Atlantic Iris
Deedo IDDP-THN-7P3JCompletion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.
Kalyan, Maharashtra 421301 · by Atlantic Winds Infrastructures Private Limited
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 22 Jun 2022, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700046415
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700046415 | 22 Jun 2022 | 31 Dec 2026 | 30 Apr 2027 | Atlantic Winds Infrastructures Private Limited | Project page |
Documents86
1 document held by Deedo, 85 filings listed on MahaRERA's project page
Legal
Migrated
- 1 Proforma of Allotment letterDraft Sale Agreement - Atlantic.pdf · uploaded 14 May 2022Source
- 1 Copy of the legal title reportKalyan Title Certificate.pdf · uploaded 31 May 2022Source
- 2 Copy of the legal title reportRERA - TC.pdf · uploaded 31 May 2022Source
- 1 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 31 May 2022Source
Show all 86 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)Layout Plan 1.pdf · uploaded 31 May 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentLayout Plan 2.pdf · uploaded 31 May 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCC for kalyan final.pdf · uploaded 31 May 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentDisclosure.pdf · uploaded 18 Jun 2022Source
- 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 18 Jun 2022Source
- 1 Declaration in FORM BForm B.pdf · uploaded 18 Jun 2022Source
- 1 CERSAI detailsCersai Latest.pdf · uploaded 18 Jun 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 18 Jun 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1Q4222319042023.pdf · uploaded 17 Jul 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1Q1232412072023.pdf · uploaded 17 Jul 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1Q2232419102023.pdf · uploaded 17 Jul 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1Q3232401012024.pdf · uploaded 17 Jul 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1Q4232411042024.pdf · uploaded 17 Jul 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2Q42223.pdf · uploaded 19 Jul 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2Q12324.pdf · uploaded 19 Jul 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2Q22324.pdf · uploaded 19 Jul 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2Q32324.pdf · uploaded 19 Jul 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2Q42324.pdf · uploaded 19 Jul 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form2A2223.pdf · uploaded 19 Jul 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form2A2324.pdf · uploaded 19 Jul 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3Q42223.pdf · uploaded 19 Jul 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3Q12324.pdf · uploaded 19 Jul 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3Q22324.pdf · uploaded 19 Jul 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3Q32324.pdf · uploaded 19 Jul 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3Q42324.pdf · uploaded 19 Jul 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form52223.pdf · uploaded 19 Jul 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q1 24-25.pdf · uploaded 30 Jan 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q2 24-25.pdf · uploaded 30 Jan 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q3 24-25.pdf · uploaded 30 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q1-24-25.pdf · uploaded 7 Feb 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q2-24-25.pdf · uploaded 7 Feb 2025Source
- 1 Disclosure of sold/ booked inventoryInventory Q1-24-25.pdf · uploaded 7 Feb 2025Source
- 2 Disclosure of sold/ booked inventoryInventory Q2-24-25.pdf · uploaded 7 Feb 2025Source
- 3 Disclosure of sold/ booked inventoryInventory Q3-24-25.pdf · uploaded 7 Feb 2025Source
- 1 CERSAI detailsCERSAI Q1-24-25.pdf · uploaded 7 Feb 2025Source
- 2 CERSAI detailsCERSAI Q2-24-25.pdf · uploaded 7 Feb 2025Source
- 3 CERSAI detailsCERSAI Q3-24-25.pdf · uploaded 7 Feb 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3- Q3- FY2024-25.pdf · uploaded 14 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2-Q1-AY2024-25 FINAL.pdf · uploaded 14 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2-Q2- FY 2024-25 FINAL.pdf · uploaded 14 Feb 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2-Q3 FY 2024-25 FINAL.pdf · uploaded 14 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form-5 FY-23-24.pdf · uploaded 20 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1 Q4 24-25.pdf · uploaded 22 Apr 2025Source
- Form 1FORM 1 Q3 24-25.pdf · uploaded 8 Jan 2026Source
- Form 2Form 2 Q3 24-25.pdf · uploaded 8 Jan 2026Source
- Form 3Form 3 Q3 24-25.pdf · uploaded 8 Jan 2026Source
- Disclosure of Sold and Booked InventoryInventory Q3-24-25.pdf · uploaded 8 Jan 2026Source
- Form 1FORM 1 Q4 24-25.pdf · uploaded 23 Jan 2026Source
- Form 2Form 2 Q4 24-25.pdf · uploaded 23 Jan 2026Source
- Form 3Form 3 Q4-24-25 Atlantic winds.pdf · uploaded 23 Jan 2026Source
- Disclosure of Sold and Booked Inventoryinventory Q4-24-25.pdf · uploaded 23 Jan 2026Source
- Form 2A (FY 2024-2025)Form-2A FY-24-25_New.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 1Form 1 Q1-25-26.pdf · uploaded 27 Jan 2026Source
- Withdrawal Update Form 1Form 1 Q2 25-26-16 Jan 2026.pdf · uploaded 27 Jan 2026Source
- Withdrawal Update Form 2Form 2 Q1 25-26.pdf · uploaded 27 Jan 2026Source
- Withdrawal Update Form 2Form-2 Q2 FY-25-26New.pdf · uploaded 27 Jan 2026Source
- Withdrawal Update Form 3Form 3 Q1 25-26 New1.pdf · uploaded 27 Jan 2026Source
- Withdrawal Update Form 3Form 3 Q2 25-26New2.pdf · uploaded 27 Jan 2026Source
- Form 5 (FY 2024-2025)Form 5 24--25 Signed.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 1Form 1 Q3 25-26.pdf · uploaded 24 Feb 2026Source
- Withdrawal Update Form 2AW FORM 2 Q3 25-26 sign.pdf · uploaded 24 Feb 2026Source
- Withdrawal Update Form 3AW FORM 3 Q3 25-26 sign_New.pdf · uploaded 24 Feb 2026Source
- Withdrawal Update Form 1form 1 Q4 25-26 Atlantic IRIS.pdf · uploaded 9 Jun 2026Source
- Withdrawal Update Form 2Atlantic IRIS Form 2 Q4 25-26.pdf · uploaded 9 Jun 2026Source
- Withdrawal Update Form 3Atlantic IRIS Form-3 Q4 25-26.pdf · uploaded 9 Jun 2026Source
- Form 2A (FY 2025-2026)Form 2A 25-26 Atlantic IRIS FINAL.pdf · uploaded 29 Jun 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —34 units in all
- Address
- Survey No 41 Hissa No 2P, t Plot No. 40, St. Xavier International School, Kalyan (West)PIN 421301
- Village
- Kolivali, Bhiwandi taluka
- Land area for this project
- 836 sq m (8,999 sq ft)
- Permissible built-up area
- 2,432 sq m (26,175 sq ft)
- Sanctioned built-up area
- 1,987 sq m (21,386 sq ft)
- Designated bank account
- 109
- Developed in phases
- No
Land as published on MahaRERA's project page
Survey No 41 Hissa No 2P,t Plot No. 40
Boundaries
- North
- 24 mtrs W DP Road
- South
- 6 mtrs W existing internal road of internal part
- East
- Survey No 41 Hissa No 1Pt Plot No 41
- West
- Remaining part of S No 41Pt and 18 mtrs W DP Rod
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking34 units
34 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 34 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | DMD Architects | — |
| Chartered accountant | H P Jadeja | — |
| Chartered accountant | Mitul Makwana & Co | — |
| Engineer | Khasnis & Associates | — |
Source: MahaRERA project page. Contact details are not shown.