Residential / Group Housing · 1 building · 38 unitsRERA P51700011876

Mohan Palms

Its promised completion date, Dec 2021, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 16% of its units are booked.

Navi Mumbai (M Corp.), Thane 400706 · Promoter: V M Constructions

Delivery4 yrs 10 mo past duePromised Dec 2021 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales16% booked6 of 38 units · as the promoter reported to MahaRERA
Mohan Palms project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Dec 2021, has passed and MahaRERA does not show it completed

  • This projectRegistered 31 Aug 2017, completion promised 30 Dec 2021, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700011876
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001187631 Aug 201730 Dec 202130 Dec 2021V M ConstructionsProject page
Documents36

1 document held by Deedo, 35 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 14 Aug 2017Source

Legal

  • Legal Title reportTITLE REPORT.pdf · uploaded 14 Aug 2017Source
  • Declaration Form BFORM B.pdf · uploaded 14 Aug 2017Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 14 Aug 2017Source
  • 1 Copy of the legal title reportTITLE REPORT.pdf · uploaded 14 Aug 2017Source
  • 1 Copy of Layout Approval (in case of layout)PLAN 1.pdf · uploaded 14 Aug 2017Source
  • 2 Copy of Layout Approval (in case of layout)PLAN 2.pdf · uploaded 14 Aug 2017Source
Show all 36 documentsShow fewer documents

Migrated

  • 3 Copy of Layout Approval (in case of layout)PLAN 3.pdf · uploaded 14 Aug 2017Source
  • 4 Copy of Layout Approval (in case of layout)PLAN 4.pdf · uploaded 14 Aug 2017Source
  • 5 Copy of Layout Approval (in case of layout)PLAN 5.pdf · uploaded 14 Aug 2017Source
  • 1 Building Plan Approval (IOD)PLAN 1.pdf · uploaded 14 Aug 2017Source
  • 2 Building Plan Approval (IOD)PLAN 2.pdf · uploaded 14 Aug 2017Source
  • 3 Building Plan Approval (IOD)PLAN 3.pdf · uploaded 14 Aug 2017Source
  • 4 Building Plan Approval (IOD)PLAN 4.pdf · uploaded 14 Aug 2017Source
  • 5 Building Plan Approval (IOD)PLAN 5.pdf · uploaded 14 Aug 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT.pdf · uploaded 14 Aug 2017Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 14 Aug 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERT NEW.pdf · uploaded 14 Aug 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERT.pdf · uploaded 14 Aug 2017Source
  • 1 Certificates of CA (Form 3)CA CERT.pdf · uploaded 14 Aug 2017Source
  • 1 Details of encumbrancesENCUMBRANCE.pdf · uploaded 18 Aug 2017Source
  • 1 Proforma of Allotment letterAGREEMENT OF V M CONSTRUCTIONS NEW.pdf · uploaded 18 Aug 2017Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4 VM.pdf · uploaded 31 Dec 2019Source

Technical

  • DocumentPLAN 1.pdf · uploaded 14 Aug 2017Source
  • DocumentPLAN 2.pdf · uploaded 14 Aug 2017Source
  • DocumentPLAN 3.pdf · uploaded 14 Aug 2017Source
  • DocumentPLAN 4.pdf · uploaded 14 Aug 2017Source
  • DocumentPLAN 5.pdf · uploaded 14 Aug 2017Source
  • DocumentPLAN 1.pdf · uploaded 14 Aug 2017Source
  • DocumentPLAN 2.pdf · uploaded 14 Aug 2017Source
  • DocumentPLAN 3.pdf · uploaded 14 Aug 2017Source
  • DocumentPLAN 4.pdf · uploaded 14 Aug 2017Source
  • DocumentPLAN 5.pdf · uploaded 14 Aug 2017Source

Technical (Architect)

  • DocumentARCHITECT CERT NEW.pdf · uploaded 14 Aug 2017Source

Technical (Engineer)

  • DocumentENGINEER CERT.pdf · uploaded 14 Aug 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsPLOT NO 17, SECTOR38

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
Residential38 units in all
Address
Plot No 17, Sector-38, NerulPIN 400706
Village
Navi Mumbai (M Corp.), Thane taluka
Designated bank account
109
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO 17SECTOR38

Boundaries

North
Plot No 23
South
Plot No 25
East
30 Mtr Wide Road
West
Recreational Open Space

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking38 units

6 of 38 units booked (16%), as the promoter reported to MahaRERA

Residential · 38 units
TypeCarpet areaUnitsBooked
Residential38.96 sq m · 419 sq ft10
Residential39.27 sq m · 423 sq ft112
Residential40.41 sq m · 435 sq ft10
Residential40.64 sq m · 437 sq ft40
Residential40.72 sq m · 438 sq ft60
Residential40.75 sq m · 439 sq ft10
Residential41.02 sq m · 442 sq ft10
Residential43.11 sq m · 464 sq ft10
Residential66.53 sq m · 716 sq ft11
Residential68.55 sq m · 738 sq ft113

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSoyuz Talib Architects—
EngineerSamarth Agarwal—
OtherAdhikalpam Enterprises—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology