Completion was pushed back 1 year and 4 months, to Dec 2026; no MahaRERA orders on record; 95% of its units are booked.

Majiwade, Thane 400610 · by T Bhimjyani Realty Pvt.Ltd · 83% of its projects kept the RERA date

DeliveryExtended 1 yr 4 moPromised Aug 2025 · now due Dec 2026RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales95% booked421 of 443 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 1 year and 4 months, to Dec 2026

  • This projectRegistered 19 Jul 2019, completion promised 28 Aug 2025, revised to 28 Dec 2026.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700021698
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002169819 Jul 201928 Aug 202528 Dec 2026T Bhimjyani Realty Pvt.Ltd.Project page
Documents130

2 documents held by Deedo, 128 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPancard.pdf · uploaded 9 Oct 2023Source

Legal

  • OtherConsent Terms.pdf · uploaded 14 Jul 2019Source
  • Legal Title reportLegal Title Report.pdf · uploaded 14 Jul 2019Source
  • Declaration Form BDeclaration-Form B.pdf · uploaded 14 Jul 2019Source
  • Declaration Form BFORM B -Infinity Towers REVISED DATE OF POSSESSION.pdf · uploaded 2 Feb 2024Source

Migrated

  • 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 14 Jul 2019Source
Show all 130 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesEncumberances -Phase II.pdf · uploaded 14 Jul 2019Source
  • 1 Copy of Layout Approval (in case of layout)Master Layout.pdf · uploaded 14 Jul 2019Source
  • 2 Copy of Layout Approval (in case of layout)Layout1.pdf · uploaded 14 Jul 2019Source
  • 1 Building Plan Approval (IOD)Commencement certificate .pdf · uploaded 14 Jul 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement certificate .pdf · uploaded 14 Jul 2019Source
  • 2 Commencement Certificates / NA Order for plotted developmentDeclaration for CC.pdf · uploaded 14 Jul 2019Source
  • 1 Declaration in FORM BDeclaration-Form B.pdf · uploaded 14 Jul 2019Source
  • 1 Certificates of CA (Form 3)Declaration for CA certificate.pdf · uploaded 14 Jul 2019Source
  • 1 Proforma of Allotment letterDeclaration allotment letter.pdf · uploaded 14 Jul 2019Source
  • 2 Proforma of Allotment letterDeclaration Agreement for Sale.pdf · uploaded 14 Jul 2019Source
  • 1 OtherConsent Terms.pdf · uploaded 14 Jul 2019Source
  • 3 Copy of Layout Approval (in case of layout)Layout1.pdf · uploaded 16 Jul 2019Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC Tmc Phase II.pdf · uploaded 16 Aug 2019Source
  • 2 Certificates of CA (Form 3)CA Certificate Infinity A B C Building D E F.pdf · uploaded 16 Aug 2019Source
  • 3 Proforma of Allotment letterAgreement For Sale - Infinity.pdf · uploaded 6 Jul 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architects Certificate (Sept 2022).pdf · uploaded 13 Jan 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engineers Certificate.pdf · uploaded 13 Jan 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architects Certificate (Dec 2022).pdf · uploaded 17 Jan 2023Source
  • 3 Certificates of CA (Form 3)Form 3 - C A Certificate.pdf · uploaded 20 Jan 2023Source
  • 1 Proforma of Agreement for saleAGREEMENT FOR SALE - Infinity I.pdf · uploaded 28 Feb 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architects Certificate.pdf · uploaded 12 May 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engineers Certificate.pdf · uploaded 12 May 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A- Quality Assurance Certificate (2022-2023).pdf · uploaded 12 May 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate (March 2022).pdf · uploaded 22 Aug 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate (June 2022).pdf · uploaded 22 Aug 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engineers Certificate March 2022.pdf · uploaded 29 Aug 2023Source
  • 4 Certificates of CA (Form 3)Form 3 - C A Certificate March 2022.pdf · uploaded 29 Aug 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM - 5 FY 21-22.pdf · uploaded 7 Sep 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architects Certificate April 2023.pdf · uploaded 7 Oct 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Sept 2019 (RERA).pdf · uploaded 7 Oct 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Dec 2019_(RERA).pdf · uploaded 7 Oct 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - March 2020_(RERA).pdf · uploaded 7 Oct 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 DEF - June 2020_(RERA).pdf · uploaded 7 Oct 2023Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 DEF - June 2021_(RERA).pdf · uploaded 7 Oct 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) .pdf · uploaded 7 Oct 2023Source
  • 1 PAN CardPancard.pdf · uploaded 9 Oct 2023Source
  • 1 Declaration about Commencement CertificateDeclaration - Commencement Certificate.pdf · uploaded 9 Oct 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engineers Certificate 2021.pdf · uploaded 1 Nov 2023Source
  • 2 a Details of encumbrances concerned to FinanceDetails of Encumbrances.pdf · uploaded 20 Nov 2023Source
  • 1 b Details of encumbrances concerned to LegalDetails of Encumbrances.pdf · uploaded 20 Nov 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory (2).pdf · uploaded 20 Nov 2023Source
  • 3 a Details of encumbrances concerned to FinanceLEGAL ENCUMBRANCE.pdf · uploaded 22 Nov 2023Source
  • 2 b Details of encumbrances concerned to LegalLEGAL ENCUMBRANCE.pdf · uploaded 22 Nov 2023Source
  • 5 Certificates of CA (Form 3)5 Certificate of CA (Form 3)1-7_compressed.pdf · uploaded 24 Nov 2023Source
  • 6 Certificates of CA (Form 3)5 Certificate of CA (Form 3)8-14.pdf · uploaded 24 Nov 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engineers Certificate (1).pdf · uploaded 30 Nov 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A.pdf · uploaded 30 Nov 2023Source
  • 4 Commencement Certificates / NA Order for plotted developmentCommencement Certificate - Infinity Feb 2024.pdf · uploaded 2 Feb 2024Source
  • 2 Declaration in FORM BFORM B -Infinity Towers REVISED DATE OF POSSESSION.pdf · uploaded 2 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Infinity tower - Form 5.pdf · uploaded 2 Feb 2024Source
  • 4 Copy of Layout Approval (in case of layout)APPROVED MUNCIPAL PLAN February 2024.pdf · uploaded 6 Feb 2024Source
  • 5 Copy of Layout Approval (in case of layout)APPROVED MUNCIPAL PLAN TB.pdf · uploaded 9 Feb 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)2A- 20.pdf · uploaded 20 Feb 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)2A-19.pdf · uploaded 20 Feb 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2A-21.pdf · uploaded 20 Feb 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2A-JUNE 21.pdf · uploaded 20 Feb 2024Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)2A-19.pdf · uploaded 7 Mar 2024Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2A-MARCH 21.pdf · uploaded 7 Mar 2024Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2A-SEPT21.pdf · uploaded 7 Mar 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2A-MARCH 22.pdf · uploaded 7 Mar 2024Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2A-SEPT 22.pdf · uploaded 7 Mar 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMAT A.pdf · uploaded 14 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf · uploaded 21 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf · uploaded 21 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf · uploaded 21 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf · uploaded 21 Mar 2024Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2AJUNE22.pdf · uploaded 26 Mar 2024Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2A JUNE23.pdf · uploaded 26 Mar 2024Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 (Tower DEF) - 9-8-2024.pdf · uploaded 13 Aug 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Infinity Tower.pdf · uploaded 11 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architects Certificate.pdf · uploaded 16 Dec 2024Source
  • 1 Proforma of Agreement for saleAgreement for Sale.pdf · uploaded 4 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Infinity Towers - Form 5 23-24.pdf · uploaded 7 Jan 2025Source
  • 1 Certificates of CA (Form 3)Form 3 June 2024.pdf · uploaded 22 Jan 2025Source
  • 2 Certificates of CA (Form 3)Form 3 September 2024.pdf · uploaded 22 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 June 2024.pdf · uploaded 22 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 December 2024.pdf · uploaded 1 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A June 2023.pdf · uploaded 1 Feb 2025Source
  • 1 Certificates of CA (Form 3)Form 3 31 Dec 2024.pdf · uploaded 11 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 31 Dec 2024.pdf · uploaded 11 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architects Certificate Mar 25.pdf · uploaded 2 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A- March 2024.pdf · uploaded 5 May 2025Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A- June 2024.pdf · uploaded 5 May 2025Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A- September 2024.pdf · uploaded 5 May 2025Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A- March 2025.pdf · uploaded 5 May 2025Source
  • Form 1Architects Certificate Form 1 March 2025.pdf · uploaded 19 Jan 2026Source
  • Form 2Form 2 Engineers Certificate Infinity Towers March 2025.pdf · uploaded 19 Jan 2026Source
  • Form 3RERA Form 3 Infinity Towers March.pdf · uploaded 19 Jan 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Inventory final.pdf · uploaded 19 Jan 2026Source
  • Form 1Architect Certificate Form 1 - Dt 30-6-2025.pdf · uploaded 19 Jan 2026Source
  • Form 2Engineers Certificate Form 2 for 30-06-2025.pdf · uploaded 19 Jan 2026Source
  • Form 3RERA Form 3 Infinity Towers 30-06-2025.pdf · uploaded 19 Jan 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Inventory final.pdf · uploaded 19 Jan 2026Source
  • Form 1Architect Certificate Form 1 - Dt-30-9-2025.pdf · uploaded 19 Jan 2026Source
  • Form 2Engineers Certificate Form 2 for 30-09-2025.pdf · uploaded 19 Jan 2026Source
  • Form 3RERA Form 3 Infinity Towers for 30-09-2025 final.pdf · uploaded 19 Jan 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Inventory final.pdf · uploaded 19 Jan 2026Source
  • Form 1Form 1 Architects Certificate 31-12-2025.pdf · uploaded 21 Jan 2026Source
  • Form 2Form 2 - 15-12-2025.pdf · uploaded 21 Jan 2026Source
  • Form 3RERA Form 3 Infinity Towers- for 31-12-2025 Final.pdf · uploaded 21 Jan 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Inventory.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 1Form 1 - Architects Certificate (Infinity).pdf · uploaded 22 Jun 2026Source
  • Withdrawal Update Form 2Infinity Towers Form 2.pdf · uploaded 22 Jun 2026Source
  • Withdrawal Update Form 3Infinity Towers FORM 3 MAR 2026.pdf · uploaded 22 Jun 2026Source
  • Withdrawal Update Form 1FORM 1 June 2026.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 2Form 2 JUN26.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 3RERA Form 3 JUN 26.pdf · uploaded 4 Aug 2026Source
  • Form 5 (FY 2025-2026)RERA Form 5 Infinity Tower A B C.pdf · uploaded 1 Oct 2026Source

Technical

  • DocumentCommencement certificate .pdf · uploaded 14 Jul 2019Source
  • DocumentMaster Layout.pdf · uploaded 14 Jul 2019Source
  • DocumentLayout1.pdf · uploaded 14 Jul 2019Source
  • DocumentLayout1.pdf · uploaded 16 Jul 2019Source
  • DocumentAPPROVED MUNCIPAL PLAN February 2024.pdf · uploaded 6 Feb 2024Source
  • DocumentAPPROVED MUNCIPAL PLAN TB.pdf · uploaded 9 Feb 2024Source

Technical (Architect)

  • DocumentForm 1 - Infinity Tower.pdf · uploaded 11 Oct 2024Source
  • DocumentForm 1 - Architects Certificate.pdf · uploaded 16 Dec 2024Source
  • DocumentForm 1 December 2024.pdf · uploaded 1 Feb 2025Source
  • DocumentForm 1 - Architects Certificate Mar 25.pdf · uploaded 2 May 2025Source
  • DocumentFORM 1 June 2026.pdf · uploaded 4 Aug 2026Source

Technical (Engineer)

  • DocumentForm 2 June 2024.pdf · uploaded 22 Jan 2025Source
  • DocumentForm 2 31 Dec 2024.pdf · uploaded 11 Mar 2025Source
  • DocumentForm 2 JUN26.pdf · uploaded 4 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 316 PT, 318/1D/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—443 units in all
Address
318/1d/1, 316 Pt, Mullabaug Manpada Ghodbunder Road, MajiwadePIN 400610
Village
Thane (M Corp.), Thane taluka
Land area for this project
5,743 sq m (61,817 sq ft)
Permissible built-up area
58,455 sq m (6,29,199 sq ft)
Sanctioned built-up area
58,455 sq m (6,29,199 sq ft)
Recreational open space
1,443 sq m (15,533 sq ft)
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

316 PT318/1D/1

Land as published on MahaRERA's project page

318/1D/1, 316 PT

Boundaries

North
Proposed Tower C 118
South
Neelkanth Woods Olivia
East
Neelkanth Greens Complex
West
The Mansion

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking443 units

443 units registered

— · 443 units
BuildingTypeCarpet areaUnits
Infinity A——160
Infinity B——160
Infinity C——123

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Chartered accountantJayesh S Vora—
EngineerNarrotam R Kumar—

Source: MahaRERA project page. Contact details are not shown.