Yashomangal
Deedo IDDP-THN-C3ERCompletion was pushed back 4 months, to Dec 2027; no MahaRERA orders on record; 0% of its units are booked.
Dombivli, Thane 421201 · Promoter: Fore Holdings
Completion was pushed back 4 months, to Dec 2027
- This projectRegistered 3 Mar 2025, completion promised 30 Aug 2027, revised to 30 Dec 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700079392
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700079392 | 3 Mar 2025 | 30 Aug 2027 | 30 Dec 2027 | Fore Holdings | Project page |
Documents55
1 document held by Deedo, 54 filings listed on MahaRERA's project page
Finance
Legal
Show all 55 documentsShow fewer documents
Migrated
- 1 Proforma of Allotment letterALLOTMENT LETTER - YASHOMANGAL.pdf · uploaded 23 Jan 2025Source
- 1 Declaration in FORM BFORM B PROMOTER 150225.pdf · uploaded 23 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECH CERTIFICATE.pdf · uploaded 23 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA.pdf · uploaded 23 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.pdf · uploaded 23 Jan 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentYASHOMANGAL COMMENCEMENT CERTIFICATE 21-01-2025_compressed.pdf · uploaded 23 Jan 2025Source
- 1 Building Plan Approval / NA Order for plotted development1 Commencement Certificates _ NA Order for plotted development (2).pdf · uploaded 23 Jan 2025Source
- 1 Declaration about Commencement CertificateDECLERATION OF CC.pdf · uploaded 23 Jan 2025Source
- 1 CERSAI detailsCERSAI LETTER.pdf · uploaded 23 Jan 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT A (5).pdf · uploaded 23 Jan 2025Source
- 1 Deviation Report with respect to Allotment letterNO DEVIATION IN ALLOTMENT FOR SALE.pdf · uploaded 23 Jan 2025Source
- 1 b Details of encumbrances concerned to LegalLEGAL AND FINANCE.pdf · uploaded 23 Jan 2025Source
- 1 Other – FinanceCLARIFICATION REGARDING INVENTORY BY PROMOTER.pdf · uploaded 23 Jan 2025Source
- 1 Deviation Report with respect to model copy of AgreementNO DEVIATION IN AGREEMENT FOR SALE.pdf · uploaded 23 Jan 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Of Intrest About Organisation In Real Estate.pdf · uploaded 23 Jan 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Kotak Bank Certificate-New.pdf · uploaded 23 Jan 2025Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure of secured unsecured finance availed for the project 15-01-25.pdf · uploaded 23 Jan 2025Source
- 2 Building Plan Approval / NA Order for plotted development1 Copy of Layout Approval (in case of layout) (4).pdf · uploaded 6 Feb 2025Source
- 1 Other – TechnicalDECLARATION CUM-UNDERTAKING.pdf · uploaded 6 Feb 2025Source
- 1 Proforma of Agreement for saleMODEL DRAFT RERA AGREEMENT - YASHOMANGAL.pdf · uploaded 6 Feb 2025Source
- 1 Copy of the legal title reportLEGAL TITLE AND SEARCH REPORT.pdf · uploaded 7 Feb 2025Source
- Form 1FORM 1.pdf · uploaded 6 Jun 2026Source
- Form 2FORM 2.pdf · uploaded 6 Jun 2026Source
- Form 3FORM 3.pdf · uploaded 6 Jun 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold and Unsold.pdf · uploaded 6 Jun 2026Source
- Form 1FORM 1 - 30-06-2025.pdf · uploaded 17 Jun 2026Source
- Form 2FORM 2 - 30-06-2025.pdf · uploaded 17 Jun 2026Source
- Form 3FORM 3 - 30-06-2025.pdf · uploaded 17 Jun 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD AND UNSOLD - 30-06-2025.pdf · uploaded 17 Jun 2026Source
- Form 1FORM 1.pdf · uploaded 18 Jun 2026Source
- Form 2FORM 2.pdf · uploaded 18 Jun 2026Source
- Form 3FORM 3.pdf · uploaded 18 Jun 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD AND UNSOLD.pdf · uploaded 18 Jun 2026Source
- Form 1FORM 1.pdf · uploaded 18 Jun 2026Source
- Form 2FORM 2.pdf · uploaded 18 Jun 2026Source
- Form 3FORM 3.pdf · uploaded 18 Jun 2026Source
- Disclosure of Sold and Booked InventoryDISLCOSURE OF SOLD AND UNSOLD.pdf · uploaded 18 Jun 2026Source
- Form 1FORM 1 - 31-03-2026.pdf · uploaded 31 Jul 2026Source
- Form 2FORM 2 - 31-03-2026.pdf · uploaded 31 Jul 2026Source
- Form 3FORM 3 - 27-07-2026.pdf · uploaded 31 Jul 2026Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD AND UNSOLD.pdf · uploaded 31 Jul 2026Source
Technical
- DocumentYASHOMANGAL SANCTION PLAN KDMCC HIGHLIGHTED.pdf · uploaded 23 Jan 2025Source
- Document1 Commencement Certificates _ NA Order for plotted development (2).pdf · uploaded 23 Jan 2025Source
- Document1 Copy of Layout Approval (in case of layout) (4).pdf · uploaded 6 Feb 2025Source
- Other – TechnicalDECLARATION CUM-UNDERTAKING.pdf · uploaded 6 Feb 2025Source
Technical (Architect)
- DocumentARCHITECH CERTIFICATE.pdf · uploaded 23 Jan 2025Source
Technical (Engineer)
- DocumentForm 2 Engineer Certificate.pdf · uploaded 23 Jan 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals4370/A/1/C
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- REAHB 2BHK, REHAB 2BHK, SALE 2BHK28 units in all
- Address
- 4370/A/1/C, Nehru Road, Near Tulsi Garden, Behind Jalaram Mandir, Thakurli East, DombivliPIN 421201
- Village
- Dombivli, Kalyan taluka
- Designated bank account
- 109
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Property Cts No 4370-A-1-D
- South
- Property Cts No 4370-A-1-B
- East
- Property Of Cts No 1273
- West
- 9 M Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking28 units
0 of 28 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| REAHB 2BHK | 60.2 sq m · 648 sq ft | 4 | 0 |
| REHAB 2BHK | 53.67 sq m · 578 sq ft | 4 | 0 |
| REHAB 2BHK | 55.09 sq m · 593 sq ft | 2 | 0 |
| REHAB 2BHK | 59.89 sq m · 645 sq ft | 4 | 0 |
| SALE 2BHK | 53.67 sq m · 578 sq ft | 3 | 0 |
| SALE 2BHK | 55.09 sq m · 593 sq ft | 5 | 0 |
| SALE 2BHK | 59.89 sq m · 645 sq ft | 3 | 0 |
| SALE 2BHK | 60.2 sq m · 648 sq ft | 3 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ninad Mhaskar | — |
| Chartered accountant | Godse And Associates | — |
| Engineer | Manihar Patil And Associates | — |
Source: MahaRERA project page. Contact details are not shown.