Century Two
Deedo IDDP-THN-14J3Completion was pushed back 4 months, to Jul 2028; no MahaRERA orders on record; 39% of its units are booked.
Ghansoli, Thane 400701 · by City Infra
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Jul 2028
- This projectRegistered 10 Oct 2023, completion promised 31 Mar 2028, revised to 31 Jul 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700053044
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700053044 | 10 Oct 2023 | 31 Mar 2028 | 31 Jul 2028 | City Infra | Project page |
Documents120
1 document held by Deedo, 119 filings listed on MahaRERA's project page
Finance
- PAN Cardpan card of company.pdf · uploaded 17 Jun 2023Source
Legal
Migrated
- 1 PAN Cardpan card of company.pdf · uploaded 17 Jun 2023Source
- 1 Copy of the legal title reportLEGAL TITLE REPORT.pdf · uploaded 17 Jun 2023Source
- 1 a Details of encumbrances concerned to FinanceLEETER OF ENCUMBRANCE FIANANCE N LEGAL.pdf · uploaded 17 Jun 2023Source
- 1 b Details of encumbrances concerned to LegalLEETER OF ENCUMBRANCE FIANANCE N LEGAL.pdf · uploaded 17 Jun 2023Source
Show all 120 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN 1.pdf · uploaded 17 Jun 2023Source
- 2 Copy of Layout Approval (in case of layout)LAYOUT PLAN 2.pdf · uploaded 17 Jun 2023Source
- 3 Copy of Layout Approval (in case of layout)LAYOUT PLAN 3.pdf · uploaded 17 Jun 2023Source
- 4 Copy of Layout Approval (in case of layout)LAYOUT PLAN 4.pdf · uploaded 17 Jun 2023Source
- 5 Copy of Layout Approval (in case of layout)LAYOUT PLAN 5.pdf · uploaded 17 Jun 2023Source
- 6 Copy of Layout Approval (in case of layout)LAYOUT PLAN 6.pdf · uploaded 17 Jun 2023Source
- 7 Copy of Layout Approval (in case of layout)LAYOUT PLAN 7.pdf · uploaded 17 Jun 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentLAYOUT PLAN 8.pdf · uploaded 17 Jun 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCC COPY.pdf · uploaded 17 Jun 2023Source
- 1 Declaration about Commencement CertificateDECLARATION OF CC.pdf · uploaded 17 Jun 2023Source
- 1 Declaration in FORM BForm-B.pdf · uploaded 17 Jun 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 17 Jun 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 17 Jun 2023Source
- 1 CERSAI detailsCersai report n undertake.pdf · uploaded 17 Jun 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3.pdf · uploaded 17 Jun 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOUSER OF INTEREST IN OTHER ORAGAN.pdf · uploaded 17 Jun 2023Source
- 1 Proforma of Agreement for saleFINAL DRAFT AGREEMENT FOR SALE.pdf · uploaded 17 Jun 2023Source
- 1 Proforma of Allotment letterFINAL ALLOTMENT LETTER.pdf · uploaded 17 Jun 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDECLARATION OF SEPERATE BANK.pdf · uploaded 17 Jun 2023Source
- 1 Deviation Report with respect to Allotment letterDEVIATION OF ALLOTMENT LETTER.pdf · uploaded 17 Jun 2023Source
- 1 Deviation Report with respect to model copy of AgreementDEVIATION OF AFS.pdf · uploaded 17 Jun 2023Source
- 2 CERSAI detailsLetter for cersai.pdf · uploaded 18 Jul 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 22 Jan 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 22 Jan 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 with sign.pdf · uploaded 30 Jan 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentRevised CC.pdf · uploaded 7 May 2024Source
- 2 Declaration about Commencement CertificateDeclaration of CC.pdf · uploaded 7 May 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P no - 22, S- 09, Form 1.pdf · uploaded 7 May 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 7 May 2024Source
- 1 Disclosure of sold/ booked inventoryInventory Sold Letter.pdf · uploaded 7 May 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 11zon.pdf · uploaded 7 May 2024Source
- 8 Copy of Layout Approval (in case of layout)Layout plan-1-2.pdf · uploaded 29 May 2024Source
- 9 Copy of Layout Approval (in case of layout)Layout plan-3 -4.pdf · uploaded 29 May 2024Source
- 10 Copy of Layout Approval (in case of layout)Layout plan-5 -6.pdf · uploaded 29 May 2024Source
- 11 Copy of Layout Approval (in case of layout)Layout plan-7.pdf · uploaded 29 May 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentLayout plan-8- 9.pdf · uploaded 29 May 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_.pdf · uploaded 19 Oct 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_.pdf · uploaded 19 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Final FORM 5.pdf · uploaded 21 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Final Form 1.pdf · uploaded 12 Feb 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Final Form 1.pdf · uploaded 12 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 12 Feb 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 12 Feb 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 12 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Final Form 2.pdf · uploaded 12 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Final Form 2.pdf · uploaded 12 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FInal FORM 1.pdf · uploaded 18 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final FORM 3.pdf · uploaded 18 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Final FORM 2.pdf · uploaded 18 Apr 2025Source
- Form 1Form 1.pdf · uploaded 20 May 2025Source
- Form 2Form 2.pdf · uploaded 20 May 2025Source
- Form 3form 3 with sign.pdf · uploaded 20 May 2025Source
- Form 1Form 1.pdf · uploaded 20 May 2025Source
- Form 2Form 2.pdf · uploaded 20 May 2025Source
- Form 3form 3 with sign.pdf · uploaded 20 May 2025Source
- Form 1Form 1.pdf · uploaded 20 May 2025Source
- Form 2form 3 with sign.pdf · uploaded 20 May 2025Source
- Form 3Form 2.pdf · uploaded 20 May 2025Source
- Form 1Form 1.pdf · uploaded 20 May 2025Source
- Form 2form 3 with sign.pdf · uploaded 20 May 2025Source
- Form 3Form 2.pdf · uploaded 20 May 2025Source
- Form 1Form 1.pdf · uploaded 20 May 2025Source
- Form 2form 3 with sign.pdf · uploaded 20 May 2025Source
- Form 3Form 2.pdf · uploaded 20 May 2025Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 28 Jul 2025Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 28 Jul 2025Source
- Withdrawal Update Form 3FORM 3 for Q1 (Century two) (1).pdf · uploaded 28 Jul 2025Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 19 Aug 2025Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 19 Aug 2025Source
- Withdrawal Update Form 3FORM 3 for Q1 (Century two) (1).pdf · uploaded 19 Aug 2025Source
- Form 5 (FY 2024-2025)Form-5 final.pdf · uploaded 30 Sep 2025Source
- Withdrawal Update Form 1Form 1 Q2 2025..pdf · uploaded 18 Oct 2025Source
- Withdrawal Update Form 1Form 1 Q2 2025..pdf · uploaded 18 Oct 2025Source
- Withdrawal Update Form 1Form 1 Q2 2025..pdf · uploaded 18 Oct 2025Source
- Withdrawal Update Form 2Form 2 Q2 2025..pdf · uploaded 18 Oct 2025Source
- Withdrawal Update Form 2Form 2 Q2 2025..pdf · uploaded 18 Oct 2025Source
- Withdrawal Update Form 2Form 2 Q2 2025..pdf · uploaded 18 Oct 2025Source
- Withdrawal Update Form 3Form-3 Q2 2025..pdf · uploaded 18 Oct 2025Source
- Withdrawal Update Form 3Form-3 Q2 2025..pdf · uploaded 18 Oct 2025Source
- Withdrawal Update Form 3Form-3 Q2 2025..pdf · uploaded 18 Oct 2025Source
- Withdrawal Update Form 1FORM1 Q3 25-26.pdf · uploaded 22 Jan 2026Source
- Withdrawal Update Form 2FORM2 Q3 25-26.pdf · uploaded 22 Jan 2026Source
- Withdrawal Update Form 3FORM3 Q3 25-26.pdf · uploaded 22 Jan 2026Source
- Withdrawal Update Form 1Form 1 Q4 2025-2026.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 2Form 2 Q4 2025-2026.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 3Form 3 Q4 2025-2026..pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 1Form 1 Q1 26-27.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2Form 2 Q1 26-27.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3Form 3 Q1 26-27.pdf · uploaded 20 Jul 2026Source
Technical
- DocumentLAYOUT PLAN 1.pdf · uploaded 17 Jun 2023Source
- DocumentLAYOUT PLAN 2.pdf · uploaded 17 Jun 2023Source
- DocumentLAYOUT PLAN 3.pdf · uploaded 17 Jun 2023Source
- DocumentLAYOUT PLAN 4.pdf · uploaded 17 Jun 2023Source
- DocumentLAYOUT PLAN 5.pdf · uploaded 17 Jun 2023Source
- DocumentLAYOUT PLAN 6.pdf · uploaded 17 Jun 2023Source
- DocumentLAYOUT PLAN 7.pdf · uploaded 17 Jun 2023Source
- DocumentLAYOUT PLAN 8.pdf · uploaded 17 Jun 2023Source
- DocumentLayout plan-1-2.pdf · uploaded 29 May 2024Source
- DocumentLayout plan-8- 9.pdf · uploaded 29 May 2024Source
- DocumentLayout plan-3 -4.pdf · uploaded 29 May 2024Source
- DocumentLayout plan-5 -6.pdf · uploaded 29 May 2024Source
- DocumentLayout plan-7.pdf · uploaded 29 May 2024Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel PLOT NO 22, SECTOR09
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK, Nursing room, Shop152 units in all
- Address
- Plot No 22, Sector-09, Plot No-22, Sector 9, GhansoliPIN 400701
- Village
- Navi Mumbai (M Corp.), Thane taluka
- Land area for this project
- 2,649 sq m (28,511 sq ft)
- Permissible built-up area
- 13,835 sq m (1,48,923 sq ft)
- Sanctioned built-up area
- 13,835 sq m (1,48,923 sq ft)
- Designated bank account
- 86
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PLOT NO 22,SECTOR-09
Boundaries
- North
- Plot No 19
- South
- 24 00 Mtr Wide Road
- East
- Plot No 23
- West
- Plot No 20
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking152 units
60 of 152 units booked (39%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 58.35 sq m · 628 sq ft | 70 | 25 |
| 2BHK | 61.82 sq m · 665 sq ft | 35 | 13 |
| 3BHK | 79.2 sq m · 853 sq ft | 35 | 15 |
| Nursing room | 191.24 sq m · 2,058 sq ft | 1 | 1 |
| Nursing room | 221.62 sq m · 2,385 sq ft | 1 | 1 |
| Shop | 17.07 sq m · 184 sq ft | 1 | 0 |
| Shop | 36.78 sq m · 396 sq ft | 1 | 0 |
| Shop | 38.77 sq m · 417 sq ft | 1 | 0 |
Show all 15 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 42.3 sq m · 455 sq ft | 1 | 1 |
| Shop | 44.68 sq m · 481 sq ft | 1 | 1 |
| Shop | 47.71 sq m · 514 sq ft | 1 | 1 |
| Shop | 49.99 sq m · 538 sq ft | 1 | 0 |
| Shop | 50.5 sq m · 544 sq ft | 1 | 0 |
| Shop | 56.04 sq m · 603 sq ft | 1 | 1 |
| Shop | 67.93 sq m · 731 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vastospati Design Group | — |
| Chartered accountant | H M Shah & Associates | — |
| Engineer | Agharkar Consultants | — |
Source: MahaRERA project page. Contact details are not shown.