Silver Icon
Its promised completion date, Feb 2020, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 74% of its units are booked.
Navi Mumbai (M Corp.), Thane 400701 · Promoter: Silver Glades Projects Private Limited
Its promised completion date, Feb 2020, has passed and MahaRERA does not show it completed
- This projectRegistered 27 Jul 2017, completion promised 29 Feb 2020, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000001364
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000001364 | 27 Jul 2017 | 29 Feb 2020 | 29 Feb 2020 | Silver Glades Projects Private Limited | Project page |
Documents65
1 document held by Deedo, 64 filings listed on MahaRERA's project page
Finance
- PAN CardPAN CARD FIRM.PDF · uploaded 22 Jul 2017Source
Legal
Show all 65 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesSILVER ENCUMBRANCES.pdf · uploaded 22 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)Project Layout Silver.pdf · uploaded 22 Jul 2017Source
- 1 Building Plan Approval (IOD)CC Ground to 7th Floor.pdf · uploaded 22 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentCC Ground to 7th Floor.pdf · uploaded 22 Jul 2017Source
- 1 Declaration in FORM BFORM B_Compressed.pdf · uploaded 22 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM-1 Architect's_Compressed.pdf · uploaded 22 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2 Engineer's_Compressed.pdf · uploaded 22 Jul 2017Source
- 1 Certificates of CA (Form 3)From 3.pdf · uploaded 22 Jul 2017Source
- 1 Proforma of Allotment letterDraft Agreement for Sale-RERA -with changes.pdf · uploaded 22 Jul 2017Source
- 1 OtherSilver Booking Format.pdf · uploaded 22 Jul 2017Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 24 Jan 2018Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 24 Jan 2018Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 24 Jan 2018Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 24 Jan 2018Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate_Compressed.pdf · uploaded 24 Jan 2018Source
- 2 Certificates of CA (Form 3)FORM-3(1)_Compressed.pdf · uploaded 24 Jan 2018Source
- 3 Certificates of CA (Form 3)FORM-3(2)_Compressed.pdf · uploaded 24 Jan 2018Source
- 4 Certificates of CA (Form 3)FORM-3(3)_Compressed.pdf · uploaded 24 Jan 2018Source
- 5 Certificates of CA (Form 3)FORM-3 FINAL.pdf · uploaded 25 Jan 2018Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM-1.pdf · uploaded 30 Apr 2018Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2.pdf · uploaded 30 Apr 2018Source
- 6 Certificates of CA (Form 3)FORM-3.pdf · uploaded 30 Apr 2018Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM-1.pdf · uploaded 6 Aug 2018Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2.pdf · uploaded 6 Aug 2018Source
- 7 Certificates of CA (Form 3)FORM-3.pdf · uploaded 6 Aug 2018Source
- 1 Certificates of CA (Form 5)Form 5.pdf · uploaded 15 Oct 2018Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM-1.pdf · uploaded 5 Nov 2018Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2.pdf · uploaded 5 Nov 2018Source
- 8 Certificates of CA (Form 3)form 3.pdf · uploaded 5 Nov 2018Source
- 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM - 1_Compressed.pdf · uploaded 29 Jan 2019Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 29 Jan 2019Source
- 9 Certificates of CA (Form 3)Form - 3 CA FINAL_Compressed.pdf · uploaded 29 Jan 2019Source
- 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 30 Apr 2019Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Certificate.pdf · uploaded 30 Apr 2019Source
- 10 Certificates of CA (Form 3)FORM-3 CA.pdf · uploaded 30 Apr 2019Source
- 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM-1.pdf · uploaded 31 Jul 2019Source
- 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2.pdf · uploaded 31 Jul 2019Source
- 2 OtherOC 1ST ACK.pdf · uploaded 24 Sep 2019Source
- 11 Certificates of CA (Form 3)FORM 3.pdf · uploaded 25 Sep 2019Source
- 2 Certificates of CA (Form 5)Silver Form-5.pdf · uploaded 3 Oct 2019Source
- 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form-1.pdf · uploaded 4 Nov 2019Source
- 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 4 Nov 2019Source
- 12 Certificates of CA (Form 3)FORM 3.pdf · uploaded 4 Nov 2019Source
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM-4.pdf · uploaded 7 Jan 2020Source
- 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)09A FORM 1 11-1-2020.pdf · uploaded 14 Jan 2020Source
- 13 Certificates of CA (Form 3)Form - 3 CA_Compressed.pdf · uploaded 14 Jan 2020Source
- 2 a Details of encumbrances concerned to FinanceNo encumbrances Certificate leagl.pdf · uploaded 3 Jul 2023Source
- 1 b Details of encumbrances concerned to LegalNo encumbrances Certificate leagl.pdf · uploaded 3 Jul 2023Source
- 1 Declaration about Commencement Certificatedeclaration about comm cert.pdf · uploaded 3 Jul 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclouser of Interest in other real estate organization.pdf · uploaded 3 Jul 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A bank account decla.pdf · uploaded 3 Jul 2023Source
- 1 Deviation Report with respect to Allotment letterdeviation-allotment.pdf · uploaded 3 Jul 2023Source
- 1 Deviation Report with respect to model copy of Agreementdeviation-draft sale.pdf · uploaded 3 Jul 2023Source
Technical
Technical (Architect)
- Document09A FORM 1 11-1-2020.pdf · uploaded 14 Jan 2020Source
Technical (Engineer)
- DocumentFORM 2.pdf · uploaded 4 Nov 2019Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals58
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, 2BHK42 units in all
- Address
- 58, Panvel, KonkanPIN 400701
- Village
- Navi Mumbai (M Corp.), Thane taluka
- Location
- 19.13581, 72.99758
- Designated bank account
- 105
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- 20 Meter Road
- South
- Plot No 46
- East
- 15 Meter Road
- West
- Plot No 57
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking42 units
31 of 42 units booked (74%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 19.42 sq m · 209 sq ft | 1 | 0 |
| 1BHK | 25.26 sq m · 272 sq ft | 1 | 1 |
| 1BHK | 26.16 sq m · 282 sq ft | 1 | 1 |
| 1BHK | 26.25 sq m · 283 sq ft | 5 | 3 |
| 1BHK | 26.44 sq m · 285 sq ft | 1 | 1 |
| 1BHK | 28.86 sq m · 311 sq ft | 4 | 4 |
| 1BHK | 28.98 sq m · 312 sq ft | 1 | 1 |
| 1BHK | 29.31 sq m · 315 sq ft | 1 | 0 |
Show all 19 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 29.36 sq m · 316 sq ft | 1 | 1 |
| 1BHK | 30.66 sq m · 330 sq ft | 5 | 4 |
| 1BHK | 35.16 sq m · 378 sq ft | 5 | 2 |
| 1RK | 18.99 sq m · 204 sq ft | 1 | 0 |
| 1RK | 19.06 sq m · 205 sq ft | 1 | 0 |
| 1RK | 20 sq m · 215 sq ft | 1 | 1 |
| 2BHK | 33.59 sq m · 362 sq ft | 7 | 6 |
| 2BHK | 33.6 sq m · 362 sq ft | 3 | 3 |
| 2BHK | 37.48 sq m · 403 sq ft | 1 | 1 |
| 2BHK | 38.92 sq m · 419 sq ft | 1 | 1 |
| 2BHK | 41.37 sq m · 445 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Satish V Ahuja & Associates | — |
| Chartered accountant | Shashank R Jain | — |
Source: MahaRERA project page. Contact details are not shown.