Tirupati Complex
Deedo IDDP-THN-R90RCompletion was pushed back 5 years, to Dec 2027; no MahaRERA orders on record; 63% of its units are booked.
Mirabhayandar (M Corp.), Thane 401101 · Promoter: Tirupati Developers
Completion was pushed back 5 years, to Dec 2027
- This projectRegistered 31 Aug 2017, completion promised 30 Dec 2022, revised to 31 Dec 2027.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700011047
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700011047 | 31 Aug 2017 | 30 Dec 2022 | 31 Dec 2027 | Tirupati Developers | Project page |
Documents123
2 documents held by Deedo, 121 filings listed on MahaRERA's project page
Finance
- PAN CardPan Card Tirupati Developers.pdf · uploaded 23 Mar 2018Source
Legal
- Legal Title reportTITAL CERTIFICATE.pdf · uploaded 1 Aug 2017Source
- Legal Title reportSEARCH REPORT.pdf · uploaded 1 Aug 2017Source
- Declaration Form BFORM B AFFIDAVIT.pdf · uploaded 2 Aug 2017Source
- OtherStop Work Leeter.pdf · uploaded 2 Aug 2019Source
- OtherDeclaration Tirupati Developers.pdf · uploaded 22 Oct 2021Source
Show all 123 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportTITAL CERTIFICATE.pdf · uploaded 1 Aug 2017Source
- 2 Copy of the legal title reportSEARCH REPORT.pdf · uploaded 1 Aug 2017Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN.pdf · uploaded 1 Aug 2017Source
- 1 Building Plan Approval (IOD)C C.pdf · uploaded 1 Aug 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentC C.pdf · uploaded 1 Aug 2017Source
- 1 Details of encumbrancesTD SELF DECLARATION.pdf · uploaded 2 Aug 2017Source
- 2 Building Plan Approval (IOD)TYPICAL FLOOR PLAN.pdf · uploaded 2 Aug 2017Source
- 1 Declaration in FORM BFORM B AFFIDAVIT.pdf · uploaded 2 Aug 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ANISH ASSCO CC OF WORK.pdf · uploaded 2 Aug 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 2 Aug 2017Source
- 1 Certificates of CA (Form 3)Form 3 C A Certificate.pdf · uploaded 2 Aug 2017Source
- 1 Proforma of Allotment letterTD DRAFT LETTER.pdf · uploaded 2 Aug 2017Source
- 1 PAN CardPan Card Tirupati Developers.pdf · uploaded 23 Mar 2018Source
- 2 Certificates of CA (Form 3)FORM 3- TIRUPATI DEVELOPER-compressed.pdf · uploaded 14 Nov 2018Source
- 1 Certificates of CA (Form 5)FORM 5- TIRUPATI DEVELOPER.pdf · uploaded 14 Nov 2018Source
- 1 Form 2AEngineer Certificate -TIRUPATI.pdf · uploaded 2 Aug 2019Source
- 3 Certificates of CA (Form 3)TIRUPATI DEVELOPER.pdf · uploaded 2 Aug 2019Source
- 2 Certificates of CA (Form 5)Form-58.pdf · uploaded 2 Aug 2019Source
- 1 OtherStop Work Leeter.pdf · uploaded 2 Aug 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form-5-TIRUPATI.pdf · uploaded 2 Jan 2020Source
- 3 Certificates of CA (Form 5)Form-5 Tirupati Developer.pdf · uploaded 27 Jan 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form-5 Tirupati Developer.pdf · uploaded 27 Jan 2021Source
- 1 Declaration about Commencement CertificateTirupati Developers.pdf · uploaded 19 Aug 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Tirupati Developers.pdf · uploaded 19 Aug 2021Source
- 1 Disclosure of sold/ booked inventoryilovepdf_merged(2)_compressed.pdf · uploaded 19 Aug 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Tirupati Developer (01-04-2020 to 31-03-2021).pdf · uploaded 19 Aug 2021Source
- 2 OtherDeclaration Tirupati Developers.pdf · uploaded 22 Oct 2021Source
- 2 a Details of encumbrances concerned to FinanceConcerned to Legal.pdf · uploaded 8 Nov 2022Source
- 1 b Details of encumbrances concerned to LegalConcerned to Legal.pdf · uploaded 8 Nov 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)1 Form 2A.pdf · uploaded 8 Nov 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200251658716_For_Asset_Based_Search_08_11_2022_18_55_33_624.pdf · uploaded 8 Nov 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form-5 (01-11-2022).pdf · uploaded 8 Nov 2022Source
- 2 Proforma of Allotment letterAllotment Letter_compressed.pdf · uploaded 8 Nov 2022Source
- 1 Proforma of Agreement for saleRERA - TIRUPATI COMPLEX.pdf · uploaded 8 Nov 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 8 Nov 2022Source
- 1 Deviation Report with respect to Allotment letterAllotment Letter Rera Agreement1.pdf · uploaded 8 Nov 2022Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Report-Model Agreement.pdf · uploaded 8 Nov 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentCC Declaration_compressed.pdf · uploaded 9 Nov 2022Source
- 2 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 11 Nov 2022Source
- 3 Building Plan Approval (IOD)Building.pdf · uploaded 11 Nov 2022Source
- 2 Declaration about Commencement CertificateTIRUPATI DEVELOPERS FORMAT D.pdf · uploaded 14 Nov 2022Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Form1.pdf · uploaded 14 Nov 2022Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form2A-22.pdf · uploaded 14 Nov 2022Source
- 2 Disclosure of sold/ booked inventorySold-Unsold List.pdf · uploaded 14 Nov 2022Source
- 4 Certificates of CA (Form 3)fORM.pdf · uploaded 14 Nov 2022Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form1-Tirupati Developer.pdf · uploaded 16 Jan 2024Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Tirupati Developer-Form 1.pdf · uploaded 16 Jan 2024Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form2-Tirupati Developer.pdf · uploaded 16 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form2A-22-23-Tirupati Complex.pdf · uploaded 16 Jan 2024Source
- 5 Certificates of CA (Form 3)TIRUPATI DEV-Form 1.pdf · uploaded 17 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)TIRUPATI FORM 5.pdf · uploaded 17 Jan 2024Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)_page-0001.pdf · uploaded 29 Apr 2024Source
- 3 Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 29 Apr 2024Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form1.pdf · uploaded 30 Apr 2024Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form2a.pdf · uploaded 30 Apr 2024Source
- 6 Certificates of CA (Form 3)Form - 3 TE.pdf · uploaded 30 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form - 5-23-24.pdf · uploaded 2 May 2024Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form-1.pdf · uploaded 25 Jul 2024Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form-2.pdf · uploaded 25 Jul 2024Source
- 4 Disclosure of sold/ booked inventorySold-Unsold List-Tirupati.pdf · uploaded 25 Jul 2024Source
- 7 Certificates of CA (Form 3)fORM-3.pdf · uploaded 25 Jul 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Bank Details.pdf · uploaded 25 Jul 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)TC - Quality Assurance Certificate.pdf · uploaded 16 Nov 2024Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)TC - Pradeep Patel - Form B2.pdf · uploaded 16 Nov 2024Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)TC - Pradeep Patel - Form B2.pdf · uploaded 16 Nov 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)TC - Quality Assurance Certificate.pdf · uploaded 16 Nov 2024Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form1 td.pdf · uploaded 23 Jan 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form2a td.pdf · uploaded 23 Jan 2025Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form2 td.pdf · uploaded 23 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryDisclouser of Tirupati Complex.pdf · uploaded 23 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)form2a td.pdf · uploaded 23 Jan 2025Source
- 1 Certificates of CA (Form 3)Form - 3 Tirupati Complex.pdf · uploaded 29 Jan 2025Source
- Withdrawal Update Form 1FORMMMM 1.pdf · uploaded 26 Jul 2025Source
- Withdrawal Update Form 2form 2.pdf · uploaded 26 Jul 2025Source
- Withdrawal Update Form 3TIRUPATI DEV.pdf · uploaded 26 Jul 2025Source
- Withdrawal Update Form 1Tirupati COMPLEX BUILDING NO 2 (3).pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 2form 2.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 3FORM 3 TIRUPATI DEVELOPERS{COMPLEX}.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 1Tirupati COMPLEX BUILDING NO 2 (3).pdf · uploaded 3 Nov 2025Source
- Withdrawal Update Form 2form 2.pdf · uploaded 3 Nov 2025Source
- Withdrawal Update Form 3FORM 3 TIRUPATI DEVELOPERS{COMPLEX}.pdf · uploaded 3 Nov 2025Source
- Withdrawal Update Form 1Form truuu.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 2form 2 truu.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 3TIRUPATI DEV.pdf · uploaded 21 Jan 2026Source
- Form 5 (FY 2018-2019)1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19).pdf · uploaded 14 Mar 2026Source
- Form 5 (FY 2019-2020)1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20).pdf · uploaded 14 Mar 2026Source
- Form 5 (FY 2020-2021)1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf · uploaded 14 Mar 2026Source
- Form 5 (FY 2021-2022)CA (Form 5) (FY 2021-22).pdf · uploaded 14 Mar 2026Source
- Form 5 (FY 2022-2023)CA (Form 5) (FY 2022-23).pdf · uploaded 14 Mar 2026Source
- Form 5 (FY 2023-2024)CA (Form 5) (FY 2023-24).pdf · uploaded 14 Mar 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 28 Apr 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 28 Apr 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 28 Apr 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 28 Apr 2026Source
- Withdrawal Update Form 3TIRUPATI DEV.pdf · uploaded 28 Apr 2026Source
- Withdrawal Update Form 3TIRUPATI DEVELOPERS-fORM 3.pdf · uploaded 28 Apr 2026Source
- Form 2A (FY 2024-2025)25-26.pdf · uploaded 28 Apr 2026Source
- Form 2A (FY 2025-2026)24-25.pdf · uploaded 28 Apr 2026Source
- Form 5 (FY 2024-2025)FORM5-24-25.pdf · uploaded 28 Apr 2026Source
- Form 5 (FY 2025-2026)fORM 5-25-26.pdf · uploaded 28 Apr 2026Source
- Withdrawal Update Form 1Form 1 Tirupati Complex.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 2Form 2 Tirupati Complex.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 3Form 3 Tirupati Complex.pdf · uploaded 17 Jul 2026Source
Technical
Technical (Architect)
Technical (Engineer)
- DocumentTC - Pradeep Patel - Form B2.pdf · uploaded 16 Nov 2024Source
- DocumentTC - Pradeep Patel - Form B2.pdf · uploaded 16 Nov 2024Source
- Documentform2a td.pdf · uploaded 23 Jan 2025Source
- Documentform2 td.pdf · uploaded 23 Jan 2025Source
- DocumentForm 2 Tirupati Complex.pdf · uploaded 17 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsOLD SNO 349 NEW 13 HNO 2 CTS NO 1514
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK40 units in all
- Address
- Old Sno 349 New 13 Hno 2 Cts No 1514, Near Railway Station, BhayandarPIN 401101
- Village
- Mira-Bhayandar (M Corp.), Thane taluka
- Location
- 19.31121, 72.85147
- Designated bank account
- 212
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- 1513 To The North
- South
- Venkatesh Plaza
- East
- Railway
- West
- Cts No 1484
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking40 units
25 of 40 units booked (63%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 40.89 sq m · 440 sq ft | 1 | 1 |
| 1BHK | 42.17 sq m · 454 sq ft | 10 | 5 |
| 1BHK | 44.01 sq m · 474 sq ft | 9 | 8 |
| 2BHK | 60.31 sq m · 649 sq ft | 1 | 1 |
| 2BHK | 64.82 sq m · 698 sq ft | 10 | 5 |
| 2BHK | 66.66 sq m · 718 sq ft | 9 | 5 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Anish And Associates | — |
| Chartered accountant | Ramesh Dhondiram Lukad | — |
| Engineer | Pradeep Patel | — |
Source: MahaRERA project page. Contact details are not shown.