Others · 1 building · 152 unitsRERA P51700053044

Century Two

Deedo IDDP-THN-14J3

Completion was pushed back 4 months, to Jul 2028; no MahaRERA orders on record; 39% of its units are booked.

Ghansoli, Thane 400701 · by City Infra

DeliveryExtended 4 moPromised Mar 2028 · now due Jul 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales39% booked60 of 152 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jul 2028

  • This projectRegistered 10 Oct 2023, completion promised 31 Mar 2028, revised to 31 Jul 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700053044
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170005304410 Oct 202331 Mar 202831 Jul 2028City InfraProject page
Documents120

1 document held by Deedo, 119 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardpan card of company.pdf · uploaded 17 Jun 2023Source

Legal

  • Legal Title reportLEGAL TITLE REPORT.pdf · uploaded 17 Jun 2023Source
  • Declaration Form BForm-B.pdf · uploaded 17 Jun 2023Source

Migrated

  • 1 PAN Cardpan card of company.pdf · uploaded 17 Jun 2023Source
  • 1 Copy of the legal title reportLEGAL TITLE REPORT.pdf · uploaded 17 Jun 2023Source
  • 1 a Details of encumbrances concerned to FinanceLEETER OF ENCUMBRANCE FIANANCE N LEGAL.pdf · uploaded 17 Jun 2023Source
  • 1 b Details of encumbrances concerned to LegalLEETER OF ENCUMBRANCE FIANANCE N LEGAL.pdf · uploaded 17 Jun 2023Source
Show all 120 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN 1.pdf · uploaded 17 Jun 2023Source
  • 2 Copy of Layout Approval (in case of layout)LAYOUT PLAN 2.pdf · uploaded 17 Jun 2023Source
  • 3 Copy of Layout Approval (in case of layout)LAYOUT PLAN 3.pdf · uploaded 17 Jun 2023Source
  • 4 Copy of Layout Approval (in case of layout)LAYOUT PLAN 4.pdf · uploaded 17 Jun 2023Source
  • 5 Copy of Layout Approval (in case of layout)LAYOUT PLAN 5.pdf · uploaded 17 Jun 2023Source
  • 6 Copy of Layout Approval (in case of layout)LAYOUT PLAN 6.pdf · uploaded 17 Jun 2023Source
  • 7 Copy of Layout Approval (in case of layout)LAYOUT PLAN 7.pdf · uploaded 17 Jun 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentLAYOUT PLAN 8.pdf · uploaded 17 Jun 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC COPY.pdf · uploaded 17 Jun 2023Source
  • 1 Declaration about Commencement CertificateDECLARATION OF CC.pdf · uploaded 17 Jun 2023Source
  • 1 Declaration in FORM BForm-B.pdf · uploaded 17 Jun 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 17 Jun 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 17 Jun 2023Source
  • 1 CERSAI detailsCersai report n undertake.pdf · uploaded 17 Jun 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3.pdf · uploaded 17 Jun 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOUSER OF INTEREST IN OTHER ORAGAN.pdf · uploaded 17 Jun 2023Source
  • 1 Proforma of Agreement for saleFINAL DRAFT AGREEMENT FOR SALE.pdf · uploaded 17 Jun 2023Source
  • 1 Proforma of Allotment letterFINAL ALLOTMENT LETTER.pdf · uploaded 17 Jun 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDECLARATION OF SEPERATE BANK.pdf · uploaded 17 Jun 2023Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION OF ALLOTMENT LETTER.pdf · uploaded 17 Jun 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION OF AFS.pdf · uploaded 17 Jun 2023Source
  • 2 CERSAI detailsLetter for cersai.pdf · uploaded 18 Jul 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 22 Jan 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 22 Jan 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 with sign.pdf · uploaded 30 Jan 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentRevised CC.pdf · uploaded 7 May 2024Source
  • 2 Declaration about Commencement CertificateDeclaration of CC.pdf · uploaded 7 May 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P no - 22, S- 09, Form 1.pdf · uploaded 7 May 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 7 May 2024Source
  • 1 Disclosure of sold/ booked inventoryInventory Sold Letter.pdf · uploaded 7 May 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 11zon.pdf · uploaded 7 May 2024Source
  • 8 Copy of Layout Approval (in case of layout)Layout plan-1-2.pdf · uploaded 29 May 2024Source
  • 9 Copy of Layout Approval (in case of layout)Layout plan-3 -4.pdf · uploaded 29 May 2024Source
  • 10 Copy of Layout Approval (in case of layout)Layout plan-5 -6.pdf · uploaded 29 May 2024Source
  • 11 Copy of Layout Approval (in case of layout)Layout plan-7.pdf · uploaded 29 May 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentLayout plan-8- 9.pdf · uploaded 29 May 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_.pdf · uploaded 19 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_.pdf · uploaded 19 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Final FORM 5.pdf · uploaded 21 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Final Form 1.pdf · uploaded 12 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Final Form 1.pdf · uploaded 12 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 12 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 12 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 12 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Final Form 2.pdf · uploaded 12 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Final Form 2.pdf · uploaded 12 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FInal FORM 1.pdf · uploaded 18 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final FORM 3.pdf · uploaded 18 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Final FORM 2.pdf · uploaded 18 Apr 2025Source
  • Form 1Form 1.pdf · uploaded 20 May 2025Source
  • Form 2Form 2.pdf · uploaded 20 May 2025Source
  • Form 3form 3 with sign.pdf · uploaded 20 May 2025Source
  • Form 1Form 1.pdf · uploaded 20 May 2025Source
  • Form 2Form 2.pdf · uploaded 20 May 2025Source
  • Form 3form 3 with sign.pdf · uploaded 20 May 2025Source
  • Form 1Form 1.pdf · uploaded 20 May 2025Source
  • Form 2form 3 with sign.pdf · uploaded 20 May 2025Source
  • Form 3Form 2.pdf · uploaded 20 May 2025Source
  • Form 1Form 1.pdf · uploaded 20 May 2025Source
  • Form 2form 3 with sign.pdf · uploaded 20 May 2025Source
  • Form 3Form 2.pdf · uploaded 20 May 2025Source
  • Form 1Form 1.pdf · uploaded 20 May 2025Source
  • Form 2form 3 with sign.pdf · uploaded 20 May 2025Source
  • Form 3Form 2.pdf · uploaded 20 May 2025Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 28 Jul 2025Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 28 Jul 2025Source
  • Withdrawal Update Form 3FORM 3 for Q1 (Century two) (1).pdf · uploaded 28 Jul 2025Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 19 Aug 2025Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 19 Aug 2025Source
  • Withdrawal Update Form 3FORM 3 for Q1 (Century two) (1).pdf · uploaded 19 Aug 2025Source
  • Form 5 (FY 2024-2025)Form-5 final.pdf · uploaded 30 Sep 2025Source
  • Withdrawal Update Form 1Form 1 Q2 2025..pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 1Form 1 Q2 2025..pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 1Form 1 Q2 2025..pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 2Form 2 Q2 2025..pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 2Form 2 Q2 2025..pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 2Form 2 Q2 2025..pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 3Form-3 Q2 2025..pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 3Form-3 Q2 2025..pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 3Form-3 Q2 2025..pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 1FORM1 Q3 25-26.pdf · uploaded 22 Jan 2026Source
  • Withdrawal Update Form 2FORM2 Q3 25-26.pdf · uploaded 22 Jan 2026Source
  • Withdrawal Update Form 3FORM3 Q3 25-26.pdf · uploaded 22 Jan 2026Source
  • Withdrawal Update Form 1Form 1 Q4 2025-2026.pdf · uploaded 22 Apr 2026Source
  • Withdrawal Update Form 2Form 2 Q4 2025-2026.pdf · uploaded 22 Apr 2026Source
  • Withdrawal Update Form 3Form 3 Q4 2025-2026..pdf · uploaded 22 Apr 2026Source
  • Withdrawal Update Form 1Form 1 Q1 26-27.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2Form 2 Q1 26-27.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3Form 3 Q1 26-27.pdf · uploaded 20 Jul 2026Source

Technical

  • DocumentLAYOUT PLAN 1.pdf · uploaded 17 Jun 2023Source
  • DocumentLAYOUT PLAN 2.pdf · uploaded 17 Jun 2023Source
  • DocumentLAYOUT PLAN 3.pdf · uploaded 17 Jun 2023Source
  • DocumentLAYOUT PLAN 4.pdf · uploaded 17 Jun 2023Source
  • DocumentLAYOUT PLAN 5.pdf · uploaded 17 Jun 2023Source
  • DocumentLAYOUT PLAN 6.pdf · uploaded 17 Jun 2023Source
  • DocumentLAYOUT PLAN 7.pdf · uploaded 17 Jun 2023Source
  • DocumentLAYOUT PLAN 8.pdf · uploaded 17 Jun 2023Source
  • DocumentLayout plan-1-2.pdf · uploaded 29 May 2024Source
  • DocumentLayout plan-8- 9.pdf · uploaded 29 May 2024Source
  • DocumentLayout plan-3 -4.pdf · uploaded 29 May 2024Source
  • DocumentLayout plan-5 -6.pdf · uploaded 29 May 2024Source
  • DocumentLayout plan-7.pdf · uploaded 29 May 2024Source

Technical (Architect)

  • DocumentForm 1_.pdf · uploaded 19 Oct 2024Source
  • DocumentFinal Form 1.pdf · uploaded 12 Feb 2025Source
  • DocumentFinal Form 1.pdf · uploaded 12 Feb 2025Source
  • DocumentFInal FORM 1.pdf · uploaded 18 Apr 2025Source
  • DocumentForm 1 Q1 26-27.pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • DocumentFORM 2_.pdf · uploaded 19 Oct 2024Source
  • DocumentFinal Form 2.pdf · uploaded 12 Feb 2025Source
  • DocumentFinal Form 2.pdf · uploaded 12 Feb 2025Source
  • DocumentFinal FORM 2.pdf · uploaded 18 Apr 2025Source
  • DocumentForm 2 Q1 26-27.pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel PLOT NO 22, SECTOR09

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK, Nursing room, Shop152 units in all
Address
Plot No 22, Sector-09, Plot No-22, Sector 9, GhansoliPIN 400701
Village
Navi Mumbai (M Corp.), Thane taluka
Land area for this project
2,649 sq m (28,511 sq ft)
Permissible built-up area
13,835 sq m (1,48,923 sq ft)
Sanctioned built-up area
13,835 sq m (1,48,923 sq ft)
Designated bank account
86
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO 22SECTOR09

Land as published on MahaRERA's project page

PLOT NO 22,SECTOR-09

Boundaries

North
Plot No 19
South
24 00 Mtr Wide Road
East
Plot No 23
West
Plot No 20

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking152 units

60 of 152 units booked (39%), as the promoter reported to MahaRERA

2BHK · 105 units3BHK · 35 unitsNursing room · 2 unitsShop · 10 units
TypeCarpet areaUnitsBooked
2BHK58.35 sq m · 628 sq ft7025
2BHK61.82 sq m · 665 sq ft3513
3BHK79.2 sq m · 853 sq ft3515
Nursing room191.24 sq m · 2,058 sq ft11
Nursing room221.62 sq m · 2,385 sq ft11
Shop17.07 sq m · 184 sq ft10
Shop36.78 sq m · 396 sq ft10
Shop38.77 sq m · 417 sq ft10
Show all 15 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop42.3 sq m · 455 sq ft11
Shop44.68 sq m · 481 sq ft11
Shop47.71 sq m · 514 sq ft11
Shop49.99 sq m · 538 sq ft10
Shop50.5 sq m · 544 sq ft10
Shop56.04 sq m · 603 sq ft11
Shop67.93 sq m · 731 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVastospati Design Group—
Chartered accountantH M Shah & Associates—
EngineerAgharkar Consultants—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology