct 2024.pdf · uploaded 28 Dec 2024Source
  • 3 Disclosure of sold/ booked inventoryCIRCULAR 29 as on 31st Oct 2024_organized.pdf · uploaded 28 Dec 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Gami Ved as on 31-10-2024 Certified.pdf · uploaded 31 Dec 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 2023-24.pdf · uploaded 3 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Gami Ved as on 31-12-2024.pdf · uploaded 13 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Gami Ved as on Dec 2024.pdf · uploaded 13 Jan 2025Source
  • 1 Copy of Layout Approval (in case of layout)GAMI SANCTIONED PLAN 1.pdf · uploaded 22 Jan 2025Source
  • 2 Copy of Layout Approval (in case of layout)1 Copy of Layout Approval (in case of layout).pdf · uploaded 22 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Dec 2024.pdf · uploaded 22 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Gami Ved as on Dec 2024.pdf · uploaded 22 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Gami Ved as on Dec 2024.pdf · uploaded 22 Jan 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentGAMI SANCTIONED PLAN 2.pdf · uploaded 22 Jan 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentGAMI SANCTIONED PLAN 3.pdf · uploaded 22 Jan 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentGAMI SANCTIONED PLAN 4.pdf · uploaded 22 Jan 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentGAMI SANCTIONED PLAN 5.pdf · uploaded 22 Jan 2025Source
  • 5 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 22 Jan 2025Source
  • 6 Building Plan Approval / NA Order for plotted development3.pdf · uploaded 22 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryCIRCULAR 29 as on 31st Dec 2024_removed.pdf · uploaded 28 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Gami Ved as on March 2025.pdf · uploaded 12 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Gami Ved as on March 2025.pdf · uploaded 12 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - Gami Ved as on March 2025.pdf · uploaded 16 Apr 2025Source
  • Form 1Form 1 - Gami Ved as on June 2025.pdf · uploaded 28 Aug 2025Source
  • Form 2Form 2 - Gami Ved as on June 2025.pdf · uploaded 28 Aug 2025Source
  • Form 3Form 3 - Gami Ved as on June 2025.pdf · uploaded 28 Aug 2025Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Gami Ved Gami Ved as on June 2025.pdf · uploaded 28 Aug 2025Source
  • Form 1Form 1 - Gami Ved as on Sept 2025.pdf · uploaded 18 Oct 2025Source
  • Form 2Form 2 - Gami Ved as on Sept 2025.pdf · uploaded 18 Oct 2025Source
  • Form 3Form 3 of Gami Ved as on Sept 2025.pdf · uploaded 18 Oct 2025Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Gami Ved as on Sept 2025.pdf · uploaded 18 Oct 2025Source
  • Form 1Form 1 - Gami Ved as on Dec 2025.pdf · uploaded 19 Jan 2026Source
  • Form 2Form 2 - Gami Ved as on Dec 2025.pdf · uploaded 19 Jan 2026Source
  • Form 3Form 3 - Gami Ved as on Dec 2025.pdf · uploaded 19 Jan 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Gami Ved as on Dec 2025.pdf · uploaded 19 Jan 2026Source
  • Form 1Form 1 - Gami Ved as on March 2026.pdf · uploaded 18 Apr 2026Source
  • Form 2Form 2 - Gami Ved as on March 2026.pdf · uploaded 18 Apr 2026Source
  • Form 3Form 3 - Gami Ved as on March 2026.pdf · uploaded 18 Apr 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Gami Ved as on March 2026.pdf · uploaded 18 Apr 2026Source
  • Form 5 (FY 2024-2025)Form 5 - Gami Ved for FY 2024-25_Final.pdf · uploaded 5 Jun 2026Source
  • Form 1Form 1 - Gami Ved June 2026.pdf · uploaded 20 Jul 2026Source
  • Form 2Form 2 - Gami Ved June 2026.pdf · uploaded 20 Jul 2026Source
  • Form 3Form 3 - Gami Ved June 2026.pdf · uploaded 20 Jul 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Gami Ved June 2026.pdf · uploaded 20 Jul 2026Source

Technical

  • Document1 Copy of Layout Approval (in case of layout).pdf · uploaded 11 May 2023Source
  • Document1 Copy of Layout Approval (in case of layout).pdf · uploaded 11 May 2023Source
  • Document2 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 11 May 2023Source
  • Document3 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 11 May 2023Source
  • DocumentGAMI SANCTIONED PLAN 1.pdf · uploaded 22 Jan 2025Source
  • Document1 Copy of Layout Approval (in case of layout).pdf · uploaded 22 Jan 2025Source
  • DocumentGAMI SANCTIONED PLAN 2.pdf · uploaded 22 Jan 2025Source
  • DocumentGAMI SANCTIONED PLAN 3.pdf · uploaded 22 Jan 2025Source
  • DocumentGAMI SANCTIONED PLAN 4.pdf · uploaded 22 Jan 2025Source
  • DocumentGAMI SANCTIONED PLAN 5.pdf · uploaded 22 Jan 2025Source
  • Document2.pdf · uploaded 22 Jan 2025Source
  • Document3.pdf · uploaded 22 Jan 2025Source

Technical (Architect)

  • DocumentForm 1 - Gami Ved as on June 2024.pdf · uploaded 8 Jul 2024Source
  • DocumentForm 1 of Gami Ved as 30-09-2024 final.pdf · uploaded 26 Oct 2024Source
  • DocumentForm 1 Dec 2024.pdf · uploaded 22 Jan 2025Source
  • DocumentFORM 1 - Gami Ved as on March 2025.pdf · uploaded 16 Apr 2025Source

Technical (Engineer)

  • DocumentForm 2 - Gami Ved as on June 2024.pdf · uploaded 13 Jul 2024Source
  • DocumentForm 2 - Gami Ved as on Sept 2024.pdf · uploaded 7 Oct 2024Source
  • DocumentForm 2 - Gami Ved as on 31st Oct 2024.pdf · uploaded 28 Dec 2024Source
  • DocumentForm 2 - Gami Ved as on Dec 2024.pdf · uploaded 13 Jan 2025Source
  • DocumentForm 2 - Gami Ved as on Dec 2024.pdf · uploaded 22 Jan 2025Source
  • DocumentForm 2 - Gami Ved as on March 2025.pdf · uploaded 12 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No 13, Sector No 18

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, CIDCO Share, NMMC Share, Rehab, Society Share173 units in all
Address
Plot No- 13, Sector No- 18, Sector No- 18, NerulPIN 400706
Village
Navi Mumbai (M Corp.), Thane taluka
Land area for this project
2,024 sq m (21,786 sq ft)
Permissible built-up area
9,715 sq m (1,04,573 sq ft)
Sanctioned built-up area
9,711 sq m (1,04,530 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
109
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No 13Sector No 18

Land as published on MahaRERA's project page

Plot No- 13, Sector No- 18

Boundaries

North
15 meters wide road
South
Plot No- 22
East
Plot No-14
West
Plot No-12

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking173 units

54 of 173 units booked (31%), as the promoter reported to MahaRERA

1BHK · 14 units2BHK · 56 unitsCIDCO Share · 1 unitNMMC Share · 1 unitRehab · 100 unitsSociety Share · 1 unit
TypeCarpet areaUnitsBooked
1BHK34.1 sq m · 367 sq ft66
1BHK34.59 sq m · 372 sq ft65
1BHK46.99 sq m · 506 sq ft20
2BHK56.75 sq m · 611 sq ft5038
2BHK58.4 sq m · 629 sq ft65
CIDCO Share22.24 sq m · 239 sq ft10
NMMC Share9.34 sq m · 101 sq ft10
Rehab28.65 sq m · 308 sq ft340
Show all 12 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Rehab28.66 sq m · 308 sq ft340
Rehab32.51 sq m · 350 sq ft160
Rehab32.55 sq m · 350 sq ft160
Society Share18.96 sq m · 204 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology