Skip to content
Others · 1 building · 52 unitsRERA P51700011381

Status

Deedo IDDP-THN-PHG4

Completion was pushed back 1 year and 10 months to Oct 2020, and that date has passed too; no MahaRERA orders on record; 100% of its units are booked.

Kalyan-Dombivali (M Corp.), Thane 421301 · by Avni Corporation

Delivery7 yrs 11 mo latePromised Dec 2018 · revised Oct 2020 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked52 of 52 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 1 year and 10 months to Oct 2020, and that date has passed too

  • This projectRegistered 31 Aug 2017, completion promised 31 Dec 2018, revised to 30 Oct 2020, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700011381
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001138131 Aug 201731 Dec 201830 Oct 2020Avni CorporationProject page
Documents35

2 documents held by Deedo, 33 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN Cardaffidavit of jigar patel.pdf · uploaded 30 Jul 2017Source

Legal

  • Declaration Form Baffidavit of jigar patel.pdf · uploaded 28 Jul 2017Source
  • Legal Title reportTITLE CERTIFICATE compressed.pdf · uploaded 30 Jul 2017Source

Migrated

  • 1 Details of encumbrancesno encumbrance declaration scan.pdf · uploaded 28 Jul 2017Source
  • 1 Declaration in FORM Baffidavit of jigar patel.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE SCAN.pdf · uploaded 28 Jul 2017Source
Show all 35 documentsShow fewer documents

Migrated

  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate merged.pdf · uploaded 28 Jul 2017Source
  • 1 Proforma of Allotment letterProvisional allotment letter-master file.pdf · uploaded 28 Jul 2017Source
  • 1 Building Plan Approval (IOD)Commencement_Certificate 1.pdf · uploaded 29 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement_Certificate 1.pdf · uploaded 29 Jul 2017Source
  • 1 PAN Cardaffidavit of jigar patel.pdf · uploaded 30 Jul 2017Source
  • 1 Copy of the legal title reportTITLE CERTIFICATE compressed.pdf · uploaded 30 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT MERGED COMPRESSED.pdf · uploaded 30 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA certificate avni.pdf · uploaded 30 Jul 2017Source
  • 2 Proforma of Allotment letterrera avni final.pdf · uploaded 30 Jul 2017Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 15-04-2018.pdf · uploaded 10 Apr 2023Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 20-04-2019.pdf · uploaded 10 Apr 2023Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2-15-4-18.pdf · uploaded 10 Apr 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 20-4-19.pdf · uploaded 10 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Form 5 avni corporation17-18.pdf · uploaded 10 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 avni corporation 18-19.pdf · uploaded 10 Apr 2023Source
  • 2 Certificates of CA (Form 3)Form 3 2017-18.pdf · uploaded 11 Apr 2023Source
  • 3 Certificates of CA (Form 3)Form 3 2018-19.pdf · uploaded 11 Apr 2023Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)AVNI CORP - SOCIETY FORMATION CERTIFICATE.pdf · uploaded 11 Apr 2023Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 13 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 avni corporation 19-20.pdf · uploaded 13 Apr 2023Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 18 Apr 2023Source
  • 4 Certificates of CA (Form 3)Form 3 2019-20.pdf · uploaded 18 Apr 2023Source
  • 1 Status of ConveyanceAdobe Scan 21-Apr-2023 (1)-1-27-12-27_compressed (1).pdf · uploaded 24 Apr 2023Source

Technical

  • DocumentCommencement_Certificate 1.pdf · uploaded 29 Jul 2017Source
  • DocumentLAYOUT MERGED COMPRESSED.pdf · uploaded 30 Jul 2017Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 18 Apr 2023Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 13 Apr 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel SURVEY NO 54 HISSA NO 1 PT 54 1B, SURVEY NO 54 HISSA NO 1 PT 54 1B

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1 BHK, 1BHK, 2 BHK, Office, Shop52 units in all
Address
Survey No 54 Hissa No 1 Pt 54 1bPIN 421301
Village
Kalyan-Dombivali (M Corp.), Kalyan taluka
Designated bank account
212
Developed in phases
No

Survey, CTS, gat or plot numbers

SURVEY NO 54 HISSA NO 1 PT 54 1BSURVEY NO 54 HISSA NO 1 PT 54 1B

Boundaries

North
Adharwadi Chowk
South
Lalchowki
East
Ramabai Ambedkar Chawl
West
Santosh Chs Ltd

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking52 units

52 of 52 units booked (100%), as the promoter reported to MahaRERA

1 BHK · 3 units1BHK · 4 units2 BHK · 42 unitsOffice · 2 unitsShop · 1 unit
TypeCarpet areaUnitsBooked
1 BHK37.62 sq m · 405 sq ft11
1 BHK38.04 sq m · 409 sq ft11
1 BHK38.58 sq m · 415 sq ft11
1BHK36.8 sq m · 396 sq ft22
1BHK36.82 sq m · 396 sq ft11
1BHK38.26 sq m · 412 sq ft11
2 BHK47.14 sq m · 507 sq ft66
2 BHK47.31 sq m · 509 sq ft33
Show all 23 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2 BHK47.34 sq m · 510 sq ft22
2 BHK47.39 sq m · 510 sq ft77
2 BHK47.79 sq m · 514 sq ft55
2 BHK47.81 sq m · 515 sq ft11
2 BHK49.66 sq m · 535 sq ft33
2 BHK49.91 sq m · 537 sq ft44
2 BHK49.93 sq m · 537 sq ft11
2 BHK51.1 sq m · 550 sq ft33
2 BHK51.12 sq m · 550 sq ft11
2 BHK51.57 sq m · 555 sq ft44
2 BHK51.59 sq m · 555 sq ft11
2 BHK56.9 sq m · 612 sq ft11
Office49.52 sq m · 533 sq ft11
Office72.89 sq m · 785 sq ft11
Shop49.79 sq m · 536 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals7

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVerghese John—
EngineerSurendra Velji Patel—
OtherAsha Lakshaman Rathod—
OtherBabu V. Parmar—
OtherNitesh Ratilal Patel—
OtherSachin Rishikant Shete—
OtherVinod Ravilal Patel—

Source: MahaRERA project page. Contact details are not shown.