Skip to content
Residential / Group Housing · 1 building · 15 unitsRERA P51700029720

Sairaj

Deedo IDDP-THN-0PA0

Its promised completion date, Mar 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Ghansoli, Thane 400701 · by Tukaram Jadhav Agaskar

Delivery3 yrs 8 mo past duePromised Mar 2023 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 15 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Mar 2023, has passed and MahaRERA does not show it completed

  • This projectRegistered 26 Jun 2021, completion promised 25 Mar 2023, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700029720
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002972026 Jun 202125 Mar 202325 Mar 2023Tukaram Jadhav AgaskarProject page
Documents31

1 document held by Deedo, 30 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card.pdf · uploaded 5 Jun 2021Source

Legal

  • OtherSearch Report comp.pdf · uploaded 5 Jun 2021Source
  • Legal Title reportlegal title report 1.pdf · uploaded 5 Jun 2021Source
  • Declaration Form BForm B Developers.pdf · uploaded 11 Jun 2021Source
  • Declaration Form BForm B Landowner.pdf · uploaded 11 Jun 2021Source
  • Legal Title reportlegal title report 2.pdf · uploaded 14 Jun 2021Source

Migrated

  • 1 PAN CardPan Card.pdf · uploaded 5 Jun 2021Source
Show all 31 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportlegal title report 1.pdf · uploaded 5 Jun 2021Source
  • 1 Details of encumbrancesForm B 8 comp.pdf · uploaded 5 Jun 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC copy comp.pdf · uploaded 5 Jun 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA form 1.pdf · uploaded 5 Jun 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer certificate 1-converted-compressed.pdf · uploaded 5 Jun 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 scan copy.pdf · uploaded 5 Jun 2021Source
  • 1 Proforma of Allotment letterAgreement for sale.pdf · uploaded 5 Jun 2021Source
  • 2 Proforma of Allotment letterallotments letter.pdf · uploaded 5 Jun 2021Source
  • 1 Status of ConveyanceCIDCO Agreement 1.pdf · uploaded 5 Jun 2021Source
  • 2 Status of ConveyanceCIDCO Agreement 2.pdf · uploaded 5 Jun 2021Source
  • 3 Status of ConveyanceCIDCO Agreement 3.pdf · uploaded 5 Jun 2021Source
  • 4 Status of ConveyanceCIDCO Agreement 4.pdf · uploaded 5 Jun 2021Source
  • 5 Status of ConveyancePlot CIDCO Transfer NOC comp.pdf · uploaded 5 Jun 2021Source
  • 1 OtherSearch Report comp.pdf · uploaded 5 Jun 2021Source
  • 1 Copy of Layout Approval (in case of layout)Lay Out and Building Plan.pdf · uploaded 11 Jun 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentLay Out and Building Plan.pdf · uploaded 11 Jun 2021Source
  • 1 Declaration in FORM BForm B Developers.pdf · uploaded 11 Jun 2021Source
  • 2 Declaration in FORM BForm B Landowner.pdf · uploaded 11 Jun 2021Source
  • 2 Copy of the legal title reportlegal title report 2.pdf · uploaded 14 Jun 2021Source

Technical

  • DocumentLay Out and Building Plan.pdf · uploaded 11 Jun 2021Source
  • DocumentLay Out and Building Plan.pdf · uploaded 11 Jun 2021Source

Technical (Architect)

  • DocumentRERA form 1.pdf · uploaded 5 Jun 2021Source

Technical (Engineer)

  • DocumentForm 2 Engineer certificate 1-converted-compressed.pdf · uploaded 5 Jun 2021Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 150

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 2BHK15 units in all
Address
150, Sec - 21, GhansoliPIN 400701
Village
Navi Mumbai (M Corp.), Thane taluka
Land area for this project
250 sq m (2,691 sq ft)
Permissible built-up area
374 sq m (4,030 sq ft)
Sanctioned built-up area
374 sq m (4,030 sq ft)
Recreational open space
250 sq m (2,691 sq ft)
Designated bank account
148
Developed in phases
No

Survey, CTS, gat or plot numbers

150

Land as published on MahaRERA's project page

150

Boundaries

North
Plot No 151
South
Plot No 149
East
11 Mtr Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking15 units

0 of 15 units booked (0%), as the promoter reported to MahaRERA

1BHK · 7 units1RK · 7 units2BHK · 1 unit
TypeCarpet areaUnitsBooked
1BHK28.24 sq m · 304 sq ft70
1RK18.74 sq m · 202 sq ft70
2BHK45.53 sq m · 490 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAtul Patel Architects—
Chartered accountantCA Aman Bhatia—
EngineerB S Sukthankar And Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology