Sai Residency
Deedo IDDP-THN-7GMFIts promised completion date, Mar 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Dombivli, Thane 421201 · Promoter: Sai Sadan Builders And Developers
Its promised completion date, Mar 2023, has passed and MahaRERA does not show it completed
- This projectRegistered 28 Apr 2022, completion promised 31 Mar 2023, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700034749
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700034749 | 28 Apr 2022 | 31 Mar 2023 | 31 Mar 2023 | Sai Sadan Builders And Developers | Project page |
Documents16
1 document held by Deedo, 15 filings listed on MahaRERA's project page
Legal
Migrated
- 1 Copy of the legal title reportLEGAL TITILE CERTIFICATE.pdf · uploaded 25 Apr 2022Source
- 1 Details of encumbrancesNON ENCUMBRANCE CERTIFICATE.pdf · uploaded 25 Apr 2022Source
- 1 Copy of Layout Approval (in case of layout)PLAN COPY.pdf · uploaded 25 Apr 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentPLAN COPY.pdf · uploaded 25 Apr 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 25 Apr 2022Source
Show all 16 documentsShow fewer documents
Migrated
- 1 Declaration about Commencement CertificateCC DECLARATION.pdf · uploaded 25 Apr 2022Source
- 1 Declaration in FORM BFORMB_PROMOTOR.pdf · uploaded 25 Apr 2022Source
- 1 CERSAI detailsCERSAI.pdf · uploaded 25 Apr 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_updated_11zon (1).pdf · uploaded 25 Apr 2022Source
- 1 Proforma of Allotment letterALLOTMENT FORMAT.pdf · uploaded 25 Apr 2022Source
- 2 Proforma of Allotment letterAGREEMENT FOR SALE.pdf · uploaded 25 Apr 2022Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsHISSA NO. 1/6, SURVEY NO. 51
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, 2BHK22 units in all
- Address
- Survey No. 51, Hissa No. 1/6, Ayre Road, Near Swami Vivekanand VidyamandirPIN 421201
- Village
- Dombivli, Kalyan taluka
- Designated bank account
- 17
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Water Tank
- South
- Vijay Patil Bunglow
- East
- Nanasaheb Dharmadhikari Udyan
- West
- Ranjeet Patil Chawl
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking22 units
0 of 22 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 48.77 sq m · 525 sq ft | 7 | 0 |
| 1BHK | 51.56 sq m · 555 sq ft | 6 | 0 |
| 1RK | 33.44 sq m · 360 sq ft | 1 | 0 |
| 1RK | 36.23 sq m · 390 sq ft | 1 | 0 |
| 1RK | 37.07 sq m · 399 sq ft | 1 | 0 |
| 2BHK | 65.96 sq m · 710 sq ft | 6 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vastu Rachana | — |
Source: MahaRERA project page. Contact details are not shown.