Completion was pushed back 4 months, to Jul 2029; no MahaRERA orders on record; 0% of its units are booked.

Dombivli, Thane 421201 · by Aditya Buildcon · 67% of its projects kept the RERA date

DeliveryExtended 4 moPromised Mar 2029 · now due Jul 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 26 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jul 2029

  • This projectRegistered 6 Mar 2025, completion promised 31 Mar 2029, revised to 31 Jul 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700079448
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000794486 Mar 202531 Mar 202931 Jul 2029Aditya BuildconProject page
Documents79

1 document held by Deedo, 78 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN OF ADITYA BUILDCON.pdf · uploaded 5 Feb 2025Source
  • Other – FinanceClarification letter Land cost.pdf · uploaded 5 Feb 2025Source

Legal

  • Legal Title reportUpdated Title Report of swachhand CHS _Rera.pdf · uploaded 5 Feb 2025Source
  • Legal Title reportLatest search report of Swachhand.pdf · uploaded 5 Feb 2025Source
  • Declaration Form BSwachhand Form B Developer.pdf · uploaded 26 Feb 2025Source

Migrated

  • 1 PAN CardPAN OF ADITYA BUILDCON.pdf · uploaded 5 Feb 2025Source
  • 1 Copy of the legal title reportUpdated Title Report of swachhand CHS _Rera.pdf · uploaded 5 Feb 2025Source
Show all 79 documentsShow fewer documents

Migrated

  • 2 Copy of the legal title reportLatest search report of Swachhand.pdf · uploaded 5 Feb 2025Source
  • 1 a Details of encumbrances concerned to FinanceDetails of encumbrances to Finance.pdf · uploaded 5 Feb 2025Source
  • 2 a Details of encumbrances concerned to FinanceDetails of encumbraces to Legal.pdf · uploaded 5 Feb 2025Source
  • 1 Copy of Layout Approval (in case of layout)Rera Sanctiond plan 2.pdf · uploaded 5 Feb 2025Source
  • 1 Proforma of Allotment letterAllottment letter sign copy.pdf · uploaded 5 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 01.pdf · uploaded 5 Feb 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement certf of Swachhand.pdf · uploaded 5 Feb 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentRera Sanctiond plan 2.pdf · uploaded 5 Feb 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentRera Sanctioned Plan.pdf · uploaded 5 Feb 2025Source
  • 1 Declaration about Commencement CertificateDeclaration about commencement certf.pdf · uploaded 5 Feb 2025Source
  • 1 CERSAI detailsUndertaking for CERSAI.pdf · uploaded 5 Feb 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Declaration about RERA Disgnated bank.pdf · uploaded 5 Feb 2025Source
  • 1 Deviation Report with respect to Allotment letterDeviation of Allottment letter.pdf · uploaded 5 Feb 2025Source
  • 1 b Details of encumbrances concerned to LegalDetails of encumbrances to Finance.pdf · uploaded 5 Feb 2025Source
  • 2 b Details of encumbrances concerned to LegalDetails of encumbraces to Legal.pdf · uploaded 5 Feb 2025Source
  • 1 Other – FinanceClarification letter Land cost.pdf · uploaded 5 Feb 2025Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation for AFS.pdf · uploaded 5 Feb 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclouser of Real Estate.pdf · uploaded 5 Feb 2025Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclouser of Real Estate 2.pdf · uploaded 5 Feb 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B from Bank.pdf · uploaded 5 Feb 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclouser secured unsecured fin.pdf · uploaded 5 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE SIGNED COPY.pdf · uploaded 15 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng-New25.pdf · uploaded 15 Feb 2025Source
  • 1 Proforma of Agreement for saleDraft Agreement For Sale-Swachhand Chs Ltd.pdf · uploaded 15 Feb 2025Source
  • 1 Declaration in FORM BSwachhand Form B Developer.pdf · uploaded 26 Feb 2025Source
  • 1 Other – TechnicalCC Confirmation.pdf · uploaded 26 Feb 2025Source
  • 2 Other – TechnicalOne Plot One Registration.pdf · uploaded 26 Feb 2025Source
  • Form 1Architect Certificate.pdf · uploaded 12 Jun 2025Source
  • Form 2Engineer Certificate.pdf · uploaded 12 Jun 2025Source
  • Form 3CA Certificate.pdf · uploaded 12 Jun 2025Source
  • Disclosure of Sold and Booked InventorySold Unsod disclosure.pdf · uploaded 12 Jun 2025Source
  • Self-declaration of Quarterly ProgressSold Unsod disclosure.pdf · uploaded 12 Jun 2025Source
  • Withdrawal Update Form 1Architect certificate - Swachhand CHS.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 2Engineeru0027s certificate - Swachhand CHS.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 3Form 03.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 1Architect certificate - Swachhand CHS.pdf · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 1Architect certificate - Swachhand CHS.pdf · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 1Architect certificate - Swachhand CHS.pdf · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 2Engineeru0027s certificate - Swachhand CHS.pdf · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 2Engineeru0027s certificate - Swachhand CHS.pdf · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 2Engineeru0027s certificate - Swachhand CHS.pdf · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 3Form 3 for Swachhand CHS.PDF · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 3Form 3 for Swachhand CHS.PDF · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 3Form 3 for Swachhand CHS.PDF · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 1Architect certificate - Swachhand CHS.pdf · uploaded 21 Jul 2025Source
  • Withdrawal Update Form 2Engineeru0027s certificate - Swachhand CHS.pdf · uploaded 21 Jul 2025Source
  • Withdrawal Update Form 3Form 3 for Swachhand CHS.PDF · uploaded 21 Jul 2025Source
  • Form 5 (FY 2024-2025)Form 5 Swachhand - Signed (1).pdf · uploaded 7 Oct 2025Source
  • Withdrawal Update Form 1Architect Certificate of Swachhand CHS.pdf · uploaded 1 Nov 2025Source
  • Withdrawal Update Form 2Engr certificate of Swachhand Revised.pdf · uploaded 1 Nov 2025Source
  • Withdrawal Update Form 3CA- Certificate - Swachhand CHS..pdf · uploaded 1 Nov 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 29 Jan 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 29 Jan 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 29 Jan 2026Source
  • Withdrawal Update Form 1Rera Architect certf of Swachhhand 31 Mar 26.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 1Rera Architect certf of Swachhhand 31 Mar 26.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 2Engr certifcate March 26.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 2Engineer Certificate June 26.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 3CA certificate March 26.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 3Form 3 June26.pdf · uploaded 27 Jul 2026Source
  • Form 2A (FY 2025-2026)Form 2 2025-26.pdf · uploaded 29 Jul 2026Source
  • Form 5 (FY 2025-2026)Swachhand -Form 5 - FY 2025-26 SIGNED.pdf · uploaded 27 Sep 2026Source

Technical

  • DocumentRera Sanctiond plan 2.pdf · uploaded 5 Feb 2025Source
  • DocumentRera Sanctiond plan 2.pdf · uploaded 5 Feb 2025Source
  • DocumentRera Sanctioned Plan.pdf · uploaded 5 Feb 2025Source
  • Other – TechnicalCC Confirmation.pdf · uploaded 26 Feb 2025Source
  • Other – TechnicalOne Plot One Registration.pdf · uploaded 26 Feb 2025Source
  • DocumentREVISED SANCTION PLAN.pdf · uploaded 19 Nov 2025Source
  • DocumentREVISED SANCTION PLAN.pdf · uploaded 20 Nov 2025Source

Technical (Architect)

  • DocumentRera Architect certf of Swachhhand 31 Mar 26.pdf · uploaded 27 Jul 2026Source

Technical (Engineer)

  • DocumentEngineer Certificate June 26.pdf · uploaded 27 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel C.T.S. No. 5261 at

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK Developer Share, 2BHK Existing Member26 units in all
Address
C.T.S. No. 5261 at Village Dombivli (New), Taluka Kalyan, District Thane - 421201, Chheda Road, Dombivli (New)PIN 421201
Village
Dombivli, Kalyan taluka
Designated bank account
21
Developed in phases
No

Survey, CTS, gat or plot numbers

C.T.S. No. 5261 at

Boundaries

North
By 12 Mtrs Wide D P Road
South
By Laxmi Apartment
East
By Access Road or Kailash Apartment
West
By Pitruchhaya Building

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking26 units

0 of 26 units booked (0%), as the promoter reported to MahaRERA

2BHK Developer Share · 6 units2BHK Existing Member · 20 units
TypeCarpet areaUnitsBooked
2BHK Developer Share32.08 sq m · 345 sq ft10
2BHK Developer Share50.34 sq m · 542 sq ft20
2BHK Developer Share53.04 sq m · 571 sq ft10
2BHK Developer Share61.37 sq m · 661 sq ft20
2BHK Existing Member42.62 sq m · 459 sq ft40
2BHK Existing Member43.01 sq m · 463 sq ft60
2BHK Existing Member65.95 sq m · 710 sq ft40
2BHK Existing Member66.58 sq m · 717 sq ft10
2BHK Existing Member67.75 sq m · 729 sq ft20
2BHK Existing Member69.63 sq m · 749 sq ft30

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals7

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSthapatya Nirman—
Chartered accountantNinad Ravi Konakanchi—
Chartered accountantPravin E Pise—
Chartered accountantSachin K. Mishra & Co—
Chartered accountantYogesh Suresh Parmar—
EngineerManohar Patil & Associates—
OtherMr. Kamalakar Lad—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology