Deedo IDDP-THN-JGRGCompletion was pushed back 4 years to May 2023, and that date has passed too; no MahaRERA orders on record; 0% of its units are booked.
Dombivli, Thane 421201 · Promoter: Kishor Ramchandra Kulkarni
Completion was pushed back 4 years to May 2023, and that date has passed too
- This projectRegistered 7 Oct 2017, completion promised 31 May 2019, revised to 30 May 2023, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700013478
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700013478 | 7 Oct 2017 | 31 May 2019 | 30 May 2023 | Kishor Ramchandra Kulkarni | Project page |
Documents36
2 documents held by Deedo, 34 filings listed on MahaRERA's project page
Finance
- PAN CardPan card pic kishor.pdf · uploaded 27 Sep 2017Source
Legal
Show all 36 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)Building plan approval.pdf · uploaded 27 Sep 2017Source
- 1 Building Plan Approval (IOD)Building plan approval.pdf · uploaded 27 Sep 2017Source
- 1 Declaration in FORM BForm B.pdf · uploaded 27 Sep 2017Source
- 1 Certificates of CA (Form 3)CA form 3.pdf · uploaded 27 Sep 2017Source
- 1 Proforma of Allotment letterAgt_for_Sale samruddhi02.pdf · uploaded 27 Sep 2017Source
- 2 Proforma of Allotment letterALLOTMENT_Letter.pdf · uploaded 27 Sep 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentNew Doc 2018-03-27.pdf · uploaded 27 Mar 2018Source
- 1 Certificates of CA (Form 5)Form 5(1).pdf · uploaded 10 May 2019Source
- 2 Certificates of CA (Form 5)Form 5 (2).pdf · uploaded 10 May 2019Source
- 3 Certificates of CA (Form 5)Form 5-com.pdf · uploaded 10 May 2019Source
- 2 Commencement Certificates / NA Order for plotted developmentR K Enterprises CC2.pdf · uploaded 13 Jan 2022Source
- 1 Declaration about Commencement CertificateDeclaration for CC.pdf · uploaded 13 Jan 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT'S CERTIFICATE30112021_compressed.pdf · uploaded 13 Jan 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)20220104_174_Engineers_Certificate.pdf · uploaded 13 Jan 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)20220104_174_Engineers_Certificate.pdf · uploaded 13 Jan 2022Source
- 1 Disclosure of sold/ booked inventoryInventory.pdf · uploaded 13 Jan 2022Source
- 2 Certificates of CA (Form 3)CA Certificate_compressed.pdf · uploaded 13 Jan 2022Source
- 1 CERSAI detailsSAMRUDDHI_Nardeco.pdf · uploaded 22 Jan 2022Source
- 2 Copy of Layout Approval (in case of layout)rera plan 02.pdf · uploaded 5 Dec 2022Source
- 3 Copy of Layout Approval (in case of layout)rera plan 01.pdf · uploaded 5 Dec 2022Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOc R K Enterprises.pdf · uploaded 5 Dec 2022Source
- 2 Architect’s Certificate on Completion of Project (Form 4)Form No 4 R K Enterprises.pdf · uploaded 5 Dec 2022Source
Technical
Technical (Architect)
- DocumentARCHITECT'S CERTIFICATE30112021_compressed.pdf · uploaded 13 Jan 2022Source
Technical (Engineer)
- Document20220104_174_Engineers_Certificate.pdf · uploaded 13 Jan 2022Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsSR No 59/6 Plot No 4
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2 BHK, Basement, Shop 1, Shop 2, Shop3, Shop419 units in all
- Address
- SR No 59/6 Plot No 4PIN 421201
- Village
- Dombivli, Kalyan taluka
- Location
- 19.23307, 73.08852
- Designated bank account
- 148
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Jai Sai Prasad Building
- South
- Road
- East
- Road
- West
- Plot No 3
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking19 units
0 of 19 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2 BHK | 55.44 sq m · 597 sq ft | 7 | 0 |
| 2 BHK | 62.46 sq m · 672 sq ft | 6 | 0 |
| 2 BHK | 65.81 sq m · 708 sq ft | 1 | 0 |
| Basement | 116.61 sq m · 1,255 sq ft | 1 | 0 |
| Shop 1 | 8.4 sq m · 90 sq ft | 1 | 0 |
| Shop 2 | 4.84 sq m · 52 sq ft | 1 | 0 |
| Shop3 | 15.42 sq m · 166 sq ft | 1 | 0 |
| Shop4 | 17.31 sq m · 186 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ankur Shetye | — |
| Engineer | Girish Marathe | — |
Source: MahaRERA project page. Contact details are not shown.