Thane Project
Deedo IDDP-THN-YMQ0It is due for completion in Jul 2029, with no extension on record; no MahaRERA orders on record; 11% of its units are booked.
Majiwade, Thane 400601 · by Lodha Developers Limited · 93% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
It is due for completion in Jul 2029, with no extension on record
- This projectRegistered 10 Oct 2023, completion promised 31 Jul 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
- Building No 1-Wing A41 floors · 210 units22% booked
- Building No 1-Wing B41 floors · 210 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700053017
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700053017 | 10 Oct 2023 | 31 Jul 2029 | 31 Jul 2029 | Lodha Developers Limited | Project page |
Documents181
1 document held by Deedo, 180 filings listed on MahaRERA's project page
Finance
- PAN CardMacrotech Developers Ltd PAN CARD.pdf · uploaded 18 Sep 2023Source
Legal
Migrated
- 1 PAN CardMacrotech Developers Ltd PAN CARD.pdf · uploaded 18 Sep 2023Source
- 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 18 Sep 2023Source
- 1 Building Plan Approval / NA Order for plotted development7- Stilt Floor-Wing-A.pdf · uploaded 18 Sep 2023Source
- 2 Building Plan Approval / NA Order for plotted development8-Typ Fl-Wing-A.pdf · uploaded 18 Sep 2023Source
Show all 181 documentsShow fewer documents
Migrated
- 3 Building Plan Approval / NA Order for plotted development9-Refuge Fl-Wing-A.pdf · uploaded 18 Sep 2023Source
- 4 Building Plan Approval / NA Order for plotted development10- Stilt Floor-Wing-B.pdf · uploaded 18 Sep 2023Source
- 5 Building Plan Approval / NA Order for plotted development11-Typ Fl-Wing-B.pdf · uploaded 18 Sep 2023Source
- 6 Building Plan Approval / NA Order for plotted development12- Refuge Fl-Wing-B.pdf · uploaded 18 Sep 2023Source
- 7 Building Plan Approval / NA Order for plotted development4-Mezznine-1st Fl parking (1).pdf · uploaded 18 Sep 2023Source
- 8 Building Plan Approval / NA Order for plotted development5-2nd Parking Floor (1).pdf · uploaded 18 Sep 2023Source
- 9 Building Plan Approval / NA Order for plotted development3 rd parking.pdf · uploaded 18 Sep 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentTMC APPROVED PERMISSION CC.pdf · uploaded 18 Sep 2023Source
- 1 Declaration in FORM BForm B.pdf · uploaded 18 Sep 2023Source
- 1 Proforma of Allotment letter1 Proforma of Allotment letter (15).pdf · uploaded 18 Sep 2023Source
- 1 CERSAI detailsCERSAI_Search_Report_200280886424_For_Asset_Based_Search_19_09_2023_22_55_08_192.pdf · uploaded 19 Sep 2023Source
- 1 Disclosure of Interest in Other Real Estate Organizations1 Disclosure of Interest in Other Real Estate Organizations (14).pdf · uploaded 19 Sep 2023Source
- 2 Disclosure of Interest in Other Real Estate Organizations2 Disclosure of Interest in Other Real Estate Organizations (12).pdf · uploaded 19 Sep 2023Source
- 1 Proforma of Agreement for sale1 Proforma of Agreement for sale (20).pdf · uploaded 19 Sep 2023Source
- 1 Deviation Report with respect to Allotment letter1 Deviation Report with respect to Allotment letter (13).pdf · uploaded 19 Sep 2023Source
- 1 Deviation Report with respect to model copy of Agreement1 Deviation Report with respect to model copy of Agreement (9).pdf · uploaded 19 Sep 2023Source
- 1 Copy of the legal title reportLegal Report on Title-Thane Project Tower A and B - Titile report (7).pdf · uploaded 20 Sep 2023Source
- 1 a Details of encumbrances concerned to FinanceFinance Encumbraces.pdf · uploaded 20 Sep 2023Source
- 2 a Details of encumbrances concerned to FinanceLegal Litigation.pdf · uploaded 20 Sep 2023Source
- 1 b Details of encumbrances concerned to LegalFinance Encumbraces.pdf · uploaded 20 Sep 2023Source
- 2 b Details of encumbrances concerned to LegalLegal Litigation.pdf · uploaded 20 Sep 2023Source
- 2 Copy of Layout Approval (in case of layout)APPROVED LAYOUT_18082018.pdf · uploaded 20 Sep 2023Source
- 1 Declaration about Commencement CertificateCC Declaration.pdf · uploaded 20 Sep 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 20 Sep 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Sep 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank declaration.pdf · uploaded 20 Sep 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 25 Sep 2023Source
- 1 Other – Technical1548_001.pdf · uploaded 4 Oct 2023Source
- 2 CERSAI detailsCErsai declaration New.pdf · uploaded 5 Oct 2023Source
- 3 Copy of Layout Approval (in case of layout)1 R1 Layout plan Model.pdf · uploaded 16 Oct 2023Source
- 10 Building Plan Approval / NA Order for plotted development2 Ground floor wing A B.pdf · uploaded 16 Oct 2023Source
- 11 Building Plan Approval / NA Order for plotted development3 Ground flr Bup area calculation wing A B.pdf · uploaded 16 Oct 2023Source
- 12 Building Plan Approval / NA Order for plotted development4 1st floor plan wing A B.pdf · uploaded 16 Oct 2023Source
- 13 Building Plan Approval / NA Order for plotted development6 4th floor plan wing A.pdf · uploaded 16 Oct 2023Source
- 14 Building Plan Approval / NA Order for plotted development7 5th floor plan wing A.pdf · uploaded 16 Oct 2023Source
- 15 Building Plan Approval / NA Order for plotted development8 Typical floor plan wing A 6th 8th 11th 13th 16th 18th 21st 23rd 26th 28th 31st 33rd 36th 38th FLOOR.pdf · uploaded 16 Oct 2023Source
- 16 Building Plan Approval / NA Order for plotted development10 39th floor plan wing A.pdf · uploaded 16 Oct 2023Source
- 17 Building Plan Approval / NA Order for plotted development10 39th floor plan wing A.pdf · uploaded 16 Oct 2023Source
- 18 Building Plan Approval / NA Order for plotted development11 40th floor plan wing A.pdf · uploaded 16 Oct 2023Source
- 19 Building Plan Approval / NA Order for plotted development13 4th floor plan wing B.pdf · uploaded 16 Oct 2023Source
- 20 Building Plan Approval / NA Order for plotted development14 5th floor plan wing B.pdf · uploaded 16 Oct 2023Source
- 21 Building Plan Approval / NA Order for plotted development15 Typical floor plan wing B 6th 8th 11th 13th 16th 18th 21st 23rd 26th 28th 31st 33rd 36th 38th FLOOR.pdf · uploaded 16 Oct 2023Source
- 22 Building Plan Approval / NA Order for plotted development17 39th floor plan wing B.pdf · uploaded 16 Oct 2023Source
- 23 Building Plan Approval / NA Order for plotted development18 40th floor plan wing B.pdf · uploaded 16 Oct 2023Source
- 24 Building Plan Approval / NA Order for plotted development12 Terrace wing A B.pdf · uploaded 16 Oct 2023Source
- 25 Building Plan Approval / NA Order for plotted development16 Refuge floor plan wing B 7th 12th 17th 22nd 27th 32nd 37th floor Plan.pdf · uploaded 16 Oct 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 - Thane Project ( Raj Tattva) - P51700053017 - Dec23.pdf · uploaded 26 Feb 2024Source
- 2 Proforma of Allotment letterATS.pdf · uploaded 20 Mar 2024Source
- 2 Commencement Certificates / NA Order for plotted development8 Amended Permission and CC.pdf · uploaded 13 May 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Thane Project - P51700053017 - March 24.pdf · uploaded 15 May 2024Source
- 26 Building Plan Approval / NA Order for plotted developmentWing A,B- Ground slith(Sheet No -10) - converted.pdf · uploaded 31 May 2024Source
- 27 Building Plan Approval / NA Order for plotted developmentWing A,B 1st Floor(Sheet No -12) - converted.pdf · uploaded 31 May 2024Source
- 28 Building Plan Approval / NA Order for plotted developmentWing A,B 2 3 Floor(Sheet No -13) - converted.pdf · uploaded 31 May 2024Source
- 29 Building Plan Approval / NA Order for plotted developmentWing A 4 ,Service Floor(Sheet No -14) - converted.pdf · uploaded 31 May 2024Source
- 30 Building Plan Approval / NA Order for plotted developmentWing A-7th Floor - converted.pdf · uploaded 31 May 2024Source
- 31 Building Plan Approval / NA Order for plotted developmentWing A-Typical Floor - converted.pdf · uploaded 31 May 2024Source
- 32 Building Plan Approval / NA Order for plotted developmentWing A-Typical Floor - converted.pdf · uploaded 31 May 2024Source
- 33 Building Plan Approval / NA Order for plotted developmentWing A-Typical 2 - converted.pdf · uploaded 31 May 2024Source
- 34 Building Plan Approval / NA Order for plotted developmentWing A-Refunge - converted.pdf · uploaded 31 May 2024Source
- 35 Building Plan Approval / NA Order for plotted developmentWing A-39 th Floor - converted.pdf · uploaded 31 May 2024Source
- 36 Building Plan Approval / NA Order for plotted developmentWing A-40th Floor - converted.pdf · uploaded 31 May 2024Source
- 37 Building Plan Approval / NA Order for plotted developmentWing A ,Fifth Floor(Sheet No -15) - converted.pdf · uploaded 31 May 2024Source
- 38 Building Plan Approval / NA Order for plotted developmentWing B-4th Floor - converted.pdf · uploaded 31 May 2024Source
- 39 Building Plan Approval / NA Order for plotted developmentWing B -5th Floor - converted.pdf · uploaded 31 May 2024Source
- 40 Building Plan Approval / NA Order for plotted developmentWing B-Typical Floor - converted.pdf · uploaded 31 May 2024Source
- 41 Building Plan Approval / NA Order for plotted developmentWing B -Typical Floor 2 - converted.pdf · uploaded 31 May 2024Source
- 42 Building Plan Approval / NA Order for plotted developmentWing B-Refuge Plan - converted.pdf · uploaded 31 May 2024Source
- 43 Building Plan Approval / NA Order for plotted developmentWing B-7th Floor Plan - converted (1).pdf · uploaded 31 May 2024Source
- 44 Building Plan Approval / NA Order for plotted developmentWing B-39th Floor Plan - converted.pdf · uploaded 31 May 2024Source
- 45 Building Plan Approval / NA Order for plotted developmentWing B-40th Floor - converted.pdf · uploaded 31 May 2024Source
- 46 Building Plan Approval / NA Order for plotted developmentWing A B-Terrace Plan - converted (1).pdf · uploaded 31 May 2024Source
- 47 Building Plan Approval / NA Order for plotted developmentSection Floor - converted (1).pdf · uploaded 31 May 2024Source
- 1 Disclosure of sold/ booked inventorySold Unsold - Thane Project - P51700053017 - March 24.pdf · uploaded 13 Jun 2024Source
- 2 Disclosure of sold/ booked inventoryThane Project - P51700053017 - March 24 - Revised.pdf · uploaded 24 Jun 2024Source
- 3 Disclosure of sold/ booked inventoryThane Project - P51700053017 - June24.pdf · uploaded 7 Aug 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Thane Project - P51700053017 - June24.pdf · uploaded 10 Aug 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A - Thane Project - P51700053017.pdf · uploaded 17 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700053017 - Thane Project.pdf · uploaded 18 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Thane Project.pdf · uploaded 5 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed Form-3 Thane Project.pdf · uploaded 31 Dec 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Signed Form-2 Thane Project-Sept-24.pdf · uploaded 31 Dec 2024Source
- 2 Disclosure of sold/ booked inventorySigned Sold Unsold Thane project-Sept-24.pdf · uploaded 31 Dec 2024Source
- 1 Disclosure of sold/ booked inventory0554_001.pdf · uploaded 21 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Thane Project.pdf · uploaded 24 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Thane project Form-3 Dec-24 Signed.pdf · uploaded 28 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Thane Project - Dec 24 Signed.pdf · uploaded 28 Feb 2025Source
- Form 1Form1 - Thane Project - March25.pdf · uploaded 30 Jun 2025Source
- Form 2Form-2_Thane Project - Mar -25.pdf · uploaded 30 Jun 2025Source
- Form 3LODHA STELLA - Mar -25 Form-3.pdf · uploaded 30 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Thane Project - P51700053017 - Mar 25.pdf · uploaded 30 Jun 2025Source
- Form 1Form -1 Thane Project P51700053017 june-25.pdf · uploaded 18 Jul 2025Source
- Form 2Form 2 Crown Thane project- June-25.pdf · uploaded 18 Jul 2025Source
- Form 3Form 3 Thane Project-June-25.pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Thane Project- June-25.pdf · uploaded 18 Jul 2025Source
- Self-declaration of Quarterly ProgressUpdated CC.pdf · uploaded 18 Jul 2025Source
- OthersLayout Rajtattav building 1 (Wing A & B).pdf · uploaded 18 Jul 2025Source
- Form 5 (FY 2024-2025)Thane Project.pdf · uploaded 14 Oct 2025Source
- Withdrawal Update Form 1Form1 - P51700053017 - Thane Project.pdf · uploaded 25 Oct 2025Source
- Withdrawal Update Form 2Thane Project_Form 2.pdf · uploaded 25 Oct 2025Source
- Withdrawal Update Form 3Thane Project_Form 3.pdf · uploaded 25 Oct 2025Source
- Withdrawal Update Form 1Form-1 Thane Project Dec-25.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 2Thane Project form 2 Dec 2025.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 3Thane Project A Form 3.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 27 Apr 2026Source
- Withdrawal Update Form 2Thane Project Mar 2026 - Form 02.pdf · uploaded 27 Apr 2026Source
- Withdrawal Update Form 3Form 03.pdf · uploaded 27 Apr 2026Source
- Form 2A (FY 2025-2026)FORM 2A - Thane Project - P51700053017.pdf · uploaded 23 Jun 2026Source
- Withdrawal Update Form 1Form1 - Thane Project - P51700053017.pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 18 Jul 2026Source
- Form 5 (FY 2025-2026)Thane Project.pdf · uploaded 28 Sep 2026Source
Technical
- DocumentLayout.pdf · uploaded 18 Sep 2023Source
- Document7- Stilt Floor-Wing-A.pdf · uploaded 18 Sep 2023Source
- Document8-Typ Fl-Wing-A.pdf · uploaded 18 Sep 2023Source
- Document9-Refuge Fl-Wing-A.pdf · uploaded 18 Sep 2023Source
- Document10- Stilt Floor-Wing-B.pdf · uploaded 18 Sep 2023Source
- Document11-Typ Fl-Wing-B.pdf · uploaded 18 Sep 2023Source
- Document12- Refuge Fl-Wing-B.pdf · uploaded 18 Sep 2023Source
- Document4-Mezznine-1st Fl parking (1).pdf · uploaded 18 Sep 2023Source
- Document5-2nd Parking Floor (1).pdf · uploaded 18 Sep 2023Source
- Document3 rd parking.pdf · uploaded 18 Sep 2023Source
- DocumentAPPROVED LAYOUT_18082018.pdf · uploaded 20 Sep 2023Source
- Other – Technical1548_001.pdf · uploaded 4 Oct 2023Source
- Document1 R1 Layout plan Model.pdf · uploaded 16 Oct 2023Source
- Document2 Ground floor wing A B.pdf · uploaded 16 Oct 2023Source
- Document3 Ground flr Bup area calculation wing A B.pdf · uploaded 16 Oct 2023Source
- Document4 1st floor plan wing A B.pdf · uploaded 16 Oct 2023Source
- Document6 4th floor plan wing A.pdf · uploaded 16 Oct 2023Source
- Document7 5th floor plan wing A.pdf · uploaded 16 Oct 2023Source
- Document8 Typical floor plan wing A 6th 8th 11th 13th 16th 18th 21st 23rd 26th 28th 31st 33rd 36th 38th FLOOR.pdf · uploaded 16 Oct 2023Source
- Document10 39th floor plan wing A.pdf · uploaded 16 Oct 2023Source
- Document10 39th floor plan wing A.pdf · uploaded 16 Oct 2023Source
- Document11 40th floor plan wing A.pdf · uploaded 16 Oct 2023Source
- Document13 4th floor plan wing B.pdf · uploaded 16 Oct 2023Source
- Document14 5th floor plan wing B.pdf · uploaded 16 Oct 2023Source
- Document15 Typical floor plan wing B 6th 8th 11th 13th 16th 18th 21st 23rd 26th 28th 31st 33rd 36th 38th FLOOR.pdf · uploaded 16 Oct 2023Source
- Document17 39th floor plan wing B.pdf · uploaded 16 Oct 2023Source
- Document18 40th floor plan wing B.pdf · uploaded 16 Oct 2023Source
- Document12 Terrace wing A B.pdf · uploaded 16 Oct 2023Source
- Document16 Refuge floor plan wing B 7th 12th 17th 22nd 27th 32nd 37th floor Plan.pdf · uploaded 16 Oct 2023Source
- DocumentWing A,B- Ground slith(Sheet No -10) - converted.pdf · uploaded 31 May 2024Source
- DocumentWing A,B 1st Floor(Sheet No -12) - converted.pdf · uploaded 31 May 2024Source
- DocumentWing A,B 2 3 Floor(Sheet No -13) - converted.pdf · uploaded 31 May 2024Source
- DocumentWing A 4 ,Service Floor(Sheet No -14) - converted.pdf · uploaded 31 May 2024Source
- DocumentWing A-7th Floor - converted.pdf · uploaded 31 May 2024Source
- DocumentWing A-Typical Floor - converted.pdf · uploaded 31 May 2024Source
- DocumentWing A-Typical Floor - converted.pdf · uploaded 31 May 2024Source
- DocumentWing A-Typical 2 - converted.pdf · uploaded 31 May 2024Source
- DocumentWing A-Refunge - converted.pdf · uploaded 31 May 2024Source
- DocumentWing A-39 th Floor - converted.pdf · uploaded 31 May 2024Source
- DocumentWing A-40th Floor - converted.pdf · uploaded 31 May 2024Source
- DocumentWing A ,Fifth Floor(Sheet No -15) - converted.pdf · uploaded 31 May 2024Source
- DocumentWing B-4th Floor - converted.pdf · uploaded 31 May 2024Source
- DocumentWing B -5th Floor - converted.pdf · uploaded 31 May 2024Source
- DocumentWing B-Typical Floor - converted.pdf · uploaded 31 May 2024Source
- DocumentWing B -Typical Floor 2 - converted.pdf · uploaded 31 May 2024Source
- DocumentWing B-Refuge Plan - converted.pdf · uploaded 31 May 2024Source
- DocumentWing B-7th Floor Plan - converted (1).pdf · uploaded 31 May 2024Source
- DocumentWing B-39th Floor Plan - converted.pdf · uploaded 31 May 2024Source
- DocumentWing B-40th Floor - converted.pdf · uploaded 31 May 2024Source
- DocumentWing A B-Terrace Plan - converted (1).pdf · uploaded 31 May 2024Source
- DocumentSection Floor - converted (1).pdf · uploaded 31 May 2024Source
- DocumentRajtattav Layout Plan.pdf · uploaded 18 Jul 2026Source
- Document2024 03 1.pdf · uploaded 18 Jul 2026Source
- Document2024 03 2.pdf · uploaded 18 Jul 2026Source
- Document2024 03 3.pdf · uploaded 18 Jul 2026Source
- Document2024 03.pdf · uploaded 18 Jul 2026Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 144/1 Part, 145/1/1 Part
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 3BHK, 4BHK, 5BHK & more, 5BHK & more420 units in all
- Address
- 144/1 Part, 145/1/1 Part, 145/2 Part, 148/1/1 Part, Majiwade, MajiwadePIN 400601
- Village
- Thane (M Corp.), Thane taluka
- Land area for this project
- 2,381 sq m (25,624 sq ft)
- Permissible built-up area
- 29,647 sq m (3,19,121 sq ft)
- Sanctioned built-up area
- 29,647 sq m (3,19,121 sq ft)
- Recreational open space
- 13,685 sq m (1,47,304 sq ft)
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
144/1 Part, 145/1/1 Part, 145/2 Part, 148/1/1 Part
Boundaries
- North
- Cine Wonder Mall
- South
- 20 Mtr Wide D P Road
- East
- 60 Mtr Wide G B Road
- West
- Nilkanth Plams
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking420 units
46 of 420 units booked (11%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building No 1-Wing A | 3BHK | 106.37 sq m · 1,145 sq ft | 67 | 19 |
| Building No 1-Wing A | 3BHK | 107.3 sq m · 1,155 sq ft | 69 | 16 |
| Building No 1-Wing A | 4BHK | 131.64 sq m · 1,417 sq ft | 67 | 7 |
| Building No 1-Wing A | 4BHK | 212.75 sq m · 2,290 sq ft | 3 | 2 |
| Building No 1-Wing A | 4BHK | 214.61 sq m · 2,310 sq ft | 1 | 0 |
| Building No 1-Wing A | 5BHK & more | 263.29 sq m · 2,834 sq ft | 3 | 2 |
| Building No 1-Wing B | 3BHK | 106.37 sq m · 1,145 sq ft | 67 | 0 |
| Building No 1-Wing B | 3BHK | 107.3 sq m · 1,155 sq ft | 69 | 0 |
Show all 12 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building No 1-Wing B | 4BHK | 131.68 sq m · 1,417 sq ft | 67 | 0 |
| Building No 1-Wing B | 4BHK | 212.75 sq m · 2,290 sq ft | 3 | 0 |
| Building No 1-Wing B | 4BHK | 214.61 sq m · 2,310 sq ft | 1 | 0 |
| Building No 1-Wing B | 5BHK & more | 263.29 sq m · 2,834 sq ft | 3 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals6
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Pradeep Kamble | — |
| Chartered accountant | Chirag Sarvaiya & Co | — |
| Chartered accountant | Mska & Associates | — |
| Engineer | Hitesh Loke | — |
| Engineer | K C Shah Consultants | — |
| Engineer | Sujit Ail | — |
Source: MahaRERA project page. Contact details are not shown.
