Mixed · 1 building · 98 unitsRERA PM1330002500343

44 West

Deedo IDDP-THN-RR1S

Completion was pushed back 4 months, to Jan 2030; no MahaRERA orders on record; 19% of its units are booked.

Nerul, Thane 400706 · by Krystal lnfra

DeliveryExtended 4 moPromised Sep 2029 · now due Jan 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales19% booked19 of 98 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jan 2030

  • This projectRegistered 23 Jul 2025, completion promised 30 Sep 2029, revised to 30 Jan 2030.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPM1330002500343
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM133000250034323 Jul 202530 Sep 202930 Jan 2030Krystal lnfraProject page
Documents40

1 document held by Deedo, 39 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan card Krystal infra (1).pdf · uploaded 28 May 2025Source

Legal

  • Declaration Form BLEGAL TITLE REPORT - KRYSTAL INFRA.pdf · uploaded 24 May 2025Source
  • Declaration Form B44 West Form B.pdf · uploaded 24 May 2025Source
  • OthersLease Agreement Plot 163_compressed.pdf · uploaded 18 Jun 2025Source
  • OthersLease Agreement Plot 163A_compressed.pdf · uploaded 18 Jun 2025Source
  • OthersCIDCO Final Order Plot 163 Krystal Infra.pdf · uploaded 18 Jun 2025Source
  • OthersCIDCO Final Order Plot 163A Krystal Infra.pdf · uploaded 18 Jun 2025Source
Show all 40 documentsShow fewer documents

Legal

  • OthersTP Aashutosh to Krystal Plot 163_compressed.pdf · uploaded 18 Jun 2025Source
  • OthersTP Arka to Krystal Plot 163A_compressed.pdf · uploaded 18 Jun 2025Source
  • OthersModified Agreement Amalgamation_compressed.pdf · uploaded 18 Jun 2025Source
  • OthersDisclosure of Interest_ Ashfaq Khan.pdf · uploaded 18 Jun 2025Source
  • OthersDisclosure of Interest_ Santosh maruti devkar.pdf · uploaded 18 Jun 2025Source
  • OthersDisclosure of Interest_ Wasif Parkar.pdf · uploaded 18 Jun 2025Source
  • OthersDisclosure of Interest__ABDUL LATIF ALI PARKAR.pdf · uploaded 18 Jun 2025Source
  • OthersDisclosure of Interest_ASHWIN SHANKARLAL PATEL(1).pdf · uploaded 18 Jun 2025Source
  • OthersDisclosure of Interest_AZAJ RAIS KHAN.pdf · uploaded 18 Jun 2025Source
  • OthersDisclosure of Interest_DILIP PUKHRAJ SINGHVI.pdf · uploaded 18 Jun 2025Source
  • OthersDisclosure of Interest_KHIMARAM CHENAJI CHOUDHARY.pdf · uploaded 18 Jun 2025Source
  • OthersDisclosure of Interest_MAHAVIR DHARAMCHAND JAIN.pdf · uploaded 18 Jun 2025Source
  • OthersDisclosure of Interest_MOHD RAIS KHAN(1).pdf · uploaded 18 Jun 2025Source
  • OthersDisclosure of Interest_RAJU MANGILAL JAIN(1).pdf · uploaded 18 Jun 2025Source
  • OthersDisclosure of Interest_SOHANPRAKASH JETHARAM CHOUDHARY.pdf · uploaded 18 Jun 2025Source
  • Declaration Form BLand Docs_ CIDCO Final , TP, Modifed _merged.pdf · uploaded 8 Jul 2025Source

Migrated

  • Withdrawal Update Form 120251231Plot no 163 163A Sector 44 Nerul.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 120251231Plot no 163 163A Sector 44 Nerul.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 244 WEST -- EC 31-12-25.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 244 WEST -- EC 31-12-25.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 3Form 3 _ 44 West_ 31-12-25_ ca signed.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 3Form 3 _ 44 West_ 31-12-25_ ca signed.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 1Form 1 20260331_Plot No 163 163A.pdf · uploaded 22 Jul 2026Source
  • Withdrawal Update Form 2Form 2 44 WEST -- EC 31-03-26 with DSC (1).pdf · uploaded 22 Jul 2026Source
  • Withdrawal Update Form 3Form 3 _ Krystal Infra_44 west_ 31-03-2026_ ca signed.pdf · uploaded 22 Jul 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 5 Aug 2026Source
  • Withdrawal Update Form 2Form 2 44 WEST -- EC 30-06-26 with DSC.pdf · uploaded 5 Aug 2026Source
  • Withdrawal Update Form 3Form 3 Krystal Infra 44 west 30-06-2026 CA and Partner Signed.pdf · uploaded 5 Aug 2026Source

Technical

  • Document44 West Annexure A.pdf · uploaded 27 May 2025Source
  • DocumentPLOT NO-163-CC DRAWING LAYOUT COPY (2).pdf · uploaded 28 May 2025Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 22 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2 44 WEST -- EC 30-06-26 with DSC.pdf · uploaded 5 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 163A, Plot no 163

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
—98 units in all
Address
Sector 44, NerulPIN 400706
Village
Navi Mumbai (M Corp.), Thane taluka
Land area for this project
1,489 sq m (16,029 sq ft)
Permissible built-up area
7,178 sq m (77,265 sq ft)
Sanctioned built-up area
7,178 sq m (77,265 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
117
Developed in phases
No

Survey, CTS, gat or plot numbers

163APlot no 163Sector-44

Land as published on MahaRERA's project page

Plot no 163 and 163A, Sector-44, Nerul

Boundaries

North
20.00 Mts. Wide Road
South
Plot No.-144 to 147
East
Plot No.-164
West
Plot No.-162

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking98 units

98 units registered

— · 98 units
TypeCarpet areaUnits
——98

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectHemant P Dhavale—
Chartered accountantBharat Achalaram Choudhary—
EngineerSamarth Pradeep Kumar Agarwal—

Source: MahaRERA project page. Contact details are not shown.